FIRE-Final Inspection | 9/5/2006 | 9/7/2006 | 9/7/2006 | A | PASS |
Troy Cobbley
|
|
|
Life safety finaled
|
BLD-Aging Inspection | 9/4/2006 | 9/4/2006 | 9/5/2006 | | DONE |
Troy Cobbley
|
|
|
Per Laten inspection will be called in for tomorrow
|
FIRE-Conference | 5/9/2006 | 5/9/2006 | 5/9/2006 | P | DONE |
Troy Cobbley
|
|
|
I contacted Laten about getting this permit finaled. He stated that he believed everything was done except for one door and that he would follow up on it.
|
FIRE-Final Inspection | 1/25/2006 | 1/25/2006 | 1/26/2006 | P | FAIL |
Troy Cobbley
|
|
|
Repair and test all exit signs and emergency lights. Provide emergency lighting in the corridor in front of the new "Interview Room 102" and in the main lobby. Remove manual flush bolts from the doors into "Interview Room 102" and into the lobby. They are not allowed per IFC 1008.1.8.4 Automatic flush bolts are allowed. Provide lever hardware or crashbar on the north office area exterior exit door.
|
BLD-Final | 1/23/2006 | 1/24/2006 | 1/24/2006 | A | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 1/23/2006 at 10:12:52 AM. Contact: ###-####. ok
|
BLD-Final | 1/19/2006 | 1/20/2006 | 1/20/2006 | P | NR |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 1/19/2006 at 2:34:51 PM. Contact: ###-####. Approved set of plans not available. Contractor to reschedule final.
|
BLD-Framing/Rough-in | 12/14/2005 | 12/14/2005 | 12/14/2005 | P | PART |
Jim Storey
|
|
|
ceiling framing///layton anderson; Phone #: ###-#### Internet Inspection Request from: Barbara Moore ceilling ok pending mech permit and sign off from mec inspector.
|
BLD-Framing/Rough-in | 12/7/2005 | 12/8/2005 | 12/8/2005 | P | PART |
Mike Jordan
|
|
|
laten Note: ceiling; Phone #: ###-#### Internet Inspection Request from: Barbara Moore. existing ceiling system is not floating, nedd to make new part of ceiling the same.
|
BLD-Framing/Rough-in | 11/21/2005 | 11/21/2005 | 11/21/2005 | P | PART |
Mike Jordan
|
|
|
layton; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles. Selected interior walls only with no elec. in walls. ok to cover partition wall on one side only. plans on site not the approved set. notified contractor that approved set needs to be on site.
|
Inspection Record Card- Bld | | | 11/16/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/16/2005 | | DONE |
|
|
|
|
Telephone call | | | 11/16/2005 | | DONE |
|
|
|
called ###-#### and left voicemessage for Clinton that permit is ready and fees
|
Issue PAID IN FULL permit | | | 11/16/2005 | | |
|
|
|
|
Plan assigned to (JCB) | 10/14/2005 | | 11/15/2005 | | PASS |
|
|
|
11/15/2005 13:06:27 JCB - activity updated through activity BLDA022 from case BLD05-02834.
|
Routing - FIRE | 11/1/2005 | | 11/15/2005 | | PASS |
|
|
|
|
1st review completed | | | 11/15/2005 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 11/15/2005 | | 11/15/2005 | | PASS |
|
|
|
Permit and plans approved and taken to front desk.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/15/2005 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 10/14/2005 | | 11/1/2005 | | PEND |
|
|
|
Plan review report e-mailed and faxed to architect. No response required. A few items have been red-lined on plans for clarification. Plans to route to the Fire Department for review. When approved by the Fire Department the permit can be issued.
|
Telephone call | | | 10/31/2005 | | DONE |
|
|
|
Called Clinton Yaka to discuss and verify a few items. Will red-line plans for clarification.
|
Plans ACCEPTED BY PLAN TECH | | | 10/14/2005 | | |
|
|
|
|
Application received | | | 10/11/2005 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/11/2005 | | |
|
|
|
|
Fee Review-notes | 10/11/2005 | 10/11/2005 | | | |
|
|
|
|