Fee Review-notes | 9/26/2005 | 9/26/2005 | 4/5/2007 | | DONE |
|
|
|
|
Third Notice BLD | 1/8/2007 | 1/8/2007 | 2/13/2007 | | DONE |
|
|
|
Second Notice has not been responded to.
|
Second Notice BLD | 9/25/2006 | 9/25/2006 | 1/8/2007 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 9/5/2006 | 9/25/2006 | | DONE |
|
|
|
|
Permanent Occupancy | | 9/5/2006 | 9/5/2006 | | DONE |
|
|
|
|
Permanent occupancy | | | 9/5/2006 | | DONE |
|
|
|
Perm. Occ. Cert. # 11198 issued 9-5-06 to Irish Auto Repair.
|
Temporary occupancy | | | 8/9/2006 | | DONE |
|
|
|
Temp. Occ. Cert. # 5423 issued 8-9-06 to Irish Auto Repair.
|
Code Occupancy Approval | 8/2/2006 | 8/2/2006 | 8/2/2006 | P | PASS |
Scott M.Brown
|
|
|
ALL IN AS REQUIRED AND FINAL SIGNED OFF 8-1-06
|
PubWorks Occupancy Approval | 7/25/2006 | 7/25/2006 | 7/25/2006 | | DONE |
|
|
|
|
BLD-Final | 7/20/2006 | 7/21/2006 | 7/21/2006 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 7/20/2006 at 9:15:04 PM. Contact: ###-####. OK for Temp Occ. OK to Perm... when Code enforce and Electr perms.......
|
BLD-Final | 7/19/2006 | 7/20/2006 | 7/20/2006 | P | FAIL |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 7/19/2006 at 4:06:23 PM. Contact: ###-####. Needs public works sign off and to install code compliant handrail.
|
FIRE-Final Inspection | 7/17/2006 | 7/18/2006 | 7/18/2006 | A | PASS |
Troy Cobbley
|
|
|
life safety finaled
|
FIRE-Final Inspection | 7/10/2006 | 7/11/2006 | 7/11/2006 | P | FAIL |
Troy Cobbley
|
|
|
Provide signage at the property entrance as discussed and provide the indicator at the lock on the main entrance/exit door.
|
BLD-Final | 7/10/2006 | 7/11/2006 | 7/11/2006 | P | NR |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 7/10/2006 at 8:09:06 PM. Contact: ###-####.needs code enforcement, public works and fire finals.
|
BLD-Other | 5/17/2006 | 5/18/2006 | 5/18/2006 | A | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 5/17/2006 at 2:56:23 PM. Contact: ###-####. Bldg framing insp, verified draftstop.
|
BLD-Conference | 5/11/2006 | 5/12/2006 | 5/12/2006 | A | PART |
Mike Jordan
|
|
|
Confirmed with Mike Jordan for 9:00 AM appt.; Phone #: ###-#### Internet Inspection Request from: misty evans. After meeting with architiect, and plan reveiw the S-1 and B occ. is not required to be seperated by 2hr. wall due to square footage being less than 10% in B occ. of total square footage.
|
BLD-Framing/Rough-in | 5/10/2006 | 5/11/2006 | 5/11/2006 | P | PART |
Mike Jordan
|
|
|
christi; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles. Compressor room not complete. rogg framing and mezz. ok. Noted 2hr seperation wall, Need wall assembly from architect, Putty pads required on steel boxes, Also need verification of UL listing on installed door frames, no tags present. Also need UL listings on penetrations for fire caulking from elec. All pending mech ri. Ok to one side walls.
|
BLD-Foundation | 3/9/2006 | 3/10/2006 | 3/10/2006 | A | PASS |
Mike Jordan
|
|
|
eric; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
|
BLD-Footing | 2/28/2006 | 3/1/2006 | 3/1/2006 | A | PART |
Mike Jordan
|
|
|
eric; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles. Perimeter footings. Contractor is getting special insp.
|
(F) Reprint permit | | | 1/27/2006 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 1/26/2006 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/20/2006 | | DONE |
|
|
|
|
Routing - FIRE | 1/13/2006 | | 1/19/2006 | | PASS |
|
|
|
See attached comments. Faxed to architect.
|
Routing - PLAN CHECK | 1/19/2006 | | 1/19/2006 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/19/2006 | | DONE |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 1/19/2006 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 1/19/2006 | | DONE |
|
|
|
|
Print Occupancy Form | | | 1/19/2006 | | DONE |
|
|
|
|
Plan assigned to (M_P) | 9/26/2005 | | 1/19/2006 | | PASS |
|
|
|
1/19/2006 16:14:31 M_P - activity updated through activity BLDA022 from case BLD05-02671.
