Third Notice BLD | 1/8/2007 | 1/8/2007 | 3/1/2007 | | DONE |
|
|
|
Second Notice has not been responded to.
|
Fee Review-notes | 9/21/2005 | 9/21/2005 | 2/6/2007 | | DONE |
|
|
|
|
Second Notice BLD | 9/25/2006 | 9/25/2006 | 1/8/2007 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | 8/17/2006 | 8/17/2006 | 9/25/2006 | | DONE |
Tom Arcoraci
|
|
|
|
First Notice | | 8/8/2006 | 8/25/2006 | | DONE |
|
|
|
|
BLD-Final | 8/16/2006 | 8/17/2006 | 8/17/2006 | A | PASS |
Tom Arcoraci
|
|
|
hc company; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley
|
DOC - Permit Finaled | 8/17/2006 | 8/17/2006 | 8/17/2006 | P | PASS |
Tom Arcoraci
|
|
|
|
Reopen Permit (ISS) | | | 8/16/2006 | | DONE |
|
|
|
m.meloy finaled the permit by mistake. I spoke to him about this. needs bld final insp
|
Permanent occupancy | | | 8/8/2006 | | PASS |
|
|
|
The applicant has provided a Shared Trash Enclosure Agreement that satisfies the trash requirements (in lieu of building the trash enclosure shown on the plans).
|
FIRE-Final Inspection | 7/13/2006 | 7/14/2006 | 7/14/2006 | A | PASS |
Troy Cobbley
|
|
|
Life safety finaled
|
FIRE-Final Inspection | 7/13/2006 | 7/13/2006 | 7/13/2006 | P | FAIL |
Troy Cobbley
|
|
|
Exit discharge lights did not work.
|
BLD-Conference | 6/2/2006 | 6/2/2006 | 6/2/2006 | P | PASS |
Jim Sly
|
|
|
daren - call prior to insp; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley
|
FIRE-Conference | 5/18/2006 | 5/19/2006 | 5/19/2006 | A | DONE |
Troy Cobbley
|
|
|
I went over life safety items with Darren. Needs address on both corners of the building and to test the exit discharge lighting when complete.
|
BLD-Framing/Rough-in | 2/16/2006 | 2/17/2006 | 2/17/2006 | P | PART |
Jim Sly
|
|
|
darin; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie Shear nailing OK...... Hold downs on exterior (of Ext) wall OK Retrofit HDs OK but need to be screwed to studs.......Epoxy inspected by special insp. Still working on draftstops.
|
BLD-Framing/Rough-in | 1/11/2006 | 1/12/2006 | 1/12/2006 | P | PART |
Jim Sly
|
|
|
re-bar inspection///pouring at 2:30 -- darren; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa Foot OK Pending MTI special insp, tests, and approvals
|
(F) Reprint permit | | | 12/22/2005 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 12/21/2005 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/31/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/31/2005 | | DONE |
|
|
|
|
Telephone call | | | 10/31/2005 | | DONE |
|
|
|
called ###-#### and left voicemessage for Anita that permit is ready and fees
|
Plan assigned to (JCM) | 9/22/2005 | 9/22/2005 | 10/27/2005 | | PASS |
|
|
|
10/27/2005 16:17:43 JCM - activity updated through activity BLDA022 from case BLD05-02650.
|
Routing - PLAN CHECK | 10/19/2005 | | 10/27/2005 | | PASS |
|
|
|
|
Routing - PLANNING Land Div | 10/27/2005 | | 10/27/2005 | | PASS |
|
|
|
Approved on Lot 2, Block 1 of LaSalle Subdivision. Final Plat of LaSalle Subdivision recorded on October 26, 2005.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/27/2005 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 10/27/2005 | | PASS |
|
|
|
Reviewed and approved resubmitte structural plans and calculations. JCM
|
Routing - PLAN CHECK | 10/27/2005 | | 10/27/2005 | | PASS |
|
|
|
|
Plan resubmittals received | | | 10/26/2005 | | DONE |
|
|
|
Received 2 review comments ,1 document transmittal, 1 letter to Wes Steele,& 4 copys of sheets A1.3,S-4,S-5,S-6 taken to John M.
|
Routing - FIRE | 9/30/2005 | | 10/19/2005 | | PASS |
|
|
|
|
1st review completed | | | 10/19/2005 | | FAIL |
|
|
|
failed planning land div.
|
Plan resubmittals requested | | | 10/6/2005 | | DONE |
|
|
|
Faxed the architect a copy of the comment list from the consulting structural engineer requesting revisions. JCM
|
Routing Off Site - STRUCTURAL | 9/22/2005 | | 10/6/2005 | | FAIL |
|
|
|
Called PDQ for pick up -- Received a faxed comment list from the consulting structural engineer requesting revisions. JCM
|
Routing - PLAN CHECK | 9/29/2005 | | 9/30/2005 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 9/29/2005 | | PASS |
|
|
|
Plans reviewed and approved as submitted. JCM
|
Routing - PLANNING | 9/27/2005 | | 9/29/2005 | | PASS |
|
|
|
DRH 05-00099 Sara S. Approved per DRH05-00099. The condition regarding the easement for the sidewalk shall be handled on the revised plat.
|
Routing - PLUMBING | 9/27/2005 | | 9/27/2005 | | PASS |
|
|
|
per plans and 2003 upc
|
Routing - Erosion and Sediment | 9/26/2005 | | 9/27/2005 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Routing - PUBLIC WORKS | 9/22/2005 | | 9/26/2005 | | PASS |
|
|
|
|
Routing - PLANNING Land Div | 9/22/2005 | | 9/22/2005 | | FAIL |
|
|
|
Do not issue building permit until Final Plat of LaSalle Subdivision is recorded. Lot 2, Block 1 of LaSalle Subdivision. Final Plat signed by Boise City Engineer on 9/18/05.
|
Plans ACCEPTED BY PLAN TECH | | | 9/22/2005 | | |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 9/22/2005 | | |
|
|
|
|
Application received | | | 9/21/2005 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/21/2005 | | DONE |
|
|
|
|