Permit Information
Permit NumberBLD05-03461
StatusFinaled
Name BODO DEVELOPMENT INC
Site Address 314 S 9TH ST
Project NameBODO BLDG #4-Foster Bldg
Customer Number 
ePlanReviewNo
Description
(FOSTER BUILDING SEISMIC UPGRADE) This building will be fire sprinklered for story increase and for future code trade-offs. To upgrade an existing 8,665 square foot, 4 story with basement historic building (5 stories total). Each story has a floor area of about 1,733 square feet. Work is to include concrete footings, concrete shear walls, concrete beams, wood floor infills, floor and roof sheathing, bolted connections between the diaphragms (i.e. floors and roof) and the perimeter walls, steel headers and trimmers at new wall openings in masonry walls, an interior basement stairway, new roof insulation and roof covering, seismic joints between this building and the adjacent buildings, 3 hour fire doors, and new steel beam hangers. The work is required to comply with the approved drawings, the structural design, the plan review report, and all applicable codes. The fire sprinkler system shall comply with NFPA 13 as regulated by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Case Summary (BLD)  6/28/2007 DONE
Second Notice BLD7/7/20067/7/20068/15/2006 DONE
First Notice has not been responded to.
First Notice6/7/20066/7/20067/7/2006 DONE
DetailsDave Hannah
Letter of compliance  6/8/2006 DONE
Letter of Compliance issued 6-8-06
BLD-Conference6/6/20066/7/20066/7/2006PPASS
DetailsDave Hannah
Please call Paul to inspect. Thank you. ###-####
DOC - Permit Finaled6/7/20066/7/20066/7/2006PPASS
DetailsDave Hannah
BLD-Final6/7/20066/7/20066/7/2006PPASS
DetailsDave Hannah
Please call Paul to inspect. Thank you. ###-####
FIRE-Final Inspection4/21/20064/21/20064/21/2006PPASS
DetailsForrest France
The building fire alarm and sprinkler permits have been finaled, life safety for the permitted seismic upgrade work is acceptable.
BLD-Final4/20/20064/20/20064/20/2006PNR
DetailsDave Hannah
Frrest is scheduled to sign-off on the fire-life safety this afternoon. Please check with Forrest to ensure that you arrive after he has reviewed. We may have to schedule you for Friday morning...I hope not. Alex.
BLD-Final4/13/20064/14/20064/17/2006PNR
DetailsDave Hannah
Dave: We would like to do the final walk through for Foster in the after noon, around 2-3 so we still have time to get the letter of compliance from the city. Call me when you get here. needs fire sign off
BLD-Framing/Rough-in4/12/20064/13/20064/13/2006APART
DetailsDave Hannah
If possible first thing in the morning. Call Paul to review the entry stair and basement stair framing prior to drywall/cover-up. Thanks.front stairs ok but stairs into basement need to be rebuilt
BLD-Conference4/5/20064/5/20064/5/2006PPASS
DetailsDave Hannah
Please come to the office and call Alex and Paul. Thanks.
Inspection Record Card- Bld  2/14/2006 DONE
Telephone call  2/14/2006 DONE
called ###-#### and told Paul permit is ready and fee, also called ###-#### and left voicemessage for James Woodbury
Permit Ready to Issue  2/14/2006 DONE
Issue PAID IN FULL permit  2/14/2006 DONE
Routing - PLAN CHECK1/20/2006 2/13/2006 PASS
(2-6-06) One item on the plan review report had not been resolved. Waiting for resolution. (2-13-06) The drawings were approved after the resubmittal review.
Plan assigned to (CJW)12/28/2005 2/13/2006 PASS
2/13/2006 13:33:17 CJW - activity updated through activity BLDA022 from case BLD05-03461.
PLANS/APPL TAKEN TO FRONT DESK  2/13/2006 DONE
Plan resubmittals received  2/9/2006  
Received a transmittal letter and 3 copies of A1.1 and taken to Carl W.
Plan resubmittals received  2/3/2006  
Received 1 transmittal letter and 3 copies of each A0.1, A1.1, A1.2, A2.0, A3.0 and taken to Carl W.
Plan resubmittals received  2/2/2006  
Recewived 3 copies of each A0.1, A1.1, A1.2, A2.0, 3.0 and 1 copy of response letter taken to Carl W.
Routing Off Site - STRUCTURAL1/17/2006 1/24/2006 PASS
The structural drawings were approved by the Consultant Structural Engineer.
1st review completed  1/20/2006 FAIL
Failed Plan Check.
Routing - FIRE1/18/2006 1/20/2006 PASS
No review comments required at this stage of construction.
Routing - PLAN CHECK12/28/2005 1/18/2006 FAIL
The IBC plan review was started on January 14, 2006 and was finished on January 18, 2004. Revised drawings were required. See the plan review report.
Plan resubmittals received  1/12/2006 DONE
Received letter of transmittal , 3 plan check response & 3 copys of sheets S1.1,S2.1,S2.2,S3.1,S3.2 taken to Carl W.
Plans ACCEPTED BY PLAN TECH  12/28/2005 DONE
Application received  12/23/2005  
Recd Pcfee & Taken To Pln CK  12/23/2005 DONE
Fee Review-notes12/23/200512/23/2005   
Routing Off Site - STRUCTURAL12/28/2005   FAIL
Failed first review by the Consultant Structural Engineer.