BLD-Final | 6/30/2006 | 7/5/2006 | 7/5/2006 | P | PASS |
Jim Storey
|
|
|
weston ; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley
|
DOC - Permit Finaled | 7/5/2006 | 7/5/2006 | 7/5/2006 | P | PASS |
Jim Storey
|
|
|
|
BLD-Framing/Rough-in | 4/14/2006 | 4/14/2006 | 4/14/2006 | P | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Internet Inspection Request from: Weston Kons
|
BLD-Framing/Rough-in | 4/12/2006 | 4/13/2006 | 4/13/2006 | P | FAIL |
Jim Storey
|
|
|
Phone #: ###-#### Internet Inspection Request from: Weston Kons
|
BLD-Framing/Rough-in | 4/11/2006 | 4/12/2006 | 4/12/2006 | A | PART |
Jim Storey
|
|
|
Phone #: ###-#### Internet Inspection Request from: Weston Kons truss bracing/ header kitchen over spaced studs. ok to inslate.
|
BLD-Footing | 2/1/2006 | 2/1/2006 | 2/1/2006 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 2/1/2006 at 7:54:28 AM. Contact: ###-####.
|
Issue PAID IN FULL permit | | | 1/18/2006 | | DONE |
|
|
|
|
Plan assigned to (SAM) | 10/6/2005 | 12/14/2005 | 12/15/2005 | | PASS |
|
|
|
12/15/2005 07:25:12 SAM - activity updated through activity BLDA022 from case BLD05-02798.
|
Routing - PLAN CHECK | 12/9/2005 | | 12/15/2005 | | PASS |
|
|
|
|
Case Summary (BLD) | | | 12/15/2005 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/15/2005 | | DONE |
|
|
|
Only one set of plans approved due to red-lining.
|
Inspection Record Card- Bld | | | 12/15/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/15/2005 | | DONE |
|
|
|
|
Telephone call | | | 12/15/2005 | | |
|
|
|
left mess that permit is ready
|
Routing - PUBLIC WORKS | 12/9/2005 | | 12/9/2005 | | PASS |
|
|
|
|
Routing - PLANNING | 12/9/2005 | | 12/9/2005 | | FAIL |
|
|
|
Returned an additioanl message from Hillary at GQ construction, specifically outlining the need for redlined/revised plans. 8:00a.m.
|
Routing - PLANNING | 12/9/2005 | | 12/9/2005 | | PASS |
|
|
|
Okay per redlines by applicant. A 5' setback is required for compliance with easment, and no bonus space will be allowed above the garage.
|
Routing - PLANNING | 12/8/2005 | | 12/8/2005 | | FAIL |
|
|
|
Returned message to applicant indicating need for revised drawings or redline.
|
Routing - PLANNING | 10/27/2005 | | 10/27/2005 | | FAIL |
|
|
|
Revised plans still fail to meet setback requirements. Storage above the garage results in an accessory structure still in excess of 500 s.f. requiring 5' side and 15' rear setbacks. (A 5' utility easement is located on both property lines.) The applicant was informed of issues at 12:30 p.m. today.
|
Routing - PLANNING | 10/6/2005 | | 10/7/2005 | | FAIL |
|
|
|
Detached accessory structure in the rear and side yard setbacks. Also, inadequate back-up space has been provided.
|
Application received | | | 10/6/2005 | | |
|
|
|
|