Second Notice BLD | 4/23/2008 | 4/23/2008 | 4/25/2008 | | DONE |
Cathy Brown
|
|
|
First Notice has not been responded to.
|
First Notice | | 3/7/2008 | 4/23/2008 | | DONE |
|
|
|
|
Permanent Occupancy | | | 3/7/2008 | | DONE |
|
|
|
|
BLD-Final | 3/5/2008 | 3/5/2008 | 3/5/2008 | P | PASS |
Jim Sly
|
|
|
allen Phone #: ###-#### OK for Perm Occ. :)
|
Code Occupancy Approval | 2/27/2008 | 2/27/2008 | 2/27/2008 | P | PASS |
Carol Montgomery
|
|
|
|
BLD-Conference | 2/21/2008 | 2/22/2008 | 2/22/2008 | A | DONE |
Jim Sly
|
|
|
Phone # ? Go to site and check out. Talked to Alan ###-####. Will proceed to final.
|
BLD-Conference | 2/20/2008 | 2/21/2008 | 2/21/2008 | A | CANC |
Jim Sly
|
|
|
Call sign center and discuss req.for perm Occ.
|
FIRE-Alarm Testing | 12/12/2006 | 12/12/2006 | 12/12/2006 | P | PASS |
Troy Cobbley
|
|
|
Life safety finaled
|
FIRE-Final Inspection | 12/1/2006 | 12/4/2006 | 12/4/2006 | A | FAIL |
Troy Cobbley
|
|
|
Need fire alarm and fire sprinkler permits finaled and then life safety will be inspected.
|
BLD-Final | 7/26/2006 | 7/27/2006 | 7/27/2006 | P | PART |
Jim Sly
|
|
|
vern ; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley OK for Temp Occ..........OK to Perm, when Fire and Code enforce Perms.
|
FIRE-Final Inspection | 7/26/2006 | 7/27/2006 | 7/27/2006 | A | PASS |
Troy Cobbley
|
|
|
A temporary occupancy was given until the south tenant is complete
|
Temporary occupancy | | | 7/27/2006 | | DONE |
|
|
|
Temp. Occ. Cert. # 5422 issued 7-27-06 to The Sign Center.
|
BLD-Final | 7/24/2006 | 7/25/2006 | 7/25/2006 | P | CANC |
Jim Sly
|
|
|
Vern : ); Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt
|
FIRE-Final Inspection | 7/24/2006 | 7/25/2006 | 7/25/2006 | A | FAIL |
Troy Cobbley
|
|
|
Fire alarm inspection failed
|
FIRE-Final Inspection | 7/21/2006 | 7/21/2006 | 7/21/2006 | P | FAIL |
Troy Cobbley
|
|
|
Still need the fire alarm permit finaled. Life safety for the shell and Sign Company tenant is ok for a temporary occupancy once the fire alarm is a go. The south tenant work is ongoing at this time.
|
BLD-Final | 7/21/2006 | 7/21/2006 | 7/21/2006 | P | CANC |
Jim Sly
|
|
|
vern; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley
|
FIRE-Final Inspection | 7/19/2006 | 7/20/2006 | 7/20/2006 | A | FAIL |
Troy Cobbley
|
|
|
The fire alarm and fire spirnkler permits need t be finaled, exit signs and emergency lights need repaired and approved hardware installed on the second floor restroom doors.
|
FIRE-Conference | 6/28/2006 | 6/29/2006 | 6/29/2006 | A | DONE |
Troy Cobbley
|
|
|
Vern requested occupying the building with the first tenant while finish construction was taking place in the second tenant space. Per Dave Hanniman and I this will be ok as long as the fire sprinklers, fire alarm and fire life safety is complete for the shell and the tenant space that is going to be occupied.
