Case Summary (BLD) | | | 7/2/2013 | | DONE |
|
|
|
|
Third Notice BLD | 6/14/2006 | 6/14/2006 | 2/8/2007 | | DONE |
|
|
|
Second Notice has not been responded to.
|
Telephone call | | | 2/6/2007 | | DONE |
|
|
|
lft vm with liz unico ###-#### that values varies I need her to call for the final values to close this case NOW
|
Telephone call | | | 9/15/2006 | | DONE |
|
|
|
lft vm for liz regarding the fees vary - she wont be intil Wednes
|
Second Notice BLD | 4/14/2006 | 4/14/2006 | 6/14/2006 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 3/22/2006 | 4/14/2006 | | DONE |
|
|
|
|
Permanent occupancy | | | 3/22/2006 | | DONE |
|
|
|
Perm. Occ. Cert. # 10945 issued 3-22-06 to the Associated Press.
|
BLD-Final | 3/15/2006 | 3/16/2006 | 3/16/2006 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 3/15/2006 at 11:38:23 AM. Contact: ###-####. ok for perm occ
|
Permanent Occupancy | | 3/16/2006 | 3/16/2006 | | DONE |
|
|
|
|
FIRE-Final Inspection | 3/3/2006 | 3/6/2006 | 3/6/2006 | A | PASS |
Troy Cobbley
|
|
|
Life safety finaled
|
BLD-Framing/Rough-in | 2/28/2006 | 2/28/2006 | 3/1/2006 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 2/28/2006 at 9:12:17 AM. Contact: ###-####.
|
BLD-Framing/Rough-in | 1/10/2006 | 1/11/2006 | 1/12/2006 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 1/10/2006 at 10:27:10 AM. Contact: ###-####.
|
Issue PAID IN FULL permit | | | 12/28/2005 | | DONE |
|
|
|
|
Print Occupancy Form | | | 12/27/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/27/2005 | | DONE |
|
|
|
|
Telephone call | | | 12/27/2005 | | DONE |
|
|
|
called ###-#### and left voice message for Dan that permit is ready and fees
|
Routing - PLAN CHECK | 12/21/2005 | | 12/23/2005 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/23/2005 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 10/27/2005 | | 12/23/2005 | | PASS |
|
|
|
12/23/2005 11:43:01 CJW - activity updated through activity BLDA022 from case BLD05-02956.
|
Routing - PLANNING | 12/16/2005 | | 12/21/2005 | | PASS |
|
|
|
Approved and as noted.
|
Routing - PLAN CHECK | 11/25/2005 | | 12/16/2005 | | PASS |
|
|
|
Drawings approved after resubmittal review.
|
Plan resubmittals received | | | 12/13/2005 | | DONE |
|
|
|
Received one copy of plan review report with two copies of plan review responses, two sets of sheets A-1,A-2,A-3,D-1 taken to Carl.
|
1st review completed | | | 11/29/2005 | | FAIL |
|
|
|
FAILED PLAN CHECK
|
Routing - FIRE | 11/15/2005 | | 11/21/2005 | | PASS |
|
|
|
sent to FV 11/17.
returned from Floyd on 11/25.
|
Routing - PLAN CHECK | 10/28/2005 | | 11/15/2005 | | FAIL |
|
|
|
The IBC plan review was started on November 14 and was finished the next day. Revised drawings were required. See the plan review report.
|
Routing - PUBLIC WORKS | 10/27/2005 | | 10/28/2005 | | PASS |
|
|
|
|
Pending Assignment by MYS | 10/21/2005 | | 10/27/2005 | | DONE |
|
|
|
10/27/2005 16:52:23 MYS - activity updated through activity BLDA172 from case BLD05-02956.
|
Plans ACCEPTED BY PLAN TECH | | | 10/25/2005 | | |
|
|
|
|
Application received | | | 10/21/2005 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/21/2005 | | |
|
|
|
|
Fee Review-notes | 10/21/2005 | 10/21/2005 | | | |
|
|
|
|