Override - People Holds | | | 1/25/2010 | | |
|
|
|
|
Permanent Occupancy | | | 1/25/2010 | | DONE |
|
|
|
|
Telephone call | | | 10/19/2007 | | DONE |
|
|
|
lft vm with russ 10/19/2004 12:55 to get final values
|
Third Notice BLD | 3/21/2007 | 3/21/2007 | 4/23/2007 | | DONE |
|
|
|
Second Notice has not been responded to.
|
Second Notice BLD | 3/8/2007 | 3/8/2007 | 3/21/2007 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 2/9/2007 | 3/8/2007 | | DONE |
|
|
|
|
Code Occupancy Approval | | | 2/1/2007 | | PASS |
|
|
|
LANDSCAPE AND SIDDING IN PLACE FINAL AND RELEASE OF BOND APPROVED.
|
Permanent occupancy | | | 2/1/2007 | | DONE |
|
|
|
Perm. Occ. Cert. # 11422 issued 2-1-07 to the Dr. Roman Schwartsman Medical Office Bldg.
|
BLD-Aging Inspection | 1/19/2007 | 1/19/2007 | 1/19/2007 | | PASS |
Tom Arcoraci
|
|
|
|
Temporary occupancy | | | 12/19/2006 | | DONE |
|
|
|
Temp. Occ. Cert. # 5493 issued 12-19-06 to Dr. Roman Schwartsman.
|
BLD-Final | 11/16/2006 | 11/17/2006 | 11/17/2006 | P | PASS |
Tom Arcoraci
|
|
|
jim; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
FIRE-Final Inspection | 11/16/2006 | 11/17/2006 | 11/17/2006 | A | PASS |
Troy Cobbley
|
|
|
Life safety finaled. Stickers at the main doors to be corrected.
|
FIRE-Final Inspection | 11/3/2006 | 11/3/2006 | 11/3/2006 | P | CANC |
Forrest France
|
|
|
No time available to complete this inspection today.
|
BLD-Final | 11/2/2006 | 11/3/2006 | 11/3/2006 | P | NR |
Jim Sly
|
|
|
jim; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
|
PubWorks Occupancy Approval | 10/30/2006 | 10/30/2006 | 10/30/2006 | | DONE |
|
|
|
Signed off by R. Rokovitz 10/27/2006.
|
Code Occupancy Approval Temp | | | 10/30/2006 | | FAIL |
|
|
|
PAVERS, LANDSCAPE AND PARKING LOT MARKINGS NOT IN, SOME SIDDING AND BLOCKS NOT DONE OR PAINTED CAN NOT VERIFY COLORS. NEED TO BOND FOR $16,000.
|
FIRE-Final Inspection | 10/25/2006 | 10/26/2006 | 10/26/2006 | A | FAIL |
Troy Cobbley
|
|
|
Need fire alarm and fire sprinkler finaled first. I did a quick walk through of the life safety and found that the thumbturns on the first floor lobby doors need removed and the exit signs and emergency lights need testing. Other life safety items appear to be ok.
|
BLD-Other | 10/9/2006 | 10/9/2006 | 10/9/2006 | P | PASS |
Tom Arcoraci
|
|
|
jim Note: ceiling grid; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
BLD-Framing/Rough-in | 8/24/2006 | 8/25/2006 | 8/25/2006 | A | PART |
Tom Arcoraci
|
|
|
jim; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles cieling ok
|
FIRE-Conference | 8/8/2006 | 8/9/2006 | 8/9/2006 | A | DONE |
Troy Cobbley
|
|
|
Went over fire extinguisher placement with contractor
|
BLD-Framing/Rough-in | 8/8/2006 | 8/9/2006 | 8/9/2006 | A | PASS |
Tom Arcoraci
|
|
|
jim; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
BLD-Aging Inspection | 8/2/2006 | 8/2/2006 | 8/7/2006 | | NR |
Tom Arcoraci
|
|
|
|
BLD-Framing/Rough-in | 5/15/2006 | 5/15/2006 | 5/15/2006 | P | PART |
Jim Storey
|
|
|
jim --re-bar; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie ok by si report.
|
BLD-Other | 5/3/2006 | 5/3/2006 | 5/3/2006 | P | PART |
Jim Sly
|
|
|
jim Note: concrete; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles 1st CMU grout pour up to 4' ........ MTI on site.
|
BLD-Footing | 3/29/2006 | 3/29/2006 | 3/29/2006 | P | PART |
Tom Arcoraci
|
|
|
Jim; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong
|
(F) Reprint permit | | | 3/9/2006 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 3/8/2006 | | DONE |
|
|
|
|
Plan assigned to (JCM) | 1/9/2006 | | 2/27/2006 | | PASS |
|
|
|
2/27/2006 08:51:56 JCM - activity updated through activity BLDA022 from case BLD06-00008.
