Print Occupancy Form | | | 10/24/2008 | | DONE |
|
|
|
|
Third Notice BLD | 1/8/2007 | 1/8/2007 | 1/25/2007 | | DONE |
|
|
|
Second Notice has not been responded to.
|
Second Notice BLD | 12/27/2006 | 12/27/2006 | 1/8/2007 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 11/24/2006 | 12/27/2006 | | DONE |
|
|
|
|
Permanent occupancy | | | 11/24/2006 | | DONE |
|
|
|
Perm. Occ. Cert. # 11308 issued 11-20-06 to the Orchards., Bldg. #7
|
Code Occupancy Approval | 11/20/2006 | 11/20/2006 | 11/20/2006 | P | PASS |
Scott M.Brown
|
|
|
OK FINAL SIGNED OFF
|
Permanent Occupancy | | 11/20/2006 | 11/20/2006 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 11/20/2006 | | |
|
|
|
|
Telephone call | | | 11/20/2006 | | DONE |
|
|
|
Called Steve Dresser and told him that there is extra plan review fees///11/20/06 @12:00BAS
|
Routing - PLANNING | 11/17/2005 | | 11/18/2006 | | PASS |
|
|
|
Approved per DRH05-00191.
|
BLD-Final | 11/16/2006 | 11/17/2006 | 11/17/2006 | A | PART |
Tom Arcoraci
|
|
|
steve ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith this will be ok for temp occ when planning is ok with contstruction change
|
BLD-Conference | 11/15/2006 | 11/16/2006 | 11/16/2006 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 11/15/2006 at 11:58:39 AM. Contact: ###-####.
|
FIRE-Final Inspection | 11/8/2006 | 11/9/2006 | 11/9/2006 | P | PART |
Forrest France
|
|
|
Corrections for Building 1414 per previous c/n have been verified for completion, inspeciton passed.
|
BLD-Final | 11/7/2006 | 11/7/2006 | 11/7/2006 | P | FAIL |
Forrest France
|
|
|
SD within 20' of a cooking appliance must be "push to silence" or of the photoelectric type, SD must not be located within 3' of an adjacent opening to a room containing a shower, detectors at two locations need the dust covers removed before final.
|
FIRE-Final Inspection | 11/6/2006 | 11/7/2006 | 11/7/2006 | P | DEFR |
Forrest France
|
|
|
|
BLD-Aging Inspection | 10/24/2006 | 10/24/2006 | 10/24/2006 | | PASS |
Tom Arcoraci
|
|
|
|
BLD-Energy code compliance | 8/21/2006 | 8/22/2006 | 8/22/2006 | A | PASS |
Tom Arcoraci
|
|
|
ken; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
BLD-Framing/Rough-in | 8/15/2006 | 8/16/2006 | 8/16/2006 | A | PART |
Tom Arcoraci
|
|
|
Roof and exterior wall nailing inspection.; Phone #: ###-#### Internet Inspection Request from: Steve Dresser
|
BLD-Wall cover | 7/17/2006 | 7/18/2006 | 7/18/2006 | A | PASS |
Mike Jordan
|
|
|
Karl - exterior sheeting; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley
|
Issue PAID IN FULL permit | | | 6/22/2006 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/20/2006 | | |
|
|
|
|
Plan assigned to (M_P) | 11/3/2005 | 11/3/2005 | 6/16/2006 | | PASS |
|
|
|
6/16/2006 15:41:54 M_P - activity updated through activity BLDA022 from case BLD05-03029.
|
Routing - PLAN CHECK | 2/16/2006 | | 6/16/2006 | | PASS |
|
|
|
Received satisfaction of nonbuild.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/16/2006 | | DONE |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 6/16/2006 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 6/16/2006 | | DONE |
|
|
|
|
Plan resubmittals received | | | 6/1/2006 | | |
|
|
|
Received 1 copy of cover letter to Mike Phillips, 1 copy of Letter from Stapley Engineering to Jeff Likes, 1 copy of the following pages- Chateau roof framing plan, Sheet # SK-1, SK-2, 1 copy of Letter from Stapley Engineering to Jeff Likes, 1 copy of the following pages- Canterbury roof framing plan, SK-3, Chateau roof framing plan, SK-4, SK-5, 1 page letter from Boise Wood Solutions, SK-6 and taken to Dave Hannah per MIke Phillips request///6/1/06 @ 9:40am BAS
|
Routing - FIRE | 2/15/2006 | | 2/16/2006 | | PASS |
|
|
|
No comments.
|
Routing - PLAN CHECK | 2/7/2006 | | 2/15/2006 | | |
|
|
|
Routing to fire.
|
Routing - PLAN CHECK | 1/27/2006 | | 2/7/2006 | | FAIL |
|
|
|
Second review failed, sent correction report to architect requesting additional information be submitted for further review prior to issuing permit.
|
Routing - PLANNING Land Div | 11/3/2005 | | 2/7/2006 | | PASS |
|
|
|
|
Telephone call | | | 1/27/2006 | | PASS |
|
|
|
See attached comments.
|
Routing - PLAN CHECK | 1/27/2006 | | 1/27/2006 | | PASS |
|
|
|
See comments.
|
Routing - PLANNING | 1/10/2006 | | 1/19/2006 | | PASS |
|
|
|
CUP05-30 & phasing mod.
|
Routing - PLAN CHECK | 1/9/2006 | | 1/10/2006 | | |
|
|
|
Routing to planning for review of CUP and sign off of DR.
|
1st review completed | | | 1/9/2006 | | FAIL |
|
|
|
Failed Plan Check and Fire
|
Routing - FIRE | 12/30/2005 | | 1/9/2006 | | FAIL |
|
|
|
See attached commnets. Faxed to architect.
|
Case Summary (BLD) | | | 12/30/2005 | | |
|
|
|
|
Routing - PLAN CHECK | 11/18/2006 | | 12/30/2005 | | FAIL |
|
|
|
Plan review complete, send correction report to architect. I am requesting additional information be submitted for further review prior to issuing permit.
|
Routing - PLUMBING | 11/10/2005 | | 11/17/2005 | | PASS |
|
|
|
see bld05-03020
|
Routing - PUBLIC WORKS | 11/7/2005 | | 11/10/2005 | | PASS |
|
|
|
|
Routing - Erosion and Sediment | 11/10/2005 | | 11/10/2005 | | PASS |
|
|
|
ESC plan approved with attached conditions. 11/10/05 Reference ESC05-01821 as Master Plan for project. adh.
|
Plan routing begun/NEW & ADDTN | | | 11/3/2005 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 11/3/2005 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 11/3/2005 | | |
|
|
|
|
Application received | | | 10/27/2005 | | |
|
|
|
|
Fee Review-notes | 11/3/2005 | 11/3/2005 | | | |
|
|
|
|