Third Notice BLD | 9/22/2008 | 9/22/2008 | 9/22/2008 | | DONE |
Cathy Brown
|
|
|
Second Notice has not been responded to.
|
Second Notice BLD | 8/11/2008 | 8/11/2008 | 9/22/2008 | | DONE |
Cathy Brown
|
|
|
First Notice has not been responded to.
|
First Notice | 7/22/2008 | 7/22/2008 | 8/11/2008 | | DONE |
Jim Storey
|
|
|
|
BLD-Final | 7/21/2008 | 7/22/2008 | 7/22/2008 | A | PASS |
Jim Storey
|
|
|
Wayne Phone #: ###-####
|
DOC - Permit Finaled | 7/22/2008 | 7/22/2008 | 7/22/2008 | P | PASS |
Jim Storey
|
|
|
|
FIRE-Final Inspection | 7/21/2008 | 7/21/2008 | 7/21/2008 | P | PASS |
Forrest France
|
|
|
Fire life safety finaled.
|
BLD-Aging Inspection | 6/3/2008 | 6/3/2008 | 6/10/2008 | | NR |
Jim Storey
|
|
|
pending 05 fir permit
|
BLD-Aging Inspection | 3/26/2008 | 3/26/2008 | 3/26/2008 | | NR |
Jim Storey
|
|
|
paul m is looking into permit / job
|
BLD-Aging Inspection | 1/16/2008 | 1/16/2008 | 1/17/2008 | | PASS |
Jim Storey
|
|
|
paul m is looking into permit / job
|
BLD-Aging Inspection | 11/15/2007 | 11/15/2007 | 11/16/2007 | | FAIL |
Jim Storey
|
|
|
pending fir permit.
|
BLD-Aging Inspection | 9/12/2007 | 9/12/2007 | 9/13/2007 | | NR |
Jim Storey
|
|
|
pending fir permit
|
BLD-Aging Inspection | 5/15/2007 | 5/15/2007 | 5/18/2007 | | PEND |
Jim Storey
|
|
|
others
|
BLD-Aging Inspection | 3/14/2007 | 3/14/2007 | 3/14/2007 | | PASS |
Jim Storey
|
|
|
wip
|
BLD-Aging Inspection | 12/14/2006 | 12/14/2006 | 12/14/2006 | | PASS |
Jim Storey
|
|
|
wip
|
BLD-Aging Inspection | 10/10/2006 | 10/10/2006 | 10/10/2006 | | FAIL |
Jim Storey
|
|
|
no call for insp.
|
BLD-Aging Inspection | 8/10/2006 | 8/10/2006 | 8/10/2006 | | PASS |
Jim Storey
|
|
|
wip
|
BLD-Aging Inspection | 5/17/2006 | 5/17/2006 | 5/17/2006 | | PASS |
Jim Storey
|
|
|
wip
|
Plan assigned to (JCM) | 1/19/2006 | | 2/15/2006 | | PASS |
|
|
|
2/15/2006 07:48:43 JCM - activity updated through activity BLDA022 from case BLD05-03247.
|
Issue & PRINT to be Invoiced | | | 2/15/2006 | | DONE |
|
|
|
|
Plan assigned from Web | 11/23/2005 | 12/3/2005 | 2/10/2006 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 2/10/2006 | | PASS |
|
|
|
Reviewed and approved plans at the Micron site. JCM
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/10/2006 | | DONE |
|
|
|
|
Routing - FIRE | 1/19/2006 | | 2/9/2006 | | PASS |
|
|
|
1/26/06 - Plans not ready; deferred review until next week 2/9/06-Passed at onsite review. AS and FA plans ready forreview but both need to be attached to this building permit project.
|
Plan Reviewer's activity | | | 1/26/2006 | | FAIL |
|
|
|
Plan not complete enough for review. Requested additional information for review next week. JCM
|
1st review completed | | | 1/26/2006 | | FAIL |
|
|
|
|
Application received | | | 11/23/2005 | | DONE |
|
|
|
This permit was created on the web by Paul Marcolina
|