Third Notice | | 6/15/2006 | 6/15/2006 | | DONE |
|
|
|
|
Second Notice BLD | 4/14/2006 | 4/14/2006 | 5/22/2006 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 4/3/2006 | 4/14/2006 | | DONE |
|
|
|
|
BLD-Final | 3/31/2006 | 4/3/2006 | 4/3/2006 | A | PASS |
Tom Arcoraci
|
|
|
tony ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie ok for final
|
Permanent Occupancy | | 4/3/2006 | 4/3/2006 | | DONE |
|
|
|
|
Permanent occupancy UNPAID FEE | | | 4/3/2006 | | |
|
|
|
Perm. Occ. Cert. # 10962 issued 4-3-06 to the Perinatology Clinic.
|
FIRE-Final Inspection | 3/30/2006 | 3/31/2006 | 3/31/2006 | P | PASS |
Troy Cobbley
|
|
|
life safety finaled
|
BLD-Framing/Rough-in | 3/20/2006 | 3/20/2006 | 3/20/2006 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 3/20/2006 at 8:48:05 AM. Contact: ###-####. Ceiling grid insp. ok pending elec. insp.
|
BLD-Aging Inspection | 3/15/2006 | 3/15/2006 | 3/15/2006 | | PASS |
Tom Arcoraci
|
|
|
wip
|
BLD-Framing/Rough-in | 12/28/2005 | 12/28/2005 | 12/28/2005 | P | CANC |
Tom Arcoraci
|
|
|
tony
|
BLD-Conference | 12/27/2005 | 12/28/2005 | 12/28/2005 | A | PASS |
Tom Arcoraci
|
|
|
tony; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
|
BLD-Framing/Rough-in | 12/28/2005 | 12/28/2005 | 12/28/2005 | P | PART |
Tom Arcoraci
|
|
|
tony; Phone #: ###-#### Internet Inspection Request from: Barbara Moore ok to cover after plum mech and elec rough ins
|
Issue & PRINT permit | | | 12/15/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/13/2005 | | DONE |
|
|
|
|
Print Occupancy Form | | | 12/13/2005 | | DONE |
|
|
|
|
Telephone call | | | 12/13/2005 | | DONE |
|
|
|
left mess for sam burrows at ###-#### that permit is ready
|
Routing - PLAN CHECK | 12/1/2005 | | 12/12/2005 | | PASS |
|
|
|
Plan submittals of 12/1/05 inserted into original plans. Red-line clarifications concerning "S" label requirement for smoke-and-draft control doors 201 & 225B to protect existing 1-hour rated corridor constructed under the UBC. Also attached details for accessible transfer type shower to further clarify data submitted by architect in response to plan review.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/12/2005 | | PASS |
|
|
|
|
Plan assigned to (DRS) | 11/3/2005 | | 12/12/2005 | | PASS |
|
|
|
12/12/2005 12:07:59 DRS - activity updated through activity BLDA022 from case BLD05-02966.
|
Routing - FIRE | 11/17/2005 | | 12/1/2005 | | PASS |
|
|
|
|
1st review completed | | | 12/1/2005 | | FAIL |
|
|
|
failed plan check.
|
Plan resubmittals received | | | 11/28/2005 | | |
|
|
|
Received (2) copies of sheet A2.1, A6.0 and A9.0. Routed to Dan S.
|
Routing - PLAN CHECK | 11/4/2005 | | 11/17/2005 | | FAIL |
|
|
|
|
Plan resubmittals requested | | | 11/17/2005 | | DONE |
|
|
|
copy e-mailed to architect for response.
|
Routing - PLUMBING | 11/3/2005 | | 11/4/2005 | | PASS |
|
|
|
approved per plan and 2003 UPC
|
Routing - PUBLIC WORKS | 11/3/2005 | | 11/3/2005 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/28/2005 | | |
|
|
|
|
Application received | | | 10/24/2005 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/24/2005 | | |
|
|
|
|
Fee Review-notes | 10/24/2005 | 10/24/2005 | | | |
|
|
|
|