Case Summary (BLD) | | | 8/16/2011 | | DONE |
|
|
|
|
Third Notice BLD | 5/25/2007 | 5/25/2007 | 10/5/2007 | | DONE |
|
|
|
Second Notice has not been responded to.
|
Second Notice BLD | 5/9/2007 | 5/9/2007 | 5/25/2007 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | 4/17/2007 | 4/17/2007 | 5/9/2007 | | DONE |
Tom Arcoraci
|
|
|
|
BLD-Final | 4/17/2007 | 4/17/2007 | 4/17/2007 | P | PASS |
Tom Arcoraci
|
|
|
kent ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
|
DOC - Permit Finaled | 4/17/2007 | 4/17/2007 | 4/17/2007 | P | PASS |
Tom Arcoraci
|
|
|
|
BLD-Final | 4/12/2007 | 4/13/2007 | 4/13/2007 | P | CANC |
Mike Jordan
|
|
|
|
BLD-Final | 4/12/2007 | 4/13/2007 | 4/13/2007 | P | NR |
Mike Jordan
|
|
|
Kent; Phone #: ###-#### Internet Inspection Request from: Stacie Backus
|
BLD-Final | 4/12/2007 | 4/13/2007 | 4/13/2007 | A | NR |
Mike Jordan
|
|
|
Kent; Phone #: ###-#### Internet Inspection Request from: Stacie Backus. Needs other trades to final.
|
Code Occupancy Approval | 4/9/2007 | 4/9/2007 | 4/9/2007 | P | PASS |
Scott M.Brown
|
|
|
ok for final
|
BLD-Final | 4/6/2007 | 4/9/2007 | 4/9/2007 | A | NR |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 4/6/2007 at 2:39:28 PM.
|
FIRE-Final Inspection | 4/5/2007 | 4/5/2007 | 4/5/2007 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
CHANGE STATUS TO (ISS) | | | 1/12/2007 | | |
|
|
|
already issued previously
|
(F) Reprint permit | | | 1/4/2007 | | DONE |
|
|
|
|
Plan assigned to (JCM) | 12/8/2006 | | 1/2/2007 | | PASS |
|
|
|
1/2/2007 08:57:18 JCM - activity updated through activity BLDA022 from case BLD06-00007.
|
Routing - PLAN CHECK | 12/28/2006 | | 1/2/2007 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/2/2007 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/2/2007 | | DONE |
|
|
|
|
Telephone call | | | 1/2/2007 | | |
|
|
|
called Ken w/Camco ###-#### and told him plan mod is ready and fee
|
Permit Ready to Issue | | | 1/2/2007 | | |
|
|
|
|
Routing - FIRE | 12/27/2006 | | 12/28/2006 | | PASS |
|
|
|
Attached updated review comments to plans.
|
Routing - PLANNING | 12/22/2006 | | 12/27/2006 | | PASS |
|
|
|
Approved per findings of DRH04-00219 Modifications 1, 2, and 3.
|
Plan Reviewer's activity | | | 12/22/2006 | | PASS |
|
|
|
Reviewed and approved plan modification sheet submitted 12/7/06. JCM
|
Routing - PLAN CHECK | 12/11/2006 | | 12/22/2006 | | PASS |
|
|
|
|
BLD-Framing/Rough-in | 12/12/2006 | 12/13/2006 | 12/13/2006 | A | PASS |
Mike Jordan
|
|
|
kent ###-####. Framing for vestibule at outdoor patio for old chicago.
|
Override - Parcel Holds | | | 12/12/2006 | | |
|
|
|
|
Telephone call | | | 12/8/2006 | | DONE |
|
|
|
per marlene southard ok to take plans in with the general growth properties stamp
|
Plan Modification Accepted | | | 12/7/2006 | | |
|
|
|
plan mod excepted for bld06-00007 for the redesign of added future pad site to site plan & floor plans. revised landscape pot quantities. revised borders tower and middle roof framing plans. revised curb lines at cheesecake factory pad location. added detail references and dimensions - all other inspections ok except for the info above (41 pages)plans routed to john menard
|
BLD-Framing/Rough-in | 10/26/2006 | 10/27/2006 | 10/27/2006 | A | PART |
Mike Jordan
|
|
|
ken; Phone #: ###-#### Internet Inspection Request from: Patricia Smith. 2hr shaft wall, inner layer.
