Case Summary (BLD) | | | 5/14/2013 | | DONE |
Tim L. Woodard
|
|
|
|
PRINT Activities | | | 7/15/2010 | | DONE |
|
|
|
|
FIRE-Final Inspection | 5/25/2006 | 5/26/2006 | 5/26/2006 | A | PASS |
Forrest France
|
|
|
andy; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
BLD-Final | 5/23/2006 | 5/23/2006 | 5/23/2006 | P | NR |
Dave Hannah
|
|
|
andy Note: late as possible; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
Case Summary (BLD) | | | 5/3/2006 | | |
|
|
|
|
BLD-Framing/Rough-in | 4/4/2006 | 4/5/2006 | 4/5/2006 | A | PASS |
Dave Hannah
|
|
|
andy ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
Issue PAID IN FULL permit | | | 2/27/2006 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/23/2006 | | |
|
|
|
|
Print Occupancy Form | | | 2/23/2006 | | DONE |
|
|
|
|
Telephone call | | | 2/23/2006 | | DONE |
|
|
|
left mess for mark sanders at ###-#### that permit is ready
|
Routing - PLAN CHECK | 1/26/2006 | | 2/22/2006 | | PASS |
|
|
|
Drawings approved after resubmittal revew.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/22/2006 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 1/10/2006 | | 2/22/2006 | | PASS |
|
|
|
2/22/2006 11:58:53 CJW - activity updated through activity BLDA022 from case BLD06-00011.
|
Telephone call | | | 2