Third Notice | | 3/27/2006 | 3/27/2006 | | DONE |
|
|
|
|
Second Notice BLD | 3/15/2006 | 3/15/2006 | 3/24/2006 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 2/27/2006 | 3/15/2006 | | DONE |
|
|
|
|
Permanent occupancy UNPAID FEE | | | 2/27/2006 | | DONE |
|
|
|
Perm. Occ. Cert. # 10916 issued 2-27-06 to New Balance.
|
BLD-Final | 2/24/2006 | 2/24/2006 | 2/24/2006 | P | PASS |
Jim Sly
|
|
|
shane; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles OK for Perm Occ. :)
|
FIRE-Final Inspection | 2/23/2006 | 2/24/2006 | 2/24/2006 | A | PASS |
Troy Cobbley
|
|
|
Life safety finaled
|
Permanent Occupancy | | 2/24/2006 | 2/24/2006 | | DONE |
|
|
|
|
FIRE-Final Inspection | 2/23/2006 | 2/23/2006 | 2/23/2006 | P | FAIL |
Troy Cobbley
|
|
|
Provide correct sample tubes for the duct smoke detectors, lower the fire extinguisher in the back of the tenant and mount the one in the front of the tenant.
|
Print Occupancy Form | | | 2/17/2006 | | DONE |
|
|
|
|
BLD-Framing/Rough-in | 2/15/2006 | 2/15/2006 | 2/15/2006 | P | PART |
Tom Arcoraci
|
|
|
Shane -- for ceiling grid; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong front half ok
|
BLD-Framing/Rough-in | 2/14/2006 | 2/14/2006 | 2/14/2006 | P | NR |
Tom Arcoraci
|
|
|
Shane -- for ceiling grid; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong needs elec insp 1st
|
Code Occupancy Approval | 2/14/2006 | 2/14/2006 | 2/14/2006 | P | CANC |
Tom Arcoraci
|
|
|
|
BLD-Framing/Rough-in | 1/25/2006 | 1/26/2006 | 1/26/2006 | A | PASS |
Jim Sly
|
|
|
shane; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
|
FIRE-Conference | 1/19/2006 | 1/19/2006 | 1/19/2006 | P | DONE |
Troy Cobbley
|
|
|
brandon ; Phone #: ###-#### Met and discussed exit signs/emergency lights. I'm ok with deleting two of the four exit signs/emergency lights in the storage area. The occupant load is only four people for this area.
|
Issue PAID IN FULL permit | | | 1/6/2006 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 12/23/2005 | | 12/27/2005 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/27/2005 | | DONE |
|
|
|
|
Print Occupancy Form | | | 12/27/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/27/2005 | | DONE |
|
|
|
|
Telephone call | | | 12/27/2005 | | DONE |
|
|
|
called ###-#### and left voicemessage for Roger that permit is ready and fees
|
Plan assigned to (R_H) | 12/9/2005 | | 12/27/2005 | | PASS |
|
|
|
12/27/2005 06:51:55 RMH - activity updated through activity BLDA022 from case BLD05-03322.
|
Routing - FIRE | 12/19/2005 | | 12/23/2005 | | PASS |
|
|
|
Faxed comments to the architect.
|
1st review completed | | | 12/23/2005 | | PASS |
|
|
|
|
Case Summary (BLD) | | | 12/19/2005 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 12/12/2005 | | 12/19/2005 | | PEND |
|
|
|
No corrections required by building department review. Routed plans to fire on 12/19/05. Permit pending fire departments approval.
|
Routing - PUBLIC WORKS | 12/9/2005 | | 12/12/2005 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 12/7/2005 | | |
|
|
|
|
Application received | | | 12/2/2005 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 12/2/2005 | | |
|
|
|
|
Fee Review-notes | 12/2/2005 | 12/2/2005 | | | |
|
|
|
|