Third Notice BLD | 1/8/2007 | 1/8/2007 | 10/20/2015 | | DONE |
Cathy Chiles
|
|
|
This permit finaled on the web by Todd Weltner
|
MISC ACTIONS | | | 5/22/2008 | | PASS |
Bob Archibald
|
|
|
Notice of Compliance recorded with ADA County, Instrument # 108059804. Copies also sent to architect and owner.
|
Agreement of Future work | 6/15/2006 | 6/15/2007 | 6/15/2007 | | DONE |
Sam Rogers
|
|
|
An upgrade agreement allowing a deferral of one year for sprinklering the North by Northwest tenant space in this structure was approved by Dave Hanneman, Deputy Fire Chief and George Slane, Building Official. This tenant space must be sprinklered by June 15, 2007.
|
Fee Review-notes | 12/16/2005 | 12/16/2005 | 1/26/2007 | | DONE |
|
|
|
|
Second Notice BLD | 12/27/2006 | 12/27/2006 | 1/8/2007 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 10/13/2006 | 12/27/2006 | | DONE |
|
|
|
|
Permanent occupancy | | | 10/13/2006 | | DONE |
|
|
|
Perm. Occ. Cert. # 11249 issued 10-13-06 to the Ada County Justice Center.
|
BLD-Final | 10/11/2006 | 10/12/2006 | 10/12/2006 | A | PASS |
Dave Hannah
|
|
|
joe; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles ok for perm occ
|
BLD-Final | 10/10/2006 | 10/11/2006 | 10/12/2006 | A | DEFR |
Dave Hannah
|
|
|
joe; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
Permanent Occupancy | | 10/12/2006 | 10/12/2006 | | DONE |
|
|
|
|
Code Occupancy Approval | 10/10/2006 | 10/10/2006 | 10/10/2006 | P | PASS |
Wm. Michael Meloy
|
|
|
Compliance met.
|
MISC ACTIONS | | | 8/2/2006 | | PART |
Bob Archibald
|
|
|
Notice of Non-Compliance recorded with ADA County, Instrument # 106123904
|
BLD-Final | 7/7/2006 | 7/7/2006 | 7/7/2006 | P | PART |
Dave Hannah
|
|
|
JOE; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles ok for temp occ needs other trades to go perm needs to install fright elev needs to finish installing glass needs to fix ada rest rooms
|
FIRE-Final Inspection | 7/7/2006 | 7/7/2006 | 7/7/2006 | P | PASS |
Forrest France
|
|
|
Fire life safety correction notice items have been completed, inspection passed.
|
FIRE-Final Inspection | 7/6/2006 | 7/7/2006 | 7/7/2006 | A | CANC |
Forrest France
|
|
|
Joe; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt
|
BLD-Final | 7/5/2006 | 7/6/2006 | 7/6/2006 | P | NR |
Dave Hannah
|
|
|
joe; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley still needs fire sign offs
|
FIRE-Final Inspection | 7/5/2006 | 7/6/2006 | 7/6/2006 | A | FAIL |
Forrest France
|
|
|
Need to install exit signs per red line notes on approved plan set and as discussed on site, provide key box for FD use, provide sheetrock at the basement soffit where separation between fire sprinklers was designed, provide paint for flooring at the basement path of egress as indicated on approved plans, need to test emergency lighting at next inspection.
|
FIRE-Final Inspection | 6/30/2006 | 7/3/2006 | 7/3/2006 | A | CANC |
Forrest France
|
|
|
not ready per raylene -joe; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley
|
BLD-Final | 6/30/2006 | 7/3/2006 | 7/3/2006 | P | CANC |
Dave Hannah
|
|
|
not ready per raylene-joe; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley
|
BLD-Conference | 6/30/2006 | 6/30/2006 | 6/30/2006 | | FAIL |
Wm. Michael Meloy
|
|
|
Exterior Siding not on. OK to Bond for $4.000 for completion of of decorative siding.
|
BLD-Other | 6/15/2006 | 6/15/2006 | 6/15/2006 | P | PART |
Dave Hannah
|
|
|
Joe, ceiling grid; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt ceiling grid rest of rooms ok to cover after elec and fire r/is are completed
|
BLD-Framing/Rough-in | 5/24/2006 | 5/24/2006 | 5/24/2006 | P | PART |
Dave Hannah
|
|
|
Joe; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles ceiling grid center area ok to cover after elec r/i is approved
|
BLD-Framing/Rough-in | 5/9/2006 | 5/9/2006 | 5/9/2006 | P | PASS |
Dave Hannah
|
|
|
joe Note: at loading dock; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles 6th street side and basement restrooms ok to cover
|
MISC ACTIONS | | | 5/8/2006 | | |
|
|
|
received request for code modification from Cole+Poe arch. Taken to George S.
