Case Summary (BLD) | | | 12/11/2006 | | |
|
|
|
|
Third Notice BLD | 6/14/2006 | 6/14/2006 | 8/4/2006 | | DONE |
|
|
|
Second Notice has not been responded to.
|
Second Notice BLD | 4/14/2006 | 4/14/2006 | 6/14/2006 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 3/27/2006 | 4/14/2006 | | DONE |
|
|
|
|
Permanent occupancy UNPAID FEE | | | 3/27/2006 | | DONE |
|
|
|
Perm. Occ. Cert. # 10951 issued 3-27-06 to Super Suppers in the Albertson's Marketplace.
|
BLD-Final | 3/14/2006 | 3/15/2006 | 3/15/2006 | A | PASS |
Tom Arcoraci
|
|
|
matt; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa ok for perm occ
|
Permanent Occupancy | | 3/15/2006 | 3/15/2006 | | DONE |
|
|
|
|
FIRE-Final Inspection | 3/13/2006 | 3/14/2006 | 3/14/2006 | A | PASS |
Forrest France
|
|
|
Fire life safety passed inspection, surface bolt hardware at the back door removed while on site.
|
FIRE-Conference | 2/1/2006 | 2/2/2006 | 2/2/2006 | A | DONE |
Forrest France
|
|
|
matt; Phone #: ###-#### Conference to discuss related permit requirements and basic life safety items for this TI.
|
Override - Parcel Holds | 1/1/1900 | 1/1/1900 | 2/1/2006 | | |
|
|
|
|
BLD-Framing/Rough-in | 1/27/2006 | 1/27/2006 | 1/27/2006 | P | PASS |
Jim Storey
|
|
|
Matt; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong
|
Override - Parcel Holds | 1/1/1900 | 1/1/1900 | 1/27/2006 | | |
|
|
|
Framing of bathrooms not related to fire alarm issues
|
Issue PAID IN FULL permit | | | 12/15/2005 | | DONE |
|
|
|
|
Telephone call | | | 12/6/2005 | | DONE |
|
|
|
called ###-#### xt.5 and left voicemessage for Matt that permit is ready and fees
|
Plan assigned to (CJW) | 11/15/2005 | | 12/5/2005 | | PASS |
|
|
|
12/5/2005 14:52:24 CJW - activity updated through activity BLDA022 from case BLD05-03099.
|
Routing - FIRE | 11/21/2005 | | 12/5/2005 | | PASS |
|
|
|
Pass with annotation that approval is subject to conditions specified in IFC reviews for BLD05-01262(Shell) and BLD05-03045 (Vanilla Finish).
|
1st review completed | | | 12/5/2005 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 12/5/2005 | | 12/5/2005 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/5/2005 | | DONE |
|
|
|
|
Print Occupancy Form | | | 12/5/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/5/2005 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 11/18/2005 | | 11/21/2005 | | PASS |
|
|
|
The IBC plan review report was started on November 19, 2005 and was finished on November 21, 2005. The drawings were approved. See the plan review report.
|
Routing - PLUMBING | 11/17/2005 | | 11/18/2005 | | PASS |
|
|
|
per plans and 2003 upc
|
Routing - PUBLIC WORKS | 11/15/2005 | | 11/17/2005 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 11/7/2005 | | |
|
|
|
|
Application received | | | 11/4/2005 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 11/4/2005 | | |
|
|
|
|
Fee Review-notes | 11/4/2005 | 11/4/2005 | | | |
|
|
|
|