PubWorks Occupancy Approval | 7/10/2006 | 7/10/2006 | 7/10/2006 | | DONE |
|
|
|
|
Letter of compliance | | | 6/29/2006 | | DONE |
|
|
|
Letter of Compliance issued 6-29-06.
|
Fee Review-notes | 10/11/2005 | 10/11/2005 | 6/13/2006 | | DONE |
|
|
|
|
BLD-Final | 6/2/2006 | 6/2/2006 | 6/2/2006 | P | PASS |
Mike Jordan
|
|
|
bill; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley. ok for perm occ once others have finaled. ok for temp.
|
Code Occupancy Approval | | | 6/2/2006 | | PASS |
|
|
|
ALL IN AS REQUIRED FINAL SIGNED OFF.
|
FIRE-Final Inspection | 5/30/2006 | 5/31/2006 | 6/1/2006 | P | PASS |
Troy Cobbley
|
|
|
Life safety finaled. The indicators on the lease spaces exit doors are on the wrong side of the doors and will need to be corrected when tenants move in.
|
FIRE-Final Inspection | 5/26/2006 | 5/30/2006 | 5/30/2006 | P | FAIL |
Troy Cobbley
|
|
|
Bill Davis; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt
Fire extinguishers mounted at 51" should be 48" to lever.
2) Provide emergency lighting for Hall 104 and Hall at office 127
2) Doors to lease spaces 201 and 301 are mounted backwards
4) Final Fire Alarm Permit
|
Print Occupancy Form | | | 5/30/2006 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/26/2006 | | DONE |
|
|
|
|
BLD-Other | 5/12/2006 | 5/15/2006 | 5/15/2006 | A | PASS |
Mike Jordan
|
|
|
ceiling grid insp//bill; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa. Ceiling grid is as per plan and cisca.
|
BLD-Wall cover | 5/11/2006 | 5/12/2006 | 5/12/2006 | P | FAIL |
Dave Hannah
|
|
|
Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt ceiling grid inspection not per plan or cisca crew rivited two sides no pods
|
BLD-Energy code compliance | 3/24/2006 | 3/27/2006 | 3/27/2006 | P | PART |
Mike Jordan
|
|
|
doug; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
BLD-Framing/Rough-in | 3/23/2006 | 3/24/2006 | 3/24/2006 | P | PART |
Mike Jordan
|
|
|
doug; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa. Interior framed walls from grids E to H and grids 3 to 6.
|
BLD-Other | 2/6/2006 | 2/7/2006 | 2/7/2006 | A | PASS |
Tom Arcoraci
|
|
|
doug Note: rebar; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles mti on site
|
BLD-Other | 2/2/2006 | 2/3/2006 | 2/3/2006 | A | PART |
Mike Jordan
|
|
|
Doug -- masonry wall; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong. wip North wall 4ft. to 8ft. elev.
|
BLD-Other | 2/1/2006 | 2/2/2006 | 2/2/2006 | A | PART |
Mike Jordan
|
|
|
grout pour inspection//doug; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa. rebar not yet installed when on site. reveiwed special insp. reports while on site.
|
BLD-Footing | 12/21/2005 | 12/22/2005 | 12/22/2005 | A | PART |
Mike Jordan
|
|
|
re-bar inspection pouring at 12:30//doug; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
|
BLD-Footing | 12/13/2005 | 12/14/2005 | 12/14/2005 | P | PASS |
Mike Jordan
|
|
|
doug; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles. Perimeter footings.
|
(F) Reprint permit | | | 11/30/2005 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 11/29/2005 | | |
|
|
|
|
Routing Off Site - STRUCTURAL | 11/17/2005 | | 11/28/2005 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 11/18/2005 | | 11/28/2005 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/28/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/28/2005 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 11/28/2005 | | DONE |
|
|
|
|
Telephone call | | | 11/28/2005 | | DONE |
|
|
|
left mess for pete rockwell at ###-#### is ready & need achd
|
Plan assigned to (MLO) | 10/11/2005 | | 11/28/2005 | | PASS |
|
|
|
11/28/2005 09:49:28 MLO - activity updated through activity BLDA022 from case BLD05-02758.
|
Routing - Erosion and Sediment | 11/17/2005 | | 11/18/2005 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Routing - PLAN CHECK | 11/17/2005 | | 11/17/2005 | | PEND |
|
|
|
pending structural review
|
Plan resubmittals received | | | 11/16/2005 | | |
|
|
|
Received (1) united water letter and (1) copy of structural calcs (sheets 1-8) and (3) copies of sheet C-1.0, C-2.0, A-1.1, A-6.1, S0.1, S2.1, S5.1, S7.2, P-1.0, P-2.0, P-3.0, E-1.0, E-1.1, E-1.1A, E-1.2, E-1.3 and E-2.0. Routed to Mike O.
|
1st review completed | | | 11/9/2005 | | FAIL |
|
|
|
failed plan check, ESC and structural.
|
Routing - PLAN CHECK | 11/9/2005 | | 11/9/2005 | | PEND |
|
|
|
|
Routing - FIRE | 10/26/2005 | | 11/9/2005 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 10/18/2005 | | 10/26/2005 | | FAIL |
|
|
|
corrections sent to architect
|
Routing Off Site - STRUCTURAL | 10/11/2005 | | 10/26/2005 | | FAIL |
|
|
|
corrections sent to architect.
|
Plan resubmittals requested | | | 10/26/2005 | | DONE |
|
|
|
For IBC corrections
|
Plan resubmittals received | | | 10/20/2005 | | |
|
|
|
Received (4) ESC plans and (2) narratives. Routed to Mike O.
|
Routing - PLANNING | 10/13/2005 | | 10/18/2005 | | PASS |
|
|
|
Approved per DRH05-00232. (MGS, 10-17-05)
Cody R. CUP05-00086
Approved per CUP05-00086. (C.R., 10-18005)
|
Routing - PLUMBING | 10/13/2005 | | 10/13/2005 | | PASS |
|
|
|
verify thermol expantion protection sizing. pvb required on hand held eyewash. label nonpotable water system per upc.
|
Routing - Erosion and Sediment | 10/12/2005 | | 10/13/2005 | | FAIL |
|
|
|
ESC plan does not meet requirements per BMC 8-17.
|
Routing - PUBLIC WORKS | 10/11/2005 | | 10/12/2005 | | PASS |
|
|
|
|
Routing - PLANNING Land Div | 10/11/2005 | | 10/11/2005 | | PASS |
|
|
|
Final Plat recorded in May 2001.
|
Plans ACCEPTED BY PLAN TECH | | | 10/11/2005 | | |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 10/11/2005 | | |
|
|
|
|
Pending Assignment by MYS | 10/11/2005 | | 10/11/2005 | | DONE |
|
|
|
10/11/2005 09:25:48 JCM - activity updated through activity BLDA174 from case BLD05-02758.
|
Recd Pcfee & Taken To Pln CK | | | 10/11/2005 | | |
|
|
|
|
Application received | | | 10/4/2005 | | |
|
|
|
|