Permit NumberBLD05-03298
StatusFinaled
Name TED MASON COMMERCIAL INC
Site Address 1889 N WILDWOOD AVE
Project NameSTEELWOOD FLEX CONDOS
Customer Number 
ePlanReviewNo
Description
(TED MASON SIGNATURE HOMES - CONDO UNITS 22 & 23 Building 3) This building is fire sprinklered for story increase and for fire flow. To construct a 5,139 square foot, 2 story office tenant space (2,675 square foot 1st story and 2,464 square foot 2nd story) within an existing 2 story building (5,550 square feet on the 1st story). The shell was constructed as a one story building under permit BLD05-01262. Work is to include concrete footings, steel columns, wood beams, wood floor joists, wood floor sheathing, interior walls, shear walls, suspended ceilings, 4 restrooms accessible to the disabled, and finishes. The work is required to comply with the approved drawings, the plan review report, and all applicable codes. The fire sprinkler system shall comply with NFPA 13 as regulated by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Fee Review-notes11/30/200511/30/20057/19/2007 DONE
Second Notice BLD5/9/20075/9/20075/10/2007 DONE
First Notice has not been responded to.
First Notice 4/23/20075/9/2007 DONE
Permanent occupancy  4/23/2007 DONE
Perm. Occ. Cert. # 11542 issued 4-23-07 to Ted Mason Signature Homes (offices)
BLD-Final4/19/20074/19/20074/19/2007PPASS
DetailsJim Sly
this just had a temp final now needs a final ###-#### Alan
OK for Perm Occ. :)
Permanent Occupancy 4/19/20074/19/2007 DONE
Details
Code Occupancy Approval  4/18/2007 PASS
FIRE-Final Inspection12/12/200612/12/200612/12/2006PPASS
DetailsTroy Cobbley
Life safety finaled
BLD-Final10/25/200610/25/200610/25/2006PPART
DetailsJim Sly
Alan = ); Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt
OK for Temp Occ. ..........
OK for Perm Occ. when Code Enforce Perms
FIRE-Final Inspection10/12/200610/12/200610/12/2006PFAIL
DetailsTroy Cobbley
Need fire alarm permits finaled first. The fire alarm permit was failed.
BLD-Conference9/20/20069/21/20069/21/2006APASS
DetailsJim Sly
allan; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley
BLD-Energy code compliance6/30/20067/5/20067/5/2006APASS
DetailsJim Sly
late am please// vern ###-####
BLD-Framing/Rough-in6/27/20066/28/20066/28/2006APASS
DetailsJim Sly
vern Note: 1st floor; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
1st Flr framing OK
BLD-Framing/Rough-in5/11/20065/12/20065/12/2006APART
DetailsJim Sly
partial framing insp///vern; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
OK to cover 1st flr ceiling and 2nd flr walls
BLD-Final5/9/20065/10/20065/10/2006ANR
DetailsJim Sly
Ted ###-####
Plan Reviewer's activity  3/28/2006 DONE
Called Ben Petersen (with Larson Architects) and told him that the drawings were ready to be picked up.
Routing - PLANNING3/21/2006 3/27/2006 PASS
approved.
Routing - PLAN CHECK3/10/2006 3/21/2006 PASS
Revised drawings approved.
Plan resubmittals received  3/10/2006  
Received 1 copy of cover letter transmittal, 1 copy of response letter, 2 copies of E0.0, E2.1L, E2.1P, E2.1S, A-1, A-2, A-5, A-6, A-7, M1.1 and taken to Carl W.
BLD-Footing2/8/20062/9/20062/9/2006APART
DetailsMike Jordan
vern; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa. Interior column pad footings for second floor addition.
Plan assigned to (CJW)12/9/2005 1/30/2006 PASS
1/30/2006 11:06:43 CJW - activity updated through activity BLDA022 from case BLD05-03298.
Routing - PLAN CHECK1/26/2006 1/30/2006 DONE
PLANS/APPL TAKEN TO FRONT DESK  1/30/2006 DONE
Print Occupancy Form  1/30/2006 DONE
Permit Ready to Issue  1/30/2006 DONE
Telephone call  1/30/2006  
called ###-#### and told Steven from Ted Mason Const. that permit is ready and fees
Issue PAID IN FULL permit  1/30/2006 DONE
Routing - PLANNING Land Div1/18/2006 1/26/2006 PASS
Steelwood Condo Subdivision (SUB04-00082) was recorded on 01/24/06.
Routing - PLAN CHECK1/3/2006 1/18/2006 PASS
Drawings approved after resubmittal review.
Plan resubmittals received  1/12/2006 DONE
Received 1 letter of transmittal,1 letter to Carl W., 1 plan review report,2 structural calcs, & 2 copys of sheets A-0,A-1,A-2,A-4,A-5,A-6,S1.0,S2.0,S3.0,M1.1,E0.0,E1.0,E2.1L,E2.1P,E2.1S taken to Carl W.
1st review completed  1/3/2006 FAIL
Routing - FIRE12/23/2005 1/3/2006 PASS
Review complete with notes.
Routing - PLAN CHECK12/15/2005 12/23/2005 FAIL
The IBC plan review was started on December 21, 2005 and was finished on December 23, 2005. Revised drawings were required. See the plan review report.
Routing - PLANNING12/14/2005 12/15/2005 PASS
Approved per DRH04-00230.
Routing - Erosion and Sediment12/13/2005 12/14/2005 PASS
ESC plan waiver request approved with attached conditions.
Routing - PUBLIC WORKS12/9/2005 12/13/2005 PASS
Routing - PLANNING Land Div12/9/2005 12/9/2005 FAIL
Condo plat is not recorded. See Dave Abo as units are being modified from original proposed condo plat.
Plans ACCEPTED BY PLAN TECH  11/30/2005  
Application received  11/30/2005  
Recd Pcfee & Taken To Pln CK  11/30/2005