Permit Information
Permit NumberBLD05-03196
StatusFinaled
Name C-2 CONSTRUCTION
Site Address 1910 N GARDEN ST
Project NameSETTLERS IRRIGATION
Customer Number 
ePlanReviewNo
Description
(RCE-3010 C-2 Construction) Settlers Irrigation District - (Office & Maintenance Building) - To construct a 4,474 sq. ft. one story type VB office/maintenance building. Other work inlcudes all site improvements, paving and landscaping per approved plans and attachments, DRH05-00285. This project has been approved with a septic system and must be signed off by CDHD.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice BLD4/27/20074/27/20075/10/2007 DONE
Second Notice has not been responded to.
Second Notice BLD4/9/20074/9/20074/27/2007 DONE
First Notice has not been responded to.
First Notice 3/29/20074/9/2007 DONE
Code Occupancy Approval  4/5/2007 PASS
4-5-07 Research shows that Venneman signed off on the Final for me while on vacation.
BLD-Final3/29/20073/29/20073/29/2007PPASS
DetailsTom Arcoraci
mario; Phone #: ###-#### - please call 1/2 hr prior to inspection Internet Inspection Request from: Patricia Smith
Permanent Occupancy 3/29/20073/29/2007 DONE
Details
Permanent occupancy UNPAID FEE  3/29/2007 DONE
Perm. Occ. Cert. # 11504 issued 3-29-07 to Settlers Irrigation.
FIRE-Final Inspection3/1/20073/2/20073/2/2007PPASS
DetailsTroy Cobbley
life safety passed
FIRE-Final Inspection2/28/20073/1/20073/1/2007AFAIL
DetailsTroy Cobbley
Provide signage at the gate as discussed.
Code Occupancy Approval2/27/20072/27/20072/27/2007PFAIL
DetailsDena Gambrel
2-27-07 Failed. Need to submit and get approved an updated landscape plan with Design Review. They have changed planters. No bike rack, no above ground handicap sign, no curbing, no landscaping, no sprinkler system.
BLD-Final2/23/20072/23/20072/23/2007PFAIL
DetailsJim Storey
mario; Phone #: ###-#### Internet Inspection Request from: Cathy Chilesc/n on site
BLD-Aging Inspection1/9/20071/9/20071/9/2007 PASS
DetailsTom Arcoraci
wip
BLD-Energy code compliance10/31/200611/1/200611/1/2006PPASS
DetailsTom Arcoraci
bill; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
BLD-Framing/Rough-in10/31/200611/1/200611/1/2006PPASS
DetailsTom Arcoraci
bill; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
BLD-Framing/Rough-in10/20/200610/23/200610/23/2006APASS
DetailsTom Arcoraci
###-####
BLD-Framing/Rough-in10/17/200610/20/200610/20/2006ANR
DetailsTom Arcoraci
Darrel; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt job shack locked no plans
BLD-Framing/Rough-in9/18/20069/19/20069/19/2006PPART
DetailsTom Arcoraci
bill; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley roof ok
BLD-Foundation7/18/20067/19/20067/19/2006APART
DetailsTom Arcoraci
mario ; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley mti for spec insp
BLD-Concrete6/15/20066/15/20066/15/2006PPASS
DetailsJim Sly
mario; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
BLD-Footing6/8/20066/8/20066/8/2006PPASS
DetailsDave Hannah
mario - call prior to insp; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley
(F) Reprint permit  5/4/2006  
Issue PAID IN FULL permit  5/3/2006 DONE
Print Occupancy Form  4/18/2006 DONE
Telephone call  4/18/2006 DONE
tlk to nathan draper ###-#### that permit and fees are ready to be picked up needs GC, ESC, ACHD
Permit Ready to Issue  4/18/2006 DONE
Routing - PLANNING Land Div3/7/2006 4/17/2006 PASS
The required documentation was submitted showing that the property is a buildable lot.
PLANS/APPL TAKEN TO FRONT DESK  4/17/2006 DONE
Plan assigned to (MLO)11/18/2005 4/17/2006 PASS
4/17/2006 11:19:28 MLO - activity updated through activity BLDA022 from case BLD05-03196.
Plan resubmittals received  3/6/2006 DONE
received fax for property info for D. Abo.
Routing - PLANNING Land Div2/14/2006 2/15/2006 FAIL
applicant has not provided information per D. Abo from 11/23/05.
Routing - PLAN CHECK2/8/2006 2/14/2006 PASS
struc. approved 2/14/2006.