|
BLD-Framing/Rough-in | 10/13/2006 | 10/17/2006 | 10/17/2006 | A | PASS |
Mike Jordan
|
|
|
kent bowman ###-####. Framing at North tower. Verified holdowns and strapping.
|
Inspection Record Card- Bld | | | 10/13/2006 | | |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 10/13/2006 | | |
|
|
|
already issued previously-a plan mod
|
(F) Reprint permit | | | 10/13/2006 | | |
|
|
|
|
Telephone call | | | 10/9/2006 | | DONE |
|
|
|
tlk to dave hoffman ###-####-0230 that permit and fee are ready to be picked up
|
Permit Ready to Issue | | | 10/9/2006 | | DONE |
|
|
|
|
Plan assigned to (JCM) | 6/5/2006 | 6/5/2006 | 10/6/2006 | | PASS |
|
|
|
10/6/2006 10:56:36 JCM - activity updated through activity BLDA022 from case BLD06-00007.
|
Routing - PLAN CHECK | 6/15/2006 | | 10/6/2006 | | PASS |
|
|
|
PLAN MODIFICATION.
|
Plan resubmittals received | | | 10/6/2006 | | |
|
|
|
Received 1 page letter from David Hoffman addressed to John Menard, and 1 copy of sheet A300 and taken to John Menard
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/6/2006 | | DONE |
|
|
|
|
BLD-Framing/Rough-in | 9/29/2006 | 10/2/2006 | 10/2/2006 | A | PART |
Mike Jordan
|
|
|
Kent, ###-#### - partial only please. Lower tower and columns, canopy framing.
|
BLD-Final | 9/28/2006 | 9/28/2006 | 9/29/2006 | P | PART |
Mike Jordan
|
|
|
Kent, ###-####. THIS IS NOT REALLY A BLDG. FINAL. Pertains to maintenance bldg. addition only. All other trades have been sighned off on maintenance bldg. Mall wants to occupy this portion only. Checked with code enforcement and noted that no bond was needed. Ok to use maintenance bldg. only.
|
FIRE-Final Inspection | 9/28/2006 | 9/28/2006 | 9/28/2006 | P | FAIL |
Troy Cobbley
|
|
|
Inspection was actually for the addition to the maintenance shop. Life safety for this area only is passed. Fire sprinklers finished in this area.
|
FIRE-Final Inspection | 9/27/2006 | 9/27/2006 | 9/28/2006 | P | CANC |
Troy Cobbley
|
|
|
Duplicate inspection
|
BLD-Final | 9/26/2006 | 9/27/2006 | 9/27/2006 | A | NR |
Mike Jordan
|
|
|
kent - ###-#### final for maintenance building only . For maint. bldg. only. Still needs life/safety insp.
|
BLD-Framing/Rough-in | 9/22/2006 | 9/22/2006 | 9/22/2006 | P | PASS |
Mike Jordan
|
|
|
###-#### - kent. Upper tower framing.
|
BLD-Other | 9/11/2006 | 9/12/2006 | 9/12/2006 | A | PART |
Mike Jordan
|
|
|
###-#### - KENT - NOTE: WALL. 2 inch furout wall, 2nd floor.
|
BLD-Conference | 9/7/2006 | 9/8/2006 | 9/8/2006 | A | PASS |
Mike Jordan
|
|
|
kent bowman - ###-####. Grid ok. Also went over shaft wall and fireblocking requirements.
|
BLD-Wall cover | 9/7/2006 | 9/7/2006 | 9/7/2006 | P | PART |
Mike Jordan
|
|
|
###-#### - kent Note: wall framing. 2nd floor. Ceiling grid framing at lower roof. No approved details could be found. Contractor to schedule bldg. confrance tommorow.
