BLD-Final | 5/23/2007 | 5/23/2007 | 5/23/2007 | P | PASS |
Tony Young
|
|
|
RALPH; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
DOC - Permit Finaled | 5/23/2007 | 5/23/2007 | 5/23/2007 | P | PASS |
Tony Young
|
|
|
c of o issued
|
BLD-Final | 5/21/2007 | 5/21/2007 | 5/21/2007 | P | FAIL |
Tony Young
|
|
|
ralph; Phone #: ###-#### Internet Inspection Request from: Delphine Kavanaugh need to finish misc things,,,
|
BLD-Final | 5/8/2007 | 5/8/2007 | 5/8/2007 | P | NR |
Tom Arcoraci
|
|
|
steve ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
|
BLD-Grading Inspection | 5/2/2007 | 5/2/2007 | 5/2/2007 | | DONE |
|
|
|
Final grading and drainage approved
|
BLD-Energy code compliance | 10/17/2006 | 10/17/2006 | 10/17/2006 | P | PASS |
Mike Jordan
|
|
|
steve; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
BLD-Framing/Rough-in | 10/13/2006 | 10/13/2006 | 10/13/2006 | P | PASS |
Tony Young
|
|
|
Phone #: ###-####
|
BLD-Framing/Rough-in | 10/12/2006 | 10/13/2006 | 10/13/2006 | A | CANC |
Tony Young
|
|
|
steve; Phone #: ###-#### out of time
|
BLD-Framing/Rough-in | 10/12/2006 | 10/12/2006 | 10/12/2006 | P | CANC |
Tony Young
|
|
|
steve; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
|
BLD-Framing/Rough-in | 10/10/2006 | 10/10/2006 | 10/10/2006 | P | FAIL |
Mike Jordan
|
|
|
steve; Phone #: ###-#### Internet Inspection Request from: Patricia Smith. Provide add. 2x6 under CG truss upstairs. Min 3 8d nails for truss connection(jack trusses.) Complete nailing of of all hangars. In stall missing floor to floor straps. Go over shear nailing, not as per plan. Fire block all furouts. c/n postd.
|
BLD-Wall cover | 9/27/2006 | 9/27/2006 | 9/27/2006 | P | CANC |
Tony Young
|
|
|
steve, shear; Phone #: ###-#### canc per contractor
|
BLD-Wall cover | 9/26/2006 | 9/27/2006 | 9/27/2006 | A | CANC |
Tony Young
|
|
|
Steve; Phone #: ###-#### Internet Inspection Request from: Darla Downs
|
BLD-Wall cover | 9/25/2006 | 9/26/2006 | 9/26/2006 | A | FAIL |
Tony Young
|
|
|
steve; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley no plans,, reinspection fee
|
BLD-Foundation | 8/17/2006 | 8/18/2006 | 8/18/2006 | A | PART |
Tony Young
|
|
|
steve; Phone #: ###-#### stair areas
|
BLD-Foundation | 8/17/2006 | 8/17/2006 | 8/17/2006 | P | CANC |
Tony Young
|
|
|
Clint; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt
|
BLD-Footing | 8/14/2006 | 8/15/2006 | 8/15/2006 | P | PART |
Tony Young
|
|
|
Clint; Phone #: ###-#### Internet Inspection Request from: Barbara Stitt stair and landscape ftgs
|
PubWorks Subgrade Approval | 8/9/2006 | 8/9/2006 | 8/9/2006 | | PASS |
|
|
|
Received letter from geotec approving foundation subgrade provided that minor amounts of loose fill are removed beneath retaining wall at rear of residence. Okay to schedule footing subgrade inspection. Inspector to verify that all loose material has been removed.
|
BLD-Foundation | 7/24/2006 | 7/25/2006 | 7/25/2006 | A | PASS |
Dave Hannah
|
|
|
clint; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
BLD-Footing | 7/18/2006 | 7/19/2006 | 7/19/2006 | P | PASS |
Mike Jordan
|
|
|
clint; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley
|
BLD-Footing | 7/13/2006 | 7/13/2006 | 7/13/2006 | P | CANC |
Tony Young
|
|
|
clint; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
PubWorks Subgrade Approval | 6/22/2006 | 6/22/2006 | 6/22/2006 | | PART |
|
|
|
Footing subgrade for the house is approved. Footing subgrade for the retaining wall in back must still be approved.
|
Issue PAID IN FULL permit | | | 5/22/2006 | | DONE |
|
|
|
|
Telephone call | | | 5/15/2006 | | DONE |
|
|
|
Spoke with Chuck and reminded him that permit is ready, fees and only good for 6 months///5/15/06 @ 3:02pm BAS
|
Telephone call | | | 3/31/2006 | | DONE |
|
|
|
left mess that permit is ready
|
OVERRIDE | | | 1/24/2006 | | |
|
|
|
|
Plan assigned to (SAM) | 12/27/2005 | 1/17/2006 | 1/24/2006 | | PASS |
|
|
|
1/24/2006 10:52:45 SAM - activity updated through activity BLDA022 from case BLD05-03471.
|
Telephone call | | | 1/24/2006 | | DONE |
|
|
|
tlk to tony ###-#### that permit and fees are ready to be picked up
|
Routing - PLAN CHECK | | | 1/24/2006 | | PASS |
|
|
|
|
Case Summary (BLD) | | | 1/24/2006 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/24/2006 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/24/2006 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/24/2006 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 1/18/2006 | | DONE |
|
|
|
1/18/06 14:25 I called and left a message for Tim J. to call me. I also called Gene with Glancey to let him know that I need to talk to the engineer about some foundation walls and beam locations. Plans are on hold.
1/20/06 I talked to Tim J. about the plans. He said the architect has the sections I need for the plans. I contacted the architect and they will get me the sections. Plans are on hold.
|
Routing - FIRE | 1/11/2006 | | 1/12/2006 | | PASS |
|
|
|
No fire sprinklers required (Afton Sub)
|
Routing - PLANNING | 12/30/2005 | | 1/11/2006 | | PASS |
|
|
|
routed to AW per CUP04-00066 ctc
|
Routing - Erosion and Sediment | 1/11/2006 | | 1/11/2006 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Routing - PUBLIC WORKS GRADING | 12/27/2005 | | 12/30/2005 | | PASS |
|
|
|
Approved as Category 3
|
Routing - PUBLIC WORKS | 12/30/2005 | | 12/30/2005 | | PASS |
|
|
|
|
Application received | | | 12/27/2005 | | |
|
|
|
|