First Notice | 4/21/2010 | 4/21/2010 | 10/24/2012 | | DONE |
Dave Hannah
|
|
|
This permit finaled on the web by Marva Schwager
|
Plan Reviewer's activity | | | 6/21/2010 | | DONE |
|
|
|
Took office copy to Records.
|
BLD-Aging Inspection | 4/19/2010 | 4/19/2010 | 4/21/2010 | | PASS |
Dave Hannah
|
|
|
|
DOC - Permit Finaled | 4/21/2010 | 4/21/2010 | 4/21/2010 | A | PASS |
Dave Hannah
|
|
|
|
BLD-Aging Inspection | 12/8/2009 | 12/8/2009 | 12/16/2009 | | PASS |
Dave Hannah
|
|
|
marva will schedule finals
|
BLD-Conference | 5/7/2007 | 5/7/2007 | 5/7/2007 | P | DONE |
Dave Hannah
|
|
|
Dave this is the one I called you about...Dixie
|
BLD-Framing/Rough-in | 9/11/2006 | 9/11/2006 | 9/11/2006 | P | PART |
Dave Hannah
|
|
|
dennis Note: 8th floor; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles ok to cover
|
BLD-Framing/Rough-in | 8/28/2006 | 8/29/2006 | 8/29/2006 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 8/28/2006 at 12:55:33 PM. Contact: ###-####.5th and 6th floor control room duct work ok
|
BLD-Framing/Rough-in | 8/24/2006 | 8/24/2006 | 8/24/2006 | P | PART |
Dave Hannah
|
|
|
###-#### - dennis Note: duct work 9th 5th and 6th ok
|
(F) Reprint permit | | | 7/26/2006 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 7/6/2006 | | 7/20/2006 | | PASS |
|
|
|
Sheets came in on or about July 5, 2006, July 12, 2006, and July 18, 2006. Review was delayed until all sheets were in. Drawings approved after review.
|
Telephone call | | | 7/20/2006 | | DONE |
|
|
|
tried to leave mess for rick at ###-#### permit is ready
|
Plan resubmittals received | | | 7/18/2006 | | DONE |
|
|
|
Received 1 letter, & 2 copys of sheets MH-101, MH-606, MP-101-A taken to Carl W.
|
Plan resubmittals received | | | 7/12/2006 | | DONE |
|
|
|
received 2 copys of sheet A-103 taken to Carl W. (plans issued 12-16-05)
|
BLD-Framing/Rough-in | 3/1/2006 | 3/2/2006 | 3/2/2006 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 3/1/2006 at 2:55:05 PM. Contact: ###-####. second floor ok to install ceiling
|
BLD-Framing/Rough-in | 2/24/2006 | 2/27/2006 | 2/27/2006 | A | PART |
Dave Hannah
|
|
|
request 1st thing///dennis; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa corr walls 5th and 6th fl ok to cover
|
(F) Reprint permit | | | 2/21/2006 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 12/16/2005 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 12/2/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/2/2005 | | DONE |
|
|
|
|
Telephone call | | | 12/2/2005 | | DONE |
|
|
|
called ###-#### and left voicemessage for Amy that permit is ready and fees
|
Routing - PLAN CHECK | 11/22/2005 | | 12/1/2005 | | PASS |
|
|
|
Drawings approved after resubmittal review.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/1/2005 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 10/27/2005 | | 12/1/2005 | | PASS |
|
|
|
12/1/2005 16:12:43 CJW - activity updated through activity BLDA022 from case BLD05-02939.
|
Routing - FIRE | 11/9/2005 | | 11/22/2005 | | PASS |
|
|
|
no fire comments required
|
1st review completed | | | 11/22/2005 | | FAIL |
|
|
|
failed plan check
|
Plan resubmittals received | | | 11/14/2005 | | DONE |
|
|
|
Received 1 Transmittal,1 letter,2 teccrete access floor specifications & 2 copys of sheet G-00 Taken to Carl W.
|
Routing - PLAN CHECK | 10/27/2005 | | 11/9/2005 | | FAIL |
|
|
|
The IBC plan review was started on November 8 and was finished the next day. Revised drawings were required. See the plan review report.
|
Plans ACCEPTED BY PLAN TECH | | | 10/25/2005 | | |
|
|
|
|
Application received | | | 10/19/2005 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/19/2005 | | |
|
|
|
|
Fee Review-notes | 10/19/2005 | 10/19/2005 | | | |
|
|
|
|