|
BLD-Wall cover | 9/5/2006 | 9/6/2006 | 9/6/2006 | A | PASS |
Mike Jordan
|
|
|
###-#### - kent Note: wall framing. 2nd floor to top of wall exterior steel stud framing. Needs to install rock wall for fireblocking at floor ceiling lines.
|
BLD-Footing | 8/10/2006 | 8/10/2006 | 8/10/2006 | P | PASS |
Mike Jordan
|
|
|
jeremy - old chicago vestibule ###-####.
|
Override - Parcel Holds | | | 8/10/2006 | | |
|
|
|
|
BLD-Framing/Rough-in | 8/7/2006 | 8/7/2006 | 8/7/2006 | P | PASS |
Mike Jordan
|
|
|
jeremy - ###-####. exterior steel stud framing at sw end od bldg. (newq storefront.)
|
Override - Parcel Holds | | | 8/7/2006 | | |
|
|
|
|
Override - Parcel Holds | | | 8/7/2006 | | |
|
|
|
|
BLD-Energy code compliance | 8/3/2006 | 8/4/2006 | 8/4/2006 | A | PASS |
Mike Jordan
|
|
|
###-#### - jeremy. maintenance bldg.
|
Override - Parcel Holds | | | 8/3/2006 | | |
|
|
|
|
BLD-Framing/Rough-in | 8/1/2006 | 8/1/2006 | 8/1/2006 | P | PASS |
Mike Jordan
|
|
|
Jeremy, ###-####. Interior stell stud framing at maintenance bldg.
|
Override - Parcel Holds | | | 8/1/2006 | | |
|
|
|
|
BLD-Footing | 7/27/2006 | 7/28/2006 | 7/28/2006 | P | PASS |
Mike Jordan
|
|
|
jeremy - ###-####. Column pad fottings and grade beam footings on grid C.9 between grids 5 to 6. All reinforcement was as per approved plans. Also verified correct mix design for conc. placement. Noted no special insp. on site at time of conc. placement.
|
BLD-Footing | 7/26/2006 | 7/27/2006 | 7/27/2006 | A | PART |
Mike Jordan
|
|
|
###-#### - jeremy Note: if possible NOON. wip on coplumn pad footings by main enterance.
|
Override - Parcel Holds | | | 7/27/2006 | | |
|
|
|
|
Override - Parcel Holds | | | 7/26/2006 | | |
|
|
|
|
BLD-Framing/Rough-in | 6/21/2006 | 6/22/2006 | 6/22/2006 | A | PASS |
Mike Jordan
|
|
|
jeremy - ###-#### per rita - modification Reveiwed new UL listing for 2hr wall, consisting of 2 layers of 5/8 type X densglass, with typex rock on interior side.,
|
BLD-Framing/Rough-in | 6/21/2006 | 6/21/2006 | 6/21/2006 | P | FAIL |
Mike Jordan
|
|
|
duncan ###-####. Southwall not per approved UL listing for 2hr. wall. Contractor to get alternate method from architect if possible.
|
Override - Parcel Holds | | | 6/21/2006 | | |
|
|
|
|
Override - Parcel Holds | | | 6/21/2006 | | |
|
|
|
|
BLD-Footing | 6/19/2006 | 6/19/2006 | 6/20/2006 | P | DEFR |
Mike Jordan
|
|
|
###-#### rebar inspection. light pole base, non structural item.
|
Override - Parcel Holds | | | 6/19/2006 | | |
|
|
|
|
Routing - PLANNING | 6/9/2006 | | 6/15/2006 | | PASS |
|
|
|
PLAN MODIFICATION. Per CUP completed by Mark Pecchenino.
|
Routing - PLANNING | 6/7/2006 | | 6/9/2006 | | FAIL |
|
|
|
PLAN MODIFICATION. Failed Design Review. A staff level modification will be required for exterior building changes as well as site and landscape revisions. Contacted applicant via fax.