Routing Off Site - STRUCTURAL2/13/2006 2/14/2006 PASS
Sent out with Action Couriers
Routing - Erosion and Sediment2/6/2006 2/8/2006 PASS
ESC plan approved with attached conditions.
Routing - FIRE2/3/2006 2/6/2006 PASS
Faxed comments to architect. Attached comments to set of plans.
Routing - PLAN CHECK2/6/2006 2/6/2006 PEND
need struc revisions, planning land ? MLO
Routing - PLANNING1/30/2006 2/3/2006 PASS
Approved per DRH05-00285.
Plan resubmittals requested  1/31/2006 DONE
structural corrections
Plan resubmittals received  1/31/2006  
Received 1 copy of Irrigation Review Comments letter, 2 copies of SD1.0 and taken to Mike Otto
Routing Off Site - STRUCTURAL1/27/2006 1/31/2006 FAIL
Called action courriers for pick up
Routing - FIRE1/26/2006 1/27/2006 FAIL
Faxed review comments to architect. See attached comments.
Plan resubmittals received  1/26/2006 DONE
One copy of each; G1.0, S-2.1, A3.2, A3.3, 1 letter to Mike O, 1 review comments, 2 calcs taken to Mike Otto///BAS
Routing - PLAN CHECK1/24/2006 1/26/2006 PEND
need structural approval
Plan resubmittals requested  1/24/2006 DONE
Plan resub rec. on 1/23 incomplete. Architect contacted to provide additional structurctural sheets, calcs and letter. MLO
Plan resubmittals received  1/23/2006 DONE
Received 1 plan corrections,1 letter to Dave Henneman & Sam Rogers,1 calcs,1 special start up for special inspections & 2 copys of sheets G-1.0,SD-1.0,S-2.1,S-1.0,S-3.2,S-3.3,S-5.0 taken to Mike O.
Meeting  1/4/2006 DONE
Received following email from D. Hanneman: "I looked at the proposal for the turn around for them and I am okay with cutting a portion of the asphalt off for use of their heavy equipment. They are suppose to widen their part of the access road to 20 feet. I am not too happy with the ACHD part that is only 16 but not a lot we can do about that now. Dave"
I called architect and left message for him to call me to discuss this decision and the other items on our review that still need to be resubmitted before Fire can approve this permit.
1st review completed  12/12/2005 FAIL
failed public works, ESC, planning, plan check structural and fire.
Routing - PLAN CHECK12/12/2005 12/12/2005 PEND
Routing - FIRE12/5/2005 12/12/2005 FAIL
Review comments faxed to architect; resubmittal items include previously discussed FD access issues which have not been satisfactorily resolved with the FD.
Routing - PUBLIC WORKS12/8/2005 12/8/2005 PASS
WET LINE WAIVER HAS BEEN RECEIVED BY PUBLIC WORKS
Plan resubmittals requested  12/5/2005 DONE
IBC corrections
Routing Off Site - STRUCTURAL11/18/2005 12/5/2005 FAIL
corrections sent to architect
Routing - PLAN CHECK11/29/2005 12/5/2005 FAIL
corrections sent to architect
Plan resubmittals received  11/30/2005 DONE
Revised ESC plans received and taken to plan check where other submittals are in the routing process.
Routing - PLANNING11/25/2005 11/29/2005 FAIL
Applicant has not met the requirement for additional landscape as discussed in the plan intake meeting.
Routing - PLUMBING11/23/2005 11/25/2005 PASS
approved per plan and 2003 upc: building is proposed to be connected to private sewer disposal system.
Routing - Erosion and Sediment11/22/2005 11/23/2005 FAIL
ESC plan does not meet requirments per BMC 8-17 and plan desinger manual. Checklist completed and faxed to PD. Re-submittal will be required.
Routing - PUBLIC WORKS11/21/2005 11/22/2005 FAIL
We need a signed waiver agreement before sign off. See Sewer Rating.
Routing - PLANNING Land Div  11/21/2005 PEND
The applicant/owner must provide a survey reflecting the property description on the submitted deed. The applicant/owner must also show that the property has the required street frontage.
Recd Pcfee & Taken To Pln CK  11/18/2005  
Plans ACCEPTED BY PLAN TECH  11/18/2005  
Plan routing begun/NEW & ADDTN  11/18/2005  
Application received  11/17/2005  
Fee Review-notes11/18/200511/18/2005   
Routing Off Site - STRUCTURAL     
waiting for additional plans, calcs and response letter for review which were not included with resubs 1/23. Architect notified. MLO