|
Routing - PLAN CHECK | 2/14/2006 | | 2/27/2006 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/27/2006 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/27/2006 | | |
|
|
|
|
Print Occupancy Form | | | 2/27/2006 | | DONE |
|
|
|
|
Telephone call | | | 2/27/2006 | | |
|
|
|
Informed Lowell Alseth (ZGA Architect & Planners) ###-#### to pick up permit; also informed Lowell that that R.P. and ACHD are needed 2-27-06 eus
|
Routing Off Site - STRUCTURAL | 2/21/2006 | | 2/24/2006 | | PASS |
|
|
|
Called Action Couriers for pick up - Received an e-mailed letter from the consulting structural engineer approving the final resubmittals. JCM
|
Plan resubmittals received | | | 2/21/2006 | | DONE |
|
|
|
Received 1 letter,3 structural calcs, & 3 copys of sheets S1.01,S1.02,S3.02,S6.01 taken to John M.
|
Plan resubmittals requested | | | 2/16/2006 | | DONE |
|
|
|
E-mailed the architect with a copy of the second comment letter from the consulting structural engineer. JCM
|
Routing Off Site - STRUCTURAL | 2/10/2006 | | 2/15/2006 | | FAIL |
|
|
|
Called Action Couriers for pick up - Received an e-mailed second review letter from consulting structural engineer requesting additional revisions. JCM
|
Routing - PLUMBING | 2/13/2006 | | 2/14/2006 | | PASS |
|
|
|
per plans and 2003 upc
|
Plan Reviewer's activity | | | 2/13/2006 | | PASS |
|
|
|
Reviewed and approved resubmittals. JCM
|
Routing - PLAN CHECK | 1/31/2006 | | 2/13/2006 | | PASS |
|
|
|
|
Plan resubmittals received | | | 2/8/2006 | | |
|
|
|
received 1 plan review comments letter, 3 copies of structural calcs, 2 copies of the following; G-001, G-002, C1.0, C2.0, C3.0, C4.0, C5.0, C6.0; 3 copies of the following; S0.1, S1.02, S1.03, S2.01, S3.02, S5.01; 2 copies of the following; A102,A104, A301, A302, A303, A401, P1.0, P2.1 and taken to John M.
|
Routing - PLANNING Land Div | 2/7/2006 | | 2/7/2006 | | PASS |
|
|
|
Property has been combined under one parcel number (R7198220087).
|
Permanent Occupancy | | 1/31/2006 | 1/31/2006 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 1/30/2006 | | 1/31/2006 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Plan resubmittals received | | | 1/31/2006 | | DONE |
|
|
|
Received 1 letter, & 1 copy of sheet C2.0 taken to John M.
|
Routing - FIRE | 1/26/2006 | | 1/30/2006 | | PASS |
|
|
|
Faxed to architect. See atttached comments.
|
1st review completed | | | 1/30/2006 | | FAIL |
|
|
|
Failed Plan Check
|
Plan resubmittals requested | | | 1/27/2006 | | DONE |
|
|
|
E-mailed the architect a copy of the comment list from the consulting structural engineer requesting revisions. JCM
|
Routing Off Site - STRUCTURAL | 1/9/2006 | | 1/26/2006 | | FAIL |
|
|
|
Called PDQ for pick up - Received and e-mailed comment list from the consulting structural engineer requesting revisions. JCM
|
Plan resubmittals requested | | | 1/26/2006 | | DONE |
|
|
|
E-mailed the architect with a copy of the plan review comment list requesting revisions. JCM
|
Routing - PLAN CHECK | 1/24/2006 | | 1/26/2006 | | FAIL |
|
|
|
John M.
|
Routing - PLANNING | 1/23/2006 | | 1/24/2006 | | PASS |
|
|
|
Approved per DRH05-00312.
|
Routing - PLUMBING | 1/17/2006 | | 1/23/2006 | | FAIL |
|
|
|
water lines in ceiling of garage must be protected from freezing, what method is to be used. boise city approved flammable liquids interceptor is to be used in the garage, downstream of a trapped area drain, resubmit drawing.
|
Routing - Erosion and Sediment | 1/20/2006 | | 1/20/2006 | | |
|
|
|
ESC resubmittal (2 copies of narrative) received.
|
Routing - Erosion and Sediment | 1/17/2006 | | 1/17/2006 | | FAIL |
|
|
|
ESC plan failed, no narrative included with plans. contacted PD.
|
Routing - PUBLIC WORKS | 1/11/2006 | | 1/17/2006 | | PASS |
|
|
|
|
Routing - PLANNING Land Div | 1/10/2006 | | 1/11/2006 | | FAIL |
|
|
|
The proposed building is located over the existing lot line between Lots 8 & 9. However, each lot has it's own parcel number. Property must be placed under one parcel number before land division is O.K.
|
Plans ACCEPTED BY PLAN TECH | | | 1/9/2006 | | |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 1/9/2006 | | |
|
|
|
|
Application received | | | 1/4/2006 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/4/2006 | | DONE |
|
|
|
|
Fee Review-notes | 1/4/2006 | 1/4/2006 | | | |
|
|
|
|