FIRE-Final Inspection | 5/16/2006 | 5/17/2006 | 5/17/2006 | P | PASS |
Mike Jordan
|
|
|
chris; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
DOC - Permit Finaled | 5/17/2006 | 5/17/2006 | 5/17/2006 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Final | 5/17/2006 | 5/17/2006 | 5/17/2006 | P | PASS |
Mike Jordan
|
|
|
chris; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
BLD-Energy code compliance | 3/15/2006 | 3/16/2006 | 3/16/2006 | A | PASS |
Mike Jordan
|
|
|
Chris; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong
|
BLD-Framing/Rough-in | 3/15/2006 | 3/15/2006 | 3/15/2006 | P | NR |
Mike Jordan
|
|
|
Chris; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong. wip when on site. needs to reshedule.
|
BLD-Framing/Rough-in | 3/13/2006 | 3/14/2006 | 3/14/2006 | A | PASS |
Mike Jordan
|
|
|
Chris; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong. All framing issues have been resolved.
|
BLD-Framing/Rough-in | 3/10/2006 | 3/10/2006 | 3/10/2006 | P | FAIL |
Mike Jordan
|
|
|
Chris; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong. Complete lateral bracing and finish nailing off simpson hangars in garage. ok to insulate. c/n posted. No framing on detached garage.
|
Case Summary (BLD) | | | 3/10/2006 | | |
|
|
|
|
Case Summary (BLD) | | | 3/10/2006 | | |
|
|
|
|
Inspection Record Card- Bld | | | 3/10/2006 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 3/10/2006 | | DONE |
|
|
|
Added detached garage wording to permit. Detached garage already was in Approved building set of plans. Phoned Jack Frank (Electrical) and Mike Jordan (Structural). Placed a new Inspection card in Mike Jordans box and faxed new Permit paperwork to builder for jobsite. (SRZ)
|
BLD-Framing/Rough-in | 3/8/2006 | 3/9/2006 | 3/9/2006 | A | NR |
Mike Jordan
|
|
|
Chris; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong. Could not find truss engineering or approved plans on site for framing inspection.
|
BLD-Foundation | 11/22/2005 | 11/22/2005 | 11/22/2005 | A | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 11/22/2005 at 7:22:18 AM. Contact: ###-####.
|
BLD-Footing | 11/22/2005 | 11/22/2005 | 11/22/2005 | A | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 11/22/2005 at 7:20:48 AM. Contact: ###-####.
|
BLD-Footing | 11/17/2005 | 11/18/2005 | 11/18/2005 | A | PASS |
Mike Jordan
|
|
|
dane; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
|
Issue PAID IN FULL permit | | | 11/9/2005 | | DONE |
|
|
|
|
Plan assigned to (SRZ) | 10/31/2005 | 10/31/2005 | 11/1/2005 | | PASS |
|
|
|
11/1/2005 13:35:33 SRZ - activity updated through activity BLDA022 from case BLD05-02640.
|
Case Summary (BLD) | | | 11/1/2005 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/1/2005 | | DONE |
|
|
|
ONE SET RED-LINED.
|
Inspection Record Card- Bld | | | 11/1/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/1/2005 | | |
|
|
|
|
Telephone call | | | 11/1/2005 | | DONE |
|
|
|
called ###-#### and told Kelly that permit is ready and fees
|
Routing - PLAN CHECK | 10/20/2005 | | 11/1/2005 | | PASS |
|
|
|
|
Plan assigned to (SAM) | 9/20/2005 | 9/20/2005 | 10/31/2005 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 10/20/2005 | | 10/20/2005 | | PASS |
|
|
|
|
Routing - PLANNING | 10/20/2005 | | 10/20/2005 | | PASS |
|
|
|
|
Application received | | | 9/20/2005 | | |
|
|
|
|
Routing - PLANNING | 9/20/2005 | | 9/20/2005 | | FAIL |
|
|
|
No driveway shown to detached garage. Left message w/ applicant at 3:30p.m. today. CER
|