Permit Information
Permit NumberBLD05-02719
StatusFinaled
Name MICRON TECHNOLOGY
Site Address 3800 S ORCHARD ST
Project NameMicron Aircraft Hanger\Office
Customer Number 
ePlanReviewNo
Description
RCE-1875///5/2/06 BAS Micron Hanger - To construct a 15,000 sq. ft. one story, Type IIB fully fire sprinklered aircraft hanger with offices. Hanger area is 12,427 sq. ft. and office area is 2573 sq. ft. Other work includes all site improvements, paving and landscaping per approved plans and attachments. Fire sprinklers are used for area and designed per NFPA 409 as regulated by Boise Fire.
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice BLD4/9/20074/9/200712/30/2008 DONE
DetailsCathy Brown
Second Notice has not been responded to.
Telephone call  10/4/2007 DONE
tlk to adam 2:30 regarding the final values he said that he will being looking at bld05-02719, bld05-03054, bld06-00569 and bld05-2616 will be given to Ron Juhnke
Telephone call  7/20/2007  
lft ms with adam get the final values to ASAP to close account
Telephone call  5/2/2007 DONE
call to adam w/ petra, he said he is working on the fv and will send it to us asap
Second Notice BLD3/30/20073/30/20074/9/2007 DONE
First Notice has not been responded to.
First Notice 3/16/20073/30/2007 DONE
Permanent occupancy UNPAID FEE  3/16/2007 DONE
Perm. Occ. Cert. # 11483 issued 3-16-07 to the Micron Aircraft Hanger and Offices.
BLD-Final3/15/20073/15/20073/15/2007PPASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 3/15/2007 at 9:54:39 AM. Contact: ###-####.
Permanent Occupancy 3/15/20073/15/2007 DONE
Details
FIRE-Final Inspection3/7/20073/7/20073/7/2007PPASS
DetailsTroy Cobbley
LIfe safety finaled
FIRE-Final Inspection2/23/20072/23/20072/23/2007PFAIL
DetailsTroy Cobbley
No smoke barrier/draft curtain has been installed per the review comments and details on drawing sheets A4 to A6. All other life safety items ok.
BLD-Other2/5/20072/6/20072/6/2007PPART
DetailsJim Storey
mike Note: t-bar; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles clip or spreader bars. wire supply hvac will check at final.
BLD-Framing/Rough-in1/3/20071/4/20071/4/2007PPART
DetailsJim Storey
mike ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
BLD-Aging Inspection12/7/200612/7/200612/8/2006 PASS
DetailsJim Storey
wip
BLD-Aging Inspection10/3/200610/3/200610/3/2006 NR
DetailsJim Storey
ncfi
BLD-Aging Inspection8/1/20068/1/20068/1/2006 FAIL
DetailsJim Storey
ncfi
(F) Reprint permit  7/21/2006 DONE
CHANGE STATUS TO (ISS)  7/21/2006 DONE
Telephone call  7/20/2006 DONE
spoke to cornel larson@###-####/reminded him that permit was ready and fees due
Telephone call  6/2/2006 DONE
left ms for cornel larson ###-#### that permit and fees are ready to be picked up
Permit Ready to Issue  6/2/2006 DONE
Plan assigned to (MLO)5/19/20065/19/20065/31/2006 PASS
5/31/2006 14:13:03 MLO - activity updated through activity BLDA022 from case BLD05-02719.
PLANS/APPL TAKEN TO FRONT DESK  5/31/2006 DONE
plan modification
Routing - FIRE5/25/2006 5/30/2006 PASS
Inserted updated review comments into plans.
Routing - Erosion and Sediment5/24/2006 5/25/2006 PASS
ESC plan approved with attached conditions.
Routing - PLANNING5/25/2006 5/25/2006 PASS
Project not in a D overlay. Use allowed in zone.
Routing - PLAN CHECK5/23/2006 5/24/2006 PASS
Routing - PUBLIC WORKS5/24/2006 5/24/2006 PASS
Plan Modification Accepted  5/22/2006  
Plan modification accepted for BLD05-02719 for the moving of the hangar to be 20' east and 57'6" north, 15 parking stalls added with landscape islands. Site area has increased but building s remained unchanged from original submittal. Sheets SP-1, SP-2, ESC-1, L-1, C-1, C-2, E2.0 resubmitted and routed to Mike Otto.
