BLD-Final | 10/12/2006 | 10/12/2006 | 10/12/2006 | P | PASS |
Tom Arcoraci
|
|
|
larry; Phone #: ###-#### Internet Inspection Request from: Patricia Smith pending mech final
|
BLD-Energy code compliance | 4/21/2006 | 4/21/2006 | 4/21/2006 | P | PASS |
Jim Storey
|
|
|
LARRY; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
|
BLD-Framing/Rough-in | 3/29/2006 | 3/29/2006 | 3/29/2006 | P | PASS |
Tom Arcoraci
|
|
|
larry ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
Case Summary (BLD) | | | 2/10/2006 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 1/3/2006 | | DONE |
|
|
|
|
BLD-Footing | 12/23/2005 | 12/27/2005 | 12/27/2005 | A | PART |
Tom Arcoraci
|
|
|
requests about 9:30am//Larry; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
|
BLD-Foundation | 12/21/2005 | 12/22/2005 | 12/22/2005 | A | PASS |
Tom Arcoraci
|
|
|
foundation wall insp///requests 11:30///Larry; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
|
BLD-Footing | 12/20/2005 | 12/21/2005 | 12/21/2005 | P | PART |
Mike Jordan
|
|
|
###-#### Larry Note: 2:00 pm is possible. Confirmed with geo-tech engineer that garage footings were acceptable.
|
PubWorks Subgrade Approval | 12/21/2005 | 12/21/2005 | 12/21/2005 | | DONE |
|
|
|
Footing subgrade approved by the geotechnical engineer. Unsuitable fill materials were removed from the north side of the existing foundation and taller walls will be placed rather than structural fill.
|
BLD-Footing | 12/19/2005 | 12/20/2005 | 12/20/2005 | P | CANC |
Tom Arcoraci
|
|
|
###-#### Larry will reschedule
|
Permit Ready to Issue | | | 11/8/2005 | | |
|
|
|
|
Inspection Record Card- Bld | | | 11/8/2005 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 11/8/2005 | | |
|
|
|
|
Case Summary (BLD) | | | 11/7/2005 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/7/2005 | | DONE |
|
|
|
|
Plan assigned to (PEP) | 11/2/2005 | | 11/7/2005 | | PASS |
|
|
|
11/7/2005 07:38:50 PEP - activity updated through activity BLDA022 from case BLD05-03070.
|
Plan assigned to (PEP) | 11/2/2005 | | 11/7/2005 | | PASS |
|
|
|
11/7/2005 07:38:50 PEP - activity updated through activity BLDA022 from case BLD05-03070.
|
Routing - PLAN CHECK | 11/2/2005 | | 11/7/2005 | | PASS |
|
|
|
|
Routing - Erosion and Sediment | 11/2/2005 | | 11/2/2005 | | PASS |
|
|
|
ESC plan waiver request approved with attached conditions.
|
Application received | | | 11/2/2005 | | |
|
|
|
|
PubWorks Subgrade Approval | 11/7/2005 | 11/7/2005 | | | |
|
|
|
|