|
BLD-Energy code compliance | 3/23/2006 | 3/24/2006 | 3/24/2006 | A | PASS |
Jim Sly
|
|
|
vern; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
|
BLD-Framing/Rough-in | 3/22/2006 | 3/22/2006 | 3/22/2006 | P | PASS |
Jim Sly
|
|
|
Vern -- prefer late afternoon; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong
|
BLD-Footing | 2/7/2006 | 2/7/2006 | 2/7/2006 | P | PART |
Jim Sly
|
|
|
slab and footing re-bar inspection//vern; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
Center (E.-W.) footing OK pending MTI special insp tests and approvals
|
BLD-Footing | 1/30/2006 | 1/31/2006 | 1/31/2006 | A | PART |
Jim Sly
|
|
|
vern nielson; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa Int pads at N 1/2 of Bldg
|
Routing - PLANNING Land Div | 1/25/2006 | | 1/27/2006 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 1/27/2006 | | 1/27/2006 | | PASS |
|
|
|
Permit and plans approved and taken to front desk.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/27/2006 | | PASS |
|
|
|
|
Print Occupancy Form | | | 1/27/2006 | | DONE |
|
|
|
|
Telephone call | | | 1/27/2006 | | DONE |
|
|
|
called ###-#### and told Ben Peterson that permit is ready and fee and need to pay sub04-00082 also
|
Permit Ready to Issue | | | 1/27/2006 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 1/27/2006 | | DONE |
|
|
|
|
Plan assigned to (JCB) | 11/23/2005 | | 1/27/2006 | | PASS |
|
|
|
1/27/2006 09:38:06 JCB - activity updated through activity BLDA022 from case BLD05-03243.
|
Routing - PLAN CHECK | 12/19/2005 | | 1/25/2006 | | PEND |
|
|
|
Routed plans to Planning/Land Division.
|
Telephone call | | | 12/29/2005 | | DONE |
|
|
|
Received telephone call from Ben Petersen of Larson Architects stating that the plans may now change. Another interior stairway may be installed in lieu of the exterior stairway shown. If this will be done new plans, details, and engineering design and calculations will be submitted and have to be worked back into the review process.
|
Routing - PLAN CHECK | 11/30/2005 | | 12/19/2005 | | PEND |
|
|
|
Permit approval dependent on approval by Planning/Land Division.
Ben Petersen or Rob Perez to let me know when these issues are resolved so plans can route back to Planning/Land Division for approval.
|
Plan resubmittals received | | | 12/1/2005 | | DONE |
|
|
|
Received 1 transmittal,2 responses,1 review comments & 2 copys of sheets A-0,A-1,A-2,A-4,A-5,S1.0,S2.0,S3.0 Taken to Jason B.
|
Routing - FIRE | 11/25/2005 | | 11/30/2005 | | PASS |
|
|
|
|
1st review completed | | | 11/30/2005 | | FAIL |
|
|
|
failed planning, planning land div, ESC and plan check.
|
Routing - PLAN CHECK | 11/21/2005 | | 11/25/2005 | | FAIL |
|
|
|
Plan review report e-mailed and faxed to architect. Plan resubmittals and written response required for further review. Plans to route to the Fire Department for review.
|
Plan resubmittals requested | | | 11/25/2005 | | DONE |
|
|
|
Plan resubmittals and written response required for further review.
|
Telephone call | | | 11/25/2005 | | DONE |
|
|
|
Discussed some of the issues that need to be addressed with Ben Petersen.
|
Plan resubmittals received | | | 11/23/2005 | | DONE |
|
|
|
Received Transmittal letter, & 3 copys of sheet A-1 Taken to Jason B.
|
Application received | | | 11/23/2005 | | |
|
|
|
|
Routing - PLANNING | 11/17/2005 | | 11/21/2005 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 11/16/2005 | | 11/17/2005 | | FAIL |
|
|
|
No building plan review done yet. Plans routed to Scott Spjute in Planning.
|
Routing - PLAN CHECK | 11/15/2005 | | 11/16/2005 | | FAIL |
|
|
|
|
Routing - Erosion and Sediment | 11/16/2005 | | 11/16/2005 | | PASS |
|
|
|
|
Routing - Erosion and Sediment | 11/14/2005 | | 11/15/2005 | | FAIL |
|
|
|
|
Routing - PUBLIC WORKS | 11/8/2005 | | 11/15/2005 | | PASS |
|
|
|
|
Routing - PLANNING | 11/7/2005 | | 11/8/2005 | | FAIL |
|
|
|
|
Routing - PLANNING Land Div | 11/8/2005 | | 11/8/2005 | | FAIL |
|
|
|
|