Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD05-02959
StatusFinaled
Name BOISE SAMARITAN
Site Address 3115 N SYCAMORE DR
Project NameBOISE SAMARITAN VILLAGE
Customer Number 
ePlanReviewNo
Description
*(Good Samaritan Village)* (Partial Phase IV)* This permit is to continue the phased upgrade agreement to bring this building into code compliance. Under this permit is to remove all of the combustible corrugated fiberglass overhang will be removed from the exterior of the south building, the fiberglass corrugated roofing from the walk way between the laundry room and the south building will be removed, the construction of a two-hour fire wall through the overhang area between the south building and the administration building will be completed, to separate the two buildings to complete the separation that was started under a previous permit. All work to be per approved plans. This building is fully fire sprinklered any alterations to the sprinkler system shall be per NFPA #13 as regulated by the fire department. (RMH)
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Letter of compliance  6/21/2006 DONE
Letter of Compliance issued 6-21-06.
FIRE-Final Inspection5/4/20065/5/20065/5/2006APASS
DetailsTroy Cobbley
Life safety finaled
BLD-Energy code compliance5/4/20065/4/20065/4/2006PPART
DetailsTony Young
call first; Phone #: ###-#### Internet Inspection Request from: Ione Coleman
not a e. code,, just a conf/final on this permit,, need f/l/s also,, ok pending f/l/s
Issue PAID IN FULL permit  4/5/2006 DONE
Telephone call  4/4/2006 DONE
left mess for steve at ###-#### that permit is ready
Telephone call  1/5/2006 DONE
left mess for steve at ###-#### that permit is ready
Permit Ready to Issue  11/10/2005 DONE
Inspection Record Card- Bld  11/10/2005 DONE
Telephone call  11/10/2005 DONE
Spoke with Steve and told him that permit is ready & fees///11/10/05 10:05am BAS
Plan assigned to (R_H)11/4/2005 11/8/2005 PASS
11/8/2005 11:09:36 RMH - activity updated through activity BLDA022 from case BLD05-02959.
Routing - PLAN CHECK11/4/2005 11/8/2005 PASS
Case Summary (BLD)  11/8/2005 DONE
Routing - FIRE11/8/2005 11/8/2005 PASS
Minor work / Field verify
PLANS/APPL TAKEN TO FRONT DESK  11/8/2005 DONE
Plans ACCEPTED BY PLAN TECH  10/26/2005  
Application received  10/21/2005  
Recd Pcfee & Taken To Pln CK  10/21/2005  
Fee Review-notes10/21/200510/21/2005