Permit NumberBLD05-02990
StatusFinaled
Name DERICK O'NEILL
Site Address 2948 S ROOKERY LN
Project Name 
Customer Number 
ePlanReviewNo
Description
To construct a two bedroom, two bathroom 1953 sq. ft. three story town home on a zero lot line (238 sq. ft. first floor/800 sq. ft. second floor/915 sq. ft. third floor) with a attached 532 sq. ft. two car garage and a 148 sq. ft. deck off the second floor. Per approved plans, enginneering and requirement list. DRH04-00103 Mod #1 per Sarah Schafer and CUP04-00032 per Susan Riggs with Planning and Zoning. An alternate approval letter by Bruce Chatterton, PDS Director, dated 2/3/05 is attached to this permit and approved plans which allows common access across property lines from both units. This alternate requires a two hour wall enclosure, protected eave overhangs, 90 minute rated assemblies and inspection requirements. (SAM)
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
CHANGE STATUS TO (FNL)  11/9/2006 DONE
Resdiential Cert. of Occ. issued 11-9-06.
BLD-Final11/8/200611/8/200611/8/2006PPASS
DetailsJim Storey
terry ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
BLD-Final11/6/200611/7/200611/7/2006PNR
DetailsJim Storey
Scheduled by a contractor via Hello! on 11/6/2006 at 4:07:01 PM. Contact: ###-####.
BLD-Wall cover7/12/20067/13/20067/13/2006APASS
DetailsDave Hannah
TERRY; Phone #: ###-#### Internet Inspection Request from: Darla Downs
BLD-Energy code compliance7/13/20067/13/20067/13/2006PPASS
DetailsDave Hannah
TERRY; Phone #: ###-#### Internet Inspection Request from: Darla Downs
BLD-Framing/Rough-in7/11/20067/11/20067/11/2006PPASS
DetailsDave Hannah
terry; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley ok to insulate
BLD-Framing/Rough-in7/6/20067/6/20067/6/2006PPART
DetailsJim Storey
Scheduled by a contractor via Hello! on 7/6/2006 at 7:10:20 AM. Contact: ###-####.
BLD-Framing/Rough-in6/2/20066/2/20066/2/2006PFAIL
DetailsJim Storey
terry; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley
Plan resubmittals received  4/27/2006  
received 1 copy of sheets A5.0 5.1 & 1 transmittal for Marlene S.
taken to Marlene permit issued 11-30-05
BLD-Wall cover4/21/20064/21/20064/21/2006PPART
DetailsJim Storey
Scheduled by a contractor via Hello! on 4/21/2006 at 8:28:20 AM. Contact: ###-####.
BLD-Energy code compliance4/17/20064/17/20064/17/2006PPART
DetailsJim Storey
Scheduled by a contractor via Hello! on 4/17/2006 at 11:28:15 AM. Contact: ###-####. nailling ok but must extened thru to exterior wall east side.
BLD-Other4/13/20064/14/20064/14/2006APASS
DetailsJim Storey
terry Note: shear nail insp; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles first floor 2 hr gyp ok
BLD-Foundation2/13/20062/13/20062/14/2006PPASS
DetailsJim Storey
Jerry; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong
BLD-Footing2/9/20062/9/20062/9/2006APASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 2/9/2006 at 7:13:39 AM. Contact: ###-####.
Inspection Record Card- Bld  1/18/2006 DONE
Telephone call  1/18/2006 DONE
Spoke with Trevor and told her that permit is ready & fees @8:15am on 1/18/06 BAS
Case Summary (BLD)  1/17/2006  
Issue PAID IN FULL permit  11/30/2005 DONE
Plan assigned to (SAM)10/26/200511/18/200511/18/2005 PASS
11/18/2005 09:57:24 SAM - activity updated through activity BLDA022 from case BLD05-02990.
Case Summary (BLD)  11/18/2005  
PLANS/APPL TAKEN TO FRONT DESK  11/18/2005 DONE
Permit Ready to Issue  11/18/2005  
Inspection Record Card- Bld  11/18/2005 DONE
Telephone call  11/18/2005  
tlk to secretary ###-#### that permit and fees are ready to be picked up
Routing - PLAN CHECK11/8/2005 11/18/2005 PASS
Routing - Erosion and Sediment11/7/2005 11/8/2005 PASS
ESC plan approved with attached conditions. Referece ESC05-00321 as master plan.
Routing - PUBLIC WORKS11/4/2005 11/7/2005 PASS
Routing - PLANNING11/3/2005 11/4/2005 PASS
Approved per DR.
Routing - PLANNING10/26/2005 11/3/2005 PASS
passed onto Sara for DR
Application received  10/26/2005