Third Notice | | 4/3/2006 | 4/3/2006 | | DONE |
|
|
|
|
Second Notice BLD | 3/29/2006 | 3/29/2006 | 3/30/2006 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 3/13/2006 | 3/29/2006 | | DONE |
|
|
|
|
Permanent occupancy UNPAID FEE | | | 3/13/2006 | | DONE |
|
|
|
Perm. Occ. Cert. # 10933 issued 3-13-06 to Nick-N-Willy's Take-N-Bake Piza.
|
BLD-Final | 3/1/2006 | 3/1/2006 | 3/1/2006 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 3/1/2006 at 8:20:35 AM. Contact: ###-####.
|
Permanent Occupancy | | 3/1/2006 | 3/1/2006 | | DONE |
|
|
|
|
FIRE-Final Inspection | 2/27/2006 | 2/27/2006 | 2/27/2006 | P | PASS |
Forrest France
|
|
|
Life safety passed inspection.
|
BLD-Framing/Rough-in | 2/9/2006 | 2/9/2006 | 2/9/2006 | P | PASS |
Jim Storey
|
|
|
Osman; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong
|
Issue PAID IN FULL permit | | | 1/31/2006 | | |
|
|
|
|
Print Occupancy Form | | | 1/30/2006 | | DONE |
|
|
|
|
Telephone call | | | 1/30/2006 | | DONE |
|
|
|
called ###-#### and told Chris that permit is ready and fees
|
Permit Ready to Issue | | | 1/30/2006 | | DONE |
|
|
|
|
Plan assigned to (JCB) | 12/20/2005 | | 1/27/2006 | | PASS |
|
|
|
1/27/2006 14:02:20 JCB - activity updated through activity BLDA022 from case BLD05-03410.
|
Routing - PLAN CHECK | 1/24/2006 | | 1/27/2006 | | PASS |
|
|
|
Permit and plans approved and taken to front desk.
|
Plan resubmittals received | | | 1/27/2006 | | DONE |
|
|
|
Received additional walk-in cooler info. via e-mail
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/27/2006 | | PASS |
|
|
|
|
Telephone call | | | 1/25/2006 | | DONE |
|
|
|
Contractor stated he would be faxing over information on the walk-in cooler today.
|
Routing - PLAN CHECK | 1/17/2006 | | 1/24/2006 | | FAIL |
|
|
|
Sent e-mail to design engineer and called contractor concerning the walk-in cooler door size. A new spec. sheet fax will be forthcoming showing compliance. When provided and approved, the permit can then be issued.
|
Telephone call | | | 1/24/2006 | | DONE |
|
|
|
Talked with Chris Miles of Repair Solutions. He stated he would fax over information concerning the size of the walk-in cooler door. When this is received and approved, the permit can be issued.
|
Plan resubmittals received | | | 1/18/2006 | | DONE |
|
|
|
Received 1 plan review comment narrative, 1 high freguency electronic ballasts, & 3 copys of sheets NW1,NW2,NW3,NW4,NW5,NW6,NW7,NW8,NW9,NW10,NW11,NW12,EN & 1 walk in specifications taken to Jason B.
|
1st review completed | | | 1/17/2006 | | FAIL |
|
|
|
Failed Plan Check
|
Routing - FIRE | 1/11/2006 | | 1/17/2006 | | PASS |
|
|
|
Faxed to architect. See attached comments.
|
Plan resubmittals requested | | | 1/11/2006 | | DONE |
|
|
|
Plan resubmittals and written response required for further review.
|
Routing - PLAN CHECK | 12/23/2005 | | 1/11/2006 | | FAIL |
|
|
|
Plan review e-mailed and faxed to design engineer. Plan resubmittals and written response required for further review. Plans to now route to the Fire Department for review.
|
Routing - PLUMBING | 12/20/2005 | | 12/22/2005 | | PASS |
|
|
|
Approved as noted to indirect waste 3 comp sink and per plan and 2003 UPC.
|
Routing - PUBLIC WORKS | 12/20/2005 | | 12/20/2005 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 12/19/2005 | | |
|
|
|
|
Application received | | | 12/16/2005 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 12/16/2005 | | |
|
|
|
|
Fee Review-notes | 12/16/2005 | 12/16/2005 | | | |
|
|
|
|