Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD05-03471
StatusFinaled
Name SHILOH DEVELOPMENT LTD CO
Site Address 1393 W VILLA NORTE ST
Project Name 
Customer Number 
ePlanReviewNo
Description
To construct a three bedroom, three and one quarter bathroom 2810 sq. ft. two story single family dwelling (1160 sq. ft. first floor/1075 sq. ft. second floor/585 sq. ft. basement) with a attached 628 sq. ft. two car garage, a 57 sq. ft. balcony off the first floor and a 56 sq. ft. covered back porch off the first floor. Per approved plans, engineering and requirement list. CUP04-6 per Angela Wood with Planning and Zoning. This lot is within a hillside area and is subject to the hillside ordinance. A class "A" roof system and defensible area will be maintained. (SAM)
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final5/23/20075/23/20075/23/2007PPASS
DetailsTony Young
RALPH; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
DOC - Permit Finaled5/23/20075/23/20075/23/2007PPASS
DetailsTony Young
c of o issued
BLD-Final5/21/20075/21/20075/21/2007PFAIL
DetailsTony Young
ralph; Phone #: ###-#### Internet Inspection Request from: Delphine Kavanaugh
need to finish misc things,,,
BLD-Final5/8/20075/8/20075/8/2007PNR
DetailsTom Arcoraci
steve ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
BLD-Grading Inspection5/2/20075/2/20075/2/2007 DONE
Final grading and drainage approved
BLD-Energy code compliance10/17/200610/17/200610/17/2006PPASS
DetailsMike Jordan
steve; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
BLD-Framing/Rough-in10/13/200610/13/200610/13/2006PPASS
DetailsTony Young
Phone #: ###-####
BLD-Framing/Rough-in10/12/200610/13/200610/13/2006ACANC
DetailsTony Young
steve; Phone #: ###-####
out of time
BLD-Framing/Rough-in10/12/200610/12/200610/12/2006PCANC
DetailsTony Young
steve; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
BLD-Framing/Rough-in10/10/200610/10/200610/10/2006PFAIL
DetailsMike Jordan
steve; Phone #: ###-#### Internet Inspection Request from: Patricia Smith. Provide add. 2x6 under CG truss upstairs. Min 3 8d nails for truss connection(jack trusses.) Complete nailing of of all hangars. In stall missing floor to floor straps. Go over shear nailing, not as per plan. Fire block all furouts. c/n postd.
BLD-Wall cover9/27/20069/27/20069/27/2006PCANC
DetailsTony Young
steve, shear; Phone #: ###-####
canc per contractor
BLD-Wall cover9/26/20069/27/20069/27/2006ACANC
DetailsTony Young
Steve; Phone #: ###-#### Internet Inspection Request from: Darla Downs
BLD-Wall cover9/25/20069/26/20069/26/2006AFAIL
DetailsTony Young
steve; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley
no plans,, reinspection fee
BLD-Foundation8/17/20068/18/20068/18/2006APART
DetailsTony Young
steve; Phone #: ###-####
stair areas
BLD-Foundation8/17/20068/17/20068/17/2006PCANC
DetailsTony Young
Clint; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt
BLD-Footing8/14/20068/15/20068/15/2006PPART
DetailsTony Young
Clint; Phone #: ###-#### Internet Inspection Request from: Barbara Stitt
stair and landscape ftgs
PubWorks Subgrade Approval8/9/20068/9/20068/9/2006 PASS
Received letter from geotec approving foundation subgrade provided that minor amounts of loose fill are removed beneath retaining wall at rear of residence. Okay to schedule footing subgrade inspection. Inspector to verify that all loose material has been removed.
BLD-Foundation7/24/20067/25/20067/25/2006APASS
DetailsDave Hannah
clint; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
BLD-Footing7/18/20067/19/20067/19/2006PPASS
DetailsMike Jordan
clint; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley
BLD-Footing7/13/20067/13/20067/13/2006PCANC
DetailsTony Young
clint; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
PubWorks Subgrade Approval6/22/20066/22/20066/22/2006 PART
Footing subgrade for the house is approved. Footing subgrade for the retaining wall in back must still be approved.
Issue PAID IN FULL permit  5/22/2006 DONE
Telephone call  5/15/2006 DONE
Spoke with Chuck and reminded him that permit is ready, fees and only good for 6 months///5/15/06 @ 3:02pm BAS
Telephone call  3/31/2006 DONE
left mess that permit is ready
OVERRIDE  1/24/2006  
Plan assigned to (SAM)12/27/20051/17/20061/24/2006 PASS
1/24/2006 10:52:45 SAM - activity updated through activity BLDA022 from case BLD05-03471.
Telephone call  1/24/2006 DONE
tlk to tony ###-#### that permit and fees are ready to be picked up
Routing - PLAN CHECK  1/24/2006 PASS
Case Summary (BLD)  1/24/2006  
PLANS/APPL TAKEN TO FRONT DESK  1/24/2006 DONE
Inspection Record Card- Bld  1/24/2006 DONE
Permit Ready to Issue  1/24/2006 DONE
Plan Reviewer's activity  1/18/2006 DONE
1/18/06 14:25 I called and left a message for Tim J. to call me. I also called Gene with Glancey to let him know that I need to talk to the engineer about some foundation walls and beam locations. Plans are on hold.

1/20/06 I talked to Tim J. about the plans. He said the architect has the sections I need for the plans. I contacted the architect and they will get me the sections. Plans are on hold.
Routing - FIRE1/11/2006 1/12/2006 PASS
No fire sprinklers required (Afton Sub)
Routing - PLANNING12/30/2005 1/11/2006 PASS
routed to AW per CUP04-00066 ctc
Routing - Erosion and Sediment1/11/2006 1/11/2006 PASS
ESC plan approved with attached conditions.
Routing - PUBLIC WORKS GRADING12/27/2005 12/30/2005 PASS
Approved as Category 3
Routing - PUBLIC WORKS12/30/2005 12/30/2005 PASS
Application received  12/27/2005