Permit Information
Permit NumberBLD05-03132
StatusFinaled
Name STS CONTRACTORS
Site Address 9380 W FAIRVIEW AVE
Project NameLARRY MILLER SUBARU
Customer Number 
ePlanReviewNo
Description
LARRY MILLER SUBARU-MITSUBISHI - (Showroom Remodel) - To constructed new perimeter foundations and install new store front glazing at three existing attached exterior roof covered areas. This is being done to increase the area of the interior showrooms. This will include 675 sq. ft. at the Subaru showroom, 675 sq. ft. at the Mitsubishi showroom and a 625 sq. ft. sales tower area at the front (south) side of the building. This remodel will increase the interior area of the building, but does not increase the existing building area. This permit also includes the installation of new flooring and ceiling finishes at certain portions of the showroom areas and the service waiting room areas. 1st. floor: 18,375 sq. ft. 2nd floor: 2,530 sq. ft. Total: 20,905 sq. ft. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Case Summary (BLD)  5/14/2012 DONE
Permanent Occupancy  7/30/2010 DONE
DetailsTisha Gallop
On 11/8/06 tenant should have been issued a certificate of occupancy upon final inspection not a letter of compliance.
Case Summary (BLD)  4/14/2008 DONE
BLD-Conference11/8/200611/9/200611/9/2006ADONE
DetailsJim Sly
Internet Inspection Request from: Patricia Smith
BLD-Final11/8/200611/9/200611/8/2006APASS
DetailsJim Sly
blane; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
OK for Perm Occ. :)
Code Occupancy Approval  11/8/2006 PASS
Letter of compliance  11/8/2006 DONE
Letter of Compliance issued 11-8-06.
COD-Stop Work/Reinspection DR6/12/20066/12/20067/10/2006PDONE
DetailsCarol Montgomery
paid under case # cod06-00918 customer receipt # 3200300000000010018
BLD-Final6/5/20066/6/20066/6/2006ANR
DetailsJim Sly
Phone #: Blaine ###-####
Talked to Blaine....trying to get a variance landscape rock in leiu of bark.......Need Code enforce final......Blaine said that they didn't do any HVAC and Electrical was existing. They didn't run any new circuits.
FIRE-Final Inspection6/1/20066/2/20066/2/2006PPASS
DetailsTroy Cobbley
Life safety finaled
FIRE-Final Inspection5/31/20066/1/20066/1/2006PCANC
DetailsTroy Cobbley
Scheduled by a contractor via Hello! on 5/31/2006 at 2:30:06 PM. Contact: ###-####. per blaine tanner change time
FIRE-Final Inspection5/23/20065/23/20065/24/2006PFAIL
DetailsTroy Cobbley
don coatworth ; Phone #: ###-#### Two doors have been added that are not shown on the plans. All of the exits require exit discharge lighting and the plans call for the doors that cars come through to have panic hardware but they do not. Contractor is going to resubmit to John Menard with plan review and inspection will be called back in.
BLD-Final5/15/20065/16/20065/16/2006AFAIL
DetailsDave Hannah
blaine tanner -call 1st before insp; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie needs fire life/safty and code enforcement finals
BLD-Framing/Rough-in3/27/20063/27/20063/27/2006PPASS
DetailsJim Sly
Blaine Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong
BLD-Energy code compliance3/10/20063/13/20063/13/2006PPASS
DetailsTom Arcoraci
Blaine -- insulation and suspended ceiling; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong insul ok
BLD-Energy code compliance3/7/20063/8/20063/8/2006ANR
DetailsJim Sly
Blaine -- efis stucco insp and insulation; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong
Insulaters need to install approved vapor barreir that meets flame and smoke.
BLD-Framing/Rough-in2/16/20062/16/20062/16/2006PPASS
DetailsJim Sly
Blaine; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong
All framing pass
BLD-Foundation1/24/20061/25/20061/25/2006APART
DetailsJim Sly
Kenyon; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong
Found wall at E. 1/2 of front of bldg OK pend MTI special insp, tests and appr.
BLD-Footing1/20/20061/24/20061/24/2006APART
DetailsJim Sly
STS Contractors; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
Foot at E. 1/2 of front of Bldg.......OK pending MTI insp, tests, and approvals.
BLD-Conference1/11/20061/11/20061/12/2006PDONE
DetailsJim Sly
kenyon--; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
Issue PAID IN FULL permit  1/4/2006 DONE
Permit Ready to Issue  12/23/2005 DONE
Print Occupancy Form  12/23/2005 DONE
Telephone call  12/23/2005 DONE
left mess for a jeffery l fisher at ###-####
PLANS/APPL TAKEN TO FRONT DESK  12/22/2005 DONE
Plan Reviewer's activity  12/22/2005 PASS
Reviewed and approved the structural and non-structural resubmittals. JCM
Plan assigned to (JCM)11/8/2005 12/22/2005 PASS
12/22/2005 09:58:31 JCM - activity updated through activity BLDA022 from case BLD05-03132.
Routing - PLAN CHECK12/9/2005 12/22/2005 PASS
Plan resubmittals received  12/20/2005 DONE
Received 3 copies of plan sheets S-100, S-101 and 2 copies of plan sheets A-001, A-301, A-401 and forwarded to John M.
Plan resubmittals received  12/12/2005 DONE
Received 1 transmittal, 1 letter, 3 review comments, 2 cover sheets, 5 copys of sheets A-101, & 2 copys of sheets of A-110,A-301,A-401,A-601 Taken to John M.
Routing - FIRE11/29/2005 12/9/2005 PASS
1st review completed  12/9/2005 FAIL
failed plan check and structural.
Routing - PLAN CHECK11/21/2005 11/29/2005 FAIL
Plan resubmittals requested  11/29/2005 DONE
E-mailed the architect with a copy of the plan review requesting revisions. JCM
Plan resubmittals requested  11/28/2005 DONE
Faxed the architect a copy of the structural plan review requesting revisions. JCM
Routing Off Site - STRUCTURAL11/9/2005 11/25/2005 FAIL
Received an e-mailed plan review from the consulting structural engineer requesting revisions. JCM
Routing - PLANNING  11/21/2005 PASS
Approved per DRH05-00297 and as noted.
Routing - PLUMBING11/16/2005 11/17/2005 PASS
n/a appears to have no plumbing
Routing - PUBLIC WORKS11/15/2005 11/16/2005 PASS
Routing - Erosion and Sediment11/16/2005 11/16/2005 PASS
ESC plan waiver request approved with attached conditions.
Routing - PLANNING Land Div11/9/2005 11/15/2005 PASS
Application received  11/8/2005  
Recd Pcfee & Taken To Pln CK  11/8/2005 DONE
Plans ACCEPTED BY PLAN TECH  11/8/2005  
Fee Review-notes11/8/200511/8/2005