Third Notice BLD | 3/29/2006 | 3/29/2006 | 9/22/2006 | | DONE |
|
|
|
Second Notice has not been responded to.
|
Second Notice BLD | 3/15/2006 | 3/15/2006 | 3/29/2006 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | 2/23/2006 | 2/23/2006 | 3/15/2006 | | DONE |
Dave Hannah
|
|
|
|
BLD-Final | 2/22/2006 | 2/23/2006 | 2/23/2006 | A | PASS |
Dave Hannah
|
|
|
please call 30 min prior//David; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong
|
DOC - Permit Finaled | 2/23/2006 | 2/23/2006 | 2/23/2006 | P | PASS |
Dave Hannah
|
|
|
|
FIRE-Final Inspection | 2/22/2006 | 2/22/2006 | 2/22/2006 | P | PASS |
Forrest France
|
|
|
c/n items have been completed, life safety is satisfactory.
|
FIRE-Final Inspection | 2/21/2006 | 2/22/2006 | 2/22/2006 | A | FAIL |
Troy Cobbley
|
|
|
repair the emergency light in the rear exit corridor and the exit sign/emergency light combo in the pass through near the front of the tenant
|
Inspection Record Card- Bld | | | 2/21/2006 | | DONE |
|
|
|
|
BLD-Framing/Rough-in | 1/9/2006 | 1/10/2006 | 1/10/2006 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 1/9/2006 at 6:56:50 AM. Contact: ###-####.
|
(F) Reprint permit | | | 12/20/2005 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 12/20/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/16/2005 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 12/16/2005 | | DONE |
|
|
|
|
Telephone call | | | 12/16/2005 | | DONE |
|
|
|
Spoke with Gene and told him that permit is ready & fees///12/16/05 @10:15am BAS
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/15/2005 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/15/2005 | | DONE |
|
|
|
|
Plan assigned to (R_H) | 12/9/2005 | | 12/15/2005 | | PASS |
|
|
|
12/15/2005 07:48:06 RMH - activity updated through activity BLDA022 from case BLD05-03299.
|
Routing - PLAN CHECK | 12/13/2005 | | 12/15/2005 | | PASS |
|
|
|
|
Routing - FIRE | | | 12/15/2005 | | PASS |
|
|
|
Minor remodel of existing restuarant, Field Verify
|
1st review completed | | | 12/15/2005 | | PASS |
|
|
|
|
Plan resubmittals received | | | 12/14/2005 | | DONE |
|
|
|
Received 3 copys of sheet E1.0 Taken to Ron H.
|
Routing - PLUMBING | 12/12/2005 | | 12/13/2005 | | PASS |
|
|
|
replacing public restroom fixtures/no kitchen work/approved per 2003 UPC
|
Plan resubmittals received | | | 12/12/2005 | | DONE |
|
|
|
Received an e-mail from Bud Fulleton (Central District Health) stating they did not need to conduct a review of the plans. Paper copy of e-mail is put in with the plan sets.
|
Routing - PUBLIC WORKS | 12/9/2005 | | 12/12/2005 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 12/1/2005 | | |
|
|
|
|
Application received | | | 11/30/2005 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 11/30/2005 | | |
|
|
|
|
Fee Review-notes | 11/30/2005 | 11/30/2005 | | | |
|
|
|
|