Routed to A. Wood per CUP.
|
Routing - PLAN CHECK | 6/5/2006 | | 6/7/2006 | | FAIL |
|
|
|
PLAN MODIFICATION.
|
Plan resubmittals requested | | | 6/7/2006 | | DONE |
|
|
|
PLAN MODIFICATION. E-mailed the architect a letter requesting clarification on the proposed plan modification. JCM
|
Telephone call | | | 6/5/2006 | | DONE |
|
|
|
PLAN MODIFICATION. Called and left voice message for Dave Hoffman that because the value went down on the overall project we owe them a refund so I would like to send back his plan mod check even tho we are charging the $500 and we will catch everything up at the end///6/5/06 @11:05am BAS
|
Plan Modification Accepted | | | 6/5/2006 | | |
|
|
|
Plan mod accepted for the redesign of Deleted tenants 1400, 1402 and 1404 to form construction pad for the Cheesecake Factory. Minor associated structural changes were made for rrouting mechanical duct work and equipment for tenant 1406. 2 COPIES OF EACH Sheets T, CC-1, LP-1, SA1, SA2, SA3, SA4, SA5, SA6, SA7, LS1, LS2, D100, D101, D200, S001, S100, S200, S201, S202, S300, S400, S401, S402, S403, S404, S405, S500, S501, S502, S503, S600, S700, A100, A101, A102, A103, A104, A105, A106, A200, A201, A202, A203, A204, A205, A206, A300, A301, A302, A303, A304, A305, A400, A401, A402, A403, A404, A405, A406, A407, A408, A409, A410, A411, A412, A413, A414, A415, A500, A700, A701, P1, P2, P3, P4, P5, P6, P7, P8, M1, M2, M3, M4, M5, M4, ED-1, E-1, E-2, E-3, E-4, E-5 and taken to John Menard
|
BLD-Other | 5/30/2006 | 5/31/2006 | 5/31/2006 | A | DEFR |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 5/30/2006 at 11:59:32 AM. Contact: ###-####.
|
BLD-Footing | 5/26/2006 | 5/30/2006 | 5/30/2006 | A | PASS |
Mike Jordan
|
|
|
jeremy -; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles. Column pad footings at grids 13 to 14 and grids A to A.5.
|
BLD-Other | 5/23/2006 | 5/23/2006 | 5/23/2006 | P | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 5/23/2006 at 7:33:05 AM. Contact: ###-####. Masonry insp. for maintenance bldg. Inspected rebar from 0 to 4ft. elev. Masons are planning 8ft high lift grout. Contractor noted that engineer has approved high lift grout and wiil send letter. Special insp. to verify cleanouts and that all steel is tied into place prior to grouting.
|
BLD-Footing | 5/18/2006 | 5/19/2006 | 5/19/2006 | A | FAIL |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 5/18/2006 at 9:06:33 AM. Contact: ###-####. footing and column pad footings on grids 7.4 to 10 and grids aa.1 to aa.4. top rebar mats missing in the column pad footings. Special insp. to verify the install of all missing rebar.
|
BLD-Footing | 5/11/2006 | 5/11/2006 | 5/11/2006 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 5/11/2006 at 7:35:58 AM. Contact: ###-####. Extension of exsiting column pad footing.
|
BLD-Footing | 5/10/2006 | 5/10/2006 | 5/10/2006 | A | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 5/10/2006 at 7:30:37 AM. Contact: ###-####. Footings for maintenance bldg. Special insp to verify addition of # 6 verts at 10ft overhrad doors.
|
Issue PAID IN FULL permit | | | 4/20/2006 | | DONE |
|
|
|
|
Telephone call | | | 4/13/2006 | | DONE |
|
|
|
lft vm with dave ###-#### 235 that permit and fees are ready to be picked up but needs ACHD
|
Permit Ready to Issue | | | 4/13/2006 | | DONE |
|
|
|
|
Plan assigned to (JCM) | 1/4/2006 | 1/4/2006 | 4/12/2006 | | PASS |
|
|
|
4/12/2006 09:39:03 JCM - activity updated through activity BLDA022 from case BLD06-00007.