|
BLD-Energy code compliance | 4/19/2006 | 4/19/2006 | 4/19/2006 | P | PASS |
Dave Hannah
|
|
|
joe; Phone #: ###-#### Internet Inspection Request from: Rita DeYoung
|
BLD-Framing/Rough-in | 4/14/2006 | 4/17/2006 | 4/17/2006 | A | PASS |
Dave Hannah
|
|
|
Joe; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esongok to cover int walls
|
BLD-Energy code compliance | 4/11/2006 | 4/12/2006 | 4/12/2006 | A | PART |
Dave Hannah
|
|
|
Joe -- prefer late insp; call 1st before insp; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong west wall ok
|
BLD-Energy code compliance | 4/11/2006 | 4/11/2006 | 4/11/2006 | P | PART |
Dave Hannah
|
|
|
Joe -- prefer late insp; call 1st before insp; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong ext walls south and east ok
|
BLD-Framing/Rough-in | 4/7/2006 | 4/10/2006 | 4/10/2006 | A | PART |
Dave Hannah
|
|
|
###-#### joe ext only wall framing not per plan need arch ok ok to insulate if ok with arch also needs to remover osb out of ext walls
|
BLD-Energy code compliance | 4/7/2006 | 4/10/2006 | 4/10/2006 | A | NR |
Dave Hannah
|
|
|
###-#### joe
|
Plan Reviewer's activity | | | 2/14/2006 | | DONE |
|
|
|
Updated Fire Review notes scope of work to correspond with Plan Reviewers scope of work regarding the automatic sprinkler installation agreement requirements. Faxed udated review comments to Bruce Poe. -Scott Arellano - Fire Plan Review.
|
Routing - PLAN CHECK | 2/7/2006 | | 2/10/2006 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/10/2006 | | DONE |
|
|
|
|
Print Occupancy Form | | | 2/10/2006 | | DONE |
|
|
|
|
Telephone call | | | 2/10/2006 | | DONE |
|
|
|
Fred Gray from Vertical construction was here, gave him copy of fees and needs ACHD
|
Permit Ready to Issue | | | 2/10/2006 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 2/10/2006 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 12/20/2005 | | 2/10/2006 | | PASS |
|
|
|
2/10/2006 09:33:11 CJW - activity updated through activity BLDA022 from case BLD05-03413.
|
Routing - PLANNING | 2/6/2006 | | 2/7/2006 | | PASS |
|
|
|
Canopies added over windows. Approved.
|
Routing - FIRE | 2/6/2006 | | 2/6/2006 | | PASS |
|
|
|
Faxed review comments to architect. Attached comments to plans.
|
Routing - PLAN CHECK | 1/23/2006 | | 2/6/2006 | | PASS |
|
|
|
The drawings were approved after the resubmittal review.
|
Plan resubmittals received | | | 1/23/2006 | | DONE |
|
|
|
Received 1 letter of transmittal,1 fire code review response taken to Carl W.
|
Routing - FIRE | 1/14/2006 | | 1/23/2006 | | FAIL |
|
|
|
Requesting resubmittal clarifying controlled access egress doors.
|
1st review completed | | | 1/23/2006 | | FAIL |
|
|
|
Failed Plan check and Fire.
|
Plan resubmittals received | | | 1/20/2006 | | DONE |
|
|
|
Received 1 letter of transmittal ,1 plan review report2 plan review comments & 2 copys of sheets A2.0,A2.1,A2.3,A3.1,A3.2,A6.1,A6.2,A6.4,A8.1,A8.2 A8.3,A8.4,A8.5,A9.1,P0.0,P2.4,P2.6,M6.0 taken to Carl W.
|
Plan resubmittals received | | | 1/17/2006 | | DONE |
|
|
|
Received 1 transmittal letter,1 response,1 plumbing plan review taken to Carl W.
|
Routing - PLAN CHECK | 1/9/2006 | | 1/14/2006 | | FAIL |
|
|
|
The IBC plan review was started on January 7, 2006 and was finished on January 14, 2006. Revised drawings were required. See the plan review report.
|
Routing - PLUMBING | 1/4/2006 | | 1/9/2006 | | PASS |
|
|
|
pvb may be required at the eye wash at P-10
|
Routing - PLANNING | 12/22/2005 | | 1/4/2006 | | PASS |
|
|
|
Approved per DRH05-00230. Pending review by Susan Riggs for CUP05-00073 and CVA05-00019.
|
Routing - PUBLIC WORKS | 12/20/2005 | | 12/22/2005 | | PASS |
|
|
|
|
Plan resubmittals received | | | 12/21/2005 | | |
|
|
|
Received new certificate of value and 3 copies of plan sheets A1.11, A1.12, A1.13 and A1.14 and inserted into plans currently routing.
|
Pending Assignment by MYS | 12/16/2005 | | 12/20/2005 | | DONE |
|
|
|
12/20/2005 16:05:28 MYS - activity updated through activity BLDA172 from case BLD05-03413.
|
Plans ACCEPTED BY PLAN TECH | | | 12/19/2005 | | |
|
|
|
per Marlene, need to reprint and submit 3 copys of sheet A0.2
|
Plan resubmittals received | | | 12/19/2005 | | DONE |
|
|
|
A0.0, A0.1, A0.2, A1.11, A1.12, A1.13, A1.14, A1.15, A1.16, A2.0, A2.1, A2.2, A2.3, A2.4, A3.1, A3.2, A4.1, A5.1, A5.2, A5.3, A5.4, A6.1, A6.2, A6.4, A7.1, A7.2, A7.3, A7.4, A8.1, A8.2, A8.3, A8.4, A8.5 and A9.1. Resubmittals put in with the plans routing.
|
Application received | | | 12/16/2005 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 12/16/2005 | | |
|
|
|
|