|
Routing - PLAN CHECK | 12/16/2005 | | 1/13/2006 | | PEND |
|
|
|
Waiting for others to approve prior to issuing permit.
|
Plan resubmittals received | | | 1/4/2006 | | DONE |
|
|
|
Received 2 Architects revisions letters, & 2 Copys of sheets - Cover,a2,a5,a8,a9,s3,e-2,en1.1,en2.0,m0.2,m1.1 Re-submittals inserted into main plans and taken back to Mike P.
|
Plan resubmittals received | | | 12/27/2005 | | DONE |
|
|
|
Received fax cover memo from architect along with United Water fire flow memo and revised copy of plan cover sheet and gave to Mike P. to insert in plans.
|
Routing - PLUMBING | 12/15/2005 | | 12/16/2005 | | PASS |
|
|
|
Rout to Plumbing after fire review, new plumbing plans have been submitted. per plans and 2003 upc
|
1st review completed | | | 12/14/2005 | | FAIL |
|
|
|
structural, plumbing, esc, plan check, fire.
|
Routing - FIRE | 12/8/2005 | | 12/14/2005 | | FAIL |
|
|
|
Require water flow data and verification of sprinklered or not; faxed to architect
|
Routing Off Site - STRUCTURAL | 12/8/2005 | | 12/13/2005 | | PASS |
|
|
|
No further review required.
Called PDQ for pick up
|
Print permit w/o conditions | | | 12/8/2005 | | |
|
|
|
|
Routing - PLAN CHECK | 11/1/2005 | | 12/8/2005 | | FAIL |
|
|
|
Plan review complete, sent correction report to architect requesting additional information be submitted for further review prior to issuing permit.
|
Plan resubmittals received | | | 12/5/2005 | | DONE |
|
|
|
Received 1 Start up for inspections, 3 review comments, & 3 copys of sheets A7,S1,S3,S4 Taken to Mike P.
|
Plan resubmittals received | | | 11/28/2005 | | |
|
|
|
Received 2 cover sheets, A7,S1,S3,S4 inserted into main plans and taken back to Mike P.
|
Routing Off Site - STRUCTURAL | 9/26/2005 | | 11/15/2005 | | FAIL |
|
|
|
Faxed outside structural review comments to architect. Additional reveiw required by outside engineering firm.
|
Plan resubmittals received | | | 11/2/2005 | | |
|
|
|
Received (2) copies of sheet P1.0 and P0.2. Routed to Mike O.
|
Routing - Erosion and Sediment | 10/31/2005 | | 11/1/2005 | | FAIL |
|
|
|
No rp listed on application and general contractor has been called out. Informed applicant.
|
Routing - Erosion and Sediment | 11/1/2005 | | 11/1/2005 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Routing - PLAN CHECK | 10/20/2005 | | 10/31/2005 | | |
|
|
|
Routing to ESC for review.
|
Routing - PLANNING | 10/17/2005 | | 10/20/2005 | | PASS |
|
|
|
Approved.
|
Plan resubmittals received | | | 10/17/2005 | | |
|
|
|
Received (4) copies of sheet SWP-1, (3) copies of ESC Narrative sheets 1 and 4, and (3) copies of reduced sheet SWP-1. Routed to Mike P.
|
Routing - PLUMBING | 10/12/2005 | | 10/17/2005 | | FAIL |
|
|
|
provide a sink with drain for the mop faucett. note 6 page P1.0.
|
Routing - Erosion and Sediment | 10/11/2005 | | 10/12/2005 | | FAIL |
|
|
|
General contractor identified but the responsible person is not certified by Boise City.
|
Routing - PUBLIC WORKS | 10/6/2005 | | 10/11/2005 | | PASS |
|
|
|
|
Routing - PLANNING Land Div | 9/29/2005 | | 10/6/2005 | | PASS |
|
|
|
Lot 8 of Vic Park Subdivision No. 1
|
Plan resubmittals received | | | 10/5/2005 | | |
|
|
|
Received 1 Hazardous material inventory taken tpo Mike P.
|
(F) Reprint permit | | | 9/29/2005 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/29/2005 | | |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 9/29/2005 | | |
|
|
|
|
Application received | | | 9/26/2005 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/26/2005 | | |
|
|
|
|