(F) Reprint permit  5/3/2006  
Issue PAID IN FULL permit  5/2/2006 DONE
Routing - AIRPORT4/25/2006 4/25/2006 PASS
received letter of approval for plan modification from Amy Snyder airport staff approving relocation. MLO
Telephone call  4/4/2006 DONE
talked to cornel larson at ###-#### that permit is ready & need achd
Plan Modification Accepted  3/17/2006 PASS
Approved faxed request to relocate the proposed new hydrant on the west side of the building approx. 15' further north and directly west to the west edge of pavement, as shown on the revised approved sketch; faxed back to the architect.
Telephone call  1/20/2006 DONE
called ###-#### and left voicemessage for Cornel Larson that permit is ready, fees, need ACHD, GC, RP
Permit Ready to Issue  1/20/2006 DONE
Routing Off Site - STRUCTURAL12/1/2005 1/19/2006 PASS
Called P D Q for pick up
Routing - FIRE1/5/2006 1/19/2006 PASS
resubmittals sent to fire. MLO
Plan Modification Accepted  1/19/2006 PASS
Plan modifications submitted as Sheets A-4 and A-6 approved.
Routing - PLAN CHECK1/19/2006 1/19/2006 PASS
Case Summary (BLD)  1/19/2006  
PLANS/APPL TAKEN TO FRONT DESK  1/19/2006 DONE
Print Occupancy Form  1/19/2006 DONE
Case Summary (BLD)  1/19/2006 DONE
Plan assigned to (MLO)10/3/2005 1/19/2006 PASS
1/19/2006 11:30:09 MLO - activity updated through activity BLDA022 from case BLD05-02719.
Routing - FIRE12/19/2005 1/5/2006 FAIL
to check draft curtains.
1/5/06- architect to fax revised dimensioned elevation details verifying required curtain depth at wall and center of building.
Holding plans for receipt of fax which architect promised to send today.
Plan resubmittals received  1/5/2006 DONE
Received transmittal letter, & 2 copys of sheets A-4,A-6 taken to Mike O.
Plan resubmittals received  12/20/2005 DONE
1 letter from Steve Appleton. taken to Mike Otto
Routing - PLAN CHECK12/19/2005 12/19/2005 PEND
need letter from engineer regarding draft curtains faxed architect. MLO
Plan resubmittals received  12/16/2005 DONE
Received transmittal letter,1 response, & 2 copys of sheets A-1,A-4,A-6,A-8 Taken to Mike O.
Plan resubmittals received  11/30/2005  
Received (2) copies of response to structural comments. Routed to Mike O.
Routing Off Site - STRUCTURAL11/14/2005 11/23/2005 FAIL
corrections sent to architect
Plan resubmittals requested  11/23/2005 DONE
structural correction
1st review completed  11/22/2005 FAIL
FAILED STRUCTURAL.
Routing - PLAN CHECK11/22/2005 11/22/2005 PEND
Routing - FIRE10/24/2005 11/18/2005 PASS
11/08/05 - routed to FV with copy of NFPA 409.
Plan resubmittals received  11/14/2005 DONE
Received letter of transmittal , 4 response to structural comments, 4 review comment calculations. & 5 copys of sheets S-0,S-1,S-2,S-3,S-4,S-5 taken to Mike Otto
Routing - PLAN CHECK10/19/2005 10/24/2005 PEND
pending structural approval
Routing Off Site - STRUCTURAL10/6/2005 10/24/2005 FAIL
corrections sent to architect
Plan resubmittals requested  10/24/2005 DONE
structural corrections
Routing - PLANNING10/13/2005 10/18/2005 PASS
Sara S.

Not in a "D" overlay. The use is allowed in the zone.
Routing - PLUMBING10/11/2005 10/13/2005 PASS
per plans and 2003 upc
Routing - Erosion and Sediment10/10/2005 10/11/2005 PASS
ESC plan approved with attached conditions.
Routing - PUBLIC WORKS10/6/2005 10/10/2005 PASS
Routing - PLANNING Land Div10/5/2005 10/6/2005 PASS
Parcel is over 5 acres in size.
Plans ACCEPTED BY PLAN TECH  10/5/2005  
Plan routing begun/NEW & ADDTN  10/5/2005  
Application received  9/29/2005  
Recd Pcfee & Taken To Pln CK  9/29/2005 DONE
Fee Review-notes9/29/20059/29/2005   
Routing - PLAN CHECK5/30/2006    
Routing - PLAN CHECK5/31/2006