|
Routing - PLANNING Land Div | 4/12/2006 | | 4/12/2006 | | PEND |
|
|
|
Building permit approved for work within area currently owned by applicant based on written agreement. Work for entire permit will be permited when deeds are recorded transfering land to applicant.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/12/2006 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 3/27/2006 | | 4/12/2006 | | PASS |
|
|
|
Plans are being issued with a condition that no construction will be done on the tenant improvement addition portion of this project until the lot line adjustment has been recorded and approved by Planning Land-Division. JCM
|
Inspection Record Card- Bld | | | 4/12/2006 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 3/27/2006 | | 3/27/2006 | | PASS |
|
|
|
Project under ESC05-01274
|
Routing - PLAN CHECK | 2/23/2006 | | 3/27/2006 | | |
|
|
|
|
Plan Reviewer's activity | | | 3/15/2006 | | PASS |
|
|
|
Reviewed and approved resubmitted plans sheets for structural and nonstructural compliance. JCM
|
Routing Off Site - STRUCTURAL | 3/15/2006 | | 3/15/2006 | | PASS |
|
|
|
Reviewed and approved structural resubmittals. JCM
|
Plan resubmittals received | | | 3/14/2006 | | DONE |
|
|
|
Received 1 response, 1 project start up for special inspections,1 seismic design category c,1 structural design calcs, & 3 copys of sheets T,D101,D200,S001,S100,S101,S200,S201,S400,S403,S405,S600,A100,A101,A103,A105,A200,A201,A202,A300,A301,A305,A402,A404,A407,A408,A413,A414,P8 taken to John M.
|
1st review completed | | | 2/23/2006 | | FAIL |
|
|
|
Failed Plan Check, ESC.
|
Routing - FIRE | 2/6/2006 | | 2/23/2006 | | PASS |
|
|
|
Attached review comments to plans. Faxed comments to architect.
|
Plan resubmittals requested | | | 2/14/2006 | | DONE |
|
|
|
E-mailed the architect a copy of the plan review report requesting revisions. JCM
|
Routing - PLAN CHECK | 2/6/2006 | | 2/6/2006 | | FAIL |
|
|
|
John M.
|
Routing - PLANNING | 1/19/2006 | | 2/6/2006 | | PASS |
|
|
|
Marty S. DRH04-00219 (1/24/2006) & Angela W. CUP04-00090 / Mark P. (Retuend from multiple day conference to find plans had been sitting in office for storage) (2/6/2006)
|
Routing - PLUMBING | 1/9/2006 | | 1/19/2006 | | PASS |
|
|
|
use boise city approved interceptor detail with sampling station for each interceptor.
|
Routing Off Site - STRUCTURAL | 1/4/2006 | | 1/19/2006 | | FAIL |
|
|
|
Called PDQ for pick up - Received a comment list from the consulting structural engineer requesting revisions. JCM
|
Plan resubmittals requested | | | 1/19/2006 | | DONE |
|
|
|
E-mailed the architect a copy of the comment list from the consulting structural engineer requesting revisions. JCM
|
Routing - Erosion and Sediment | 1/9/2006 | | 1/9/2006 | | FAIL |
|
|
|
ref existing esc permit: Prior ESC permit; ESC05-02293 was approved with attached conditions. No RP is yet provide to City of Boise and a contractor is called out. Informed applicant to have contractor informed Boise City of the person who is RP and a letter requesting that work be under prior ESC number.
|
Routing - PUBLIC WORKS | 1/5/2006 | | 1/9/2006 | | PASS |
|
|
|
|
Routing - PLANNING Land Div | 1/4/2006 | | 1/5/2006 | | FAIL |
|
|
|
The pending Record of Survey applications (ROS05-00003 & ROS05-00004) must be finaled and the Record of Survey and Notice of Buildable Parcels must be recorded prior to approval of the Building Permit.
|
Plan routing begun/NEW & ADDTN | | | 1/4/2006 | | |
|
|
|
|
Application received | | | 1/4/2006 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/4/2006 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 1/4/2006 | | |
|
|
|
Only 4 sets of civil plans submitted, 1 set was attached to the Issue set .
|
Fee Review-notes | 1/4/2006 | 1/4/2006 | | | |
|
|
|
|