Third Notice BLD | 8/18/2006 | 8/18/2006 | 9/25/2006 | | DONE |
|
|
|
Second Notice has not been responded to.
|
Second Notice BLD | 7/7/2006 | 7/7/2006 | 8/18/2006 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 6/15/2006 | 7/7/2006 | | DONE |
|
|
|
|
Permanent occupancy | | | 6/14/2006 | | DONE |
|
|
|
Perm. Occ. Cert. # 11078 issued 6-14-06 to Boise Pottery.
|
Code Occupancy Approval | 5/24/2006 | 5/24/2006 | 5/24/2006 | P | PASS |
Dena Gambrel
|
|
|
05-24-06 Site inspection shows that the landscaping is completed. Signed off on Final.
|
Permanent Occupancy | | 5/24/2006 | 5/24/2006 | | DONE |
|
|
|
|
BLD-Final | 3/10/2006 | 3/10/2006 | 3/10/2006 | P | PASS |
Tom Arcoraci
|
|
|
Steve; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong ok for perm when code enforcement signs perm
|
Temporary occupancy | | | 3/10/2006 | | DONE |
|
|
|
Temp. Occ. Cert. # 5383 issued 3-10-06 to Boise Pottery.
|
Code Occupancy Approval Temp | 3/9/2006 | 3/9/2006 | 3/9/2006 | P | PASS |
Dena Gambrel
|
|
|
03-09-06 Bond received in the amount of $738.04.
|
FIRE-Final Inspection | 3/7/2006 | 3/9/2006 | 3/9/2006 | A | PASS |
Troy Cobbley
|
|
|
Life safety finaled
|
Code Occupancy Approval Temp | 3/9/2006 | 3/9/2006 | 3/9/2006 | P | FAIL |
Dena Gambrel
|
|
|
03-09-06 Need to bond for the trees. Bond will be in the amount of $738.04.
|
BLD-Final | 3/1/2006 | 3/1/2006 | 3/2/2006 | P | NR |
Tom Arcoraci
|
|
|
Steve -- permit shows that electrical and plumbing signatures are required but contractor states that electrical and plumbing are NOT needed; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong
|
Telephone call | | | 2/14/2006 | | DONE |
|
|
|
Passed by location enroute to another facility and observed construction of canopy appears complete, area is stocked with products, several parked cars on site, appears as if it is open for business. Called architect to inquire on status since no final inspection has been requested and no CO issued. He thinks they are just stocking; he will follow up and advise us; ( and remind them of inspection/CO requirements).
|
Additional plans submitted | | | 2/7/2006 | | DONE |
|
|
|
2/1/06-Information submitted by L. K. Achitects from ADA cty indicates this is a 16' alley. Hold for D. Hanneman approval. 2/7/2006- D. Hanneman checked site and verified the alley is paved to over 20' width and therefore approved the existing alley as an acceptable FD vehicle access roadway. Architect advised by Scott Arellano via voice mail and a faxed letter (see attached documents).
|
BLD-Footing | 1/11/2006 | 1/13/2006 | 1/13/2006 | A | PART |
Mike Jordan
|
|
|
steve Note: before 2:00 pm for concrete; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles. wip. North footing complete, working on south footing.
|
Routing - PLAN CHECK | 1/10/2006 | | 1/11/2006 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/11/2006 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/11/2006 | | DONE |
|
|
|
|
Print Occupancy Form | | | 1/11/2006 | | DONE |
|
|
|
|
Telephone call | | | 1/11/2006 | | DONE |
|
|
|
called Steve Packard (applicant) ###-#### and told him permit is ready and fee
|
Issue PAID IN FULL permit | | | 1/11/2006 | | DONE |
|
|
|
|
Plan assigned to (JCM) | 12/20/2005 | | 1/11/2006 | | PASS |
|
|
|
1/11/2006 09:33:50 JCM - activity updated through activity BLDA022 from case BLD05-03417.
|
Routing - PLAN CHECK | 1/9/2006 | | 1/10/2006 | | |
|
|
|
|
Plan resubmittals received | | | 1/10/2006 | | DONE |
|
|
|
Received 2 transmittal letters, & 2 copys of sheet A3.1 A1.0 taken to John M.
|
Routing - FIRE | 1/10/2006 | | 1/10/2006 | | PASS |
|
|
|
See attached comments. Proper access agreement documentation must be provided to PDS prior to final inspection.
|
Routing - FIRE | 1/4/2006 | | 1/9/2006 | | FAIL |
|
|
|
called architect to discuss but no answer; left voce message to call me to discuss. faxed review to architect.
|
1st review completed | | | 1/9/2006 | | FAIL |
|
|
|
failed plan check public works and fire.
|
Plan resubmittals received | | | 1/6/2006 | | DONE |
|
|
|
Received 1 transmittal , & 2 copys of sheets A1.0,A3.1 Taken to John M.
|
Plan resubmittals requested | | | 1/4/2006 | | DONE |
|
|
|
E-mailed the architect with a copy of the plan review comment list requesting revisions. JCM
|
Routing - PLAN CHECK | 1/3/2006 | | 1/4/2006 | | FAIL |
|
|
|
|
Routing - PLANNING | 12/23/2005 | | 12/30/2005 | | PASS |
|
|
|
Routed to Cody Riddle; rerouted to Martin Santoyo.
Approved per DRH05-00343 (MGS).
|
Plan resubmittals received | | | 12/23/2005 | | DONE |
|
|
|
Received 5 copies of sheet A1.0 and forwarded them to Brian Murphy.
|
Routing - PUBLIC WORKS | 12/23/2005 | | 12/23/2005 | | PASS |
|
|
|
Routed plans back to Public Works from ESC after resubmittals received.
|
Routing - Erosion and Sediment | 12/22/2005 | | 12/23/2005 | | PASS |
|
|
|
ESC plan waiver request approved with attached conditions.
|
Routing - PUBLIC WORKS | 12/21/2005 | | 12/22/2005 | | FAIL |
|
|
|
Requires Drainage revisions: Contact Brian Murphy ###-####
|
Plan resubmittals received | | | 12/21/2005 | | DONE |
|
|
|
Received 4 copies of plan sheet A3.1 with revisions showing upgrade of existing restroom for accessibility. Inserted into plans and began routing.
|
Plans ACCEPTED BY PLAN CHECK | | | 12/21/2005 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN CHECK | | | 12/20/2005 | | PEND |
|
|
|
Talked to Oscar at Larry Knopp's office. Plans have been placed on hold until restroom remodel plans are submitted. He said they should be ready to submit by 12/21/05. Do not start routing until revised plans have been submitted.
|
Application received | | | 12/16/2005 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 12/16/2005 | | |
|
|
|
|
Fee Review-notes | 12/16/2005 | 12/16/2005 | | | |
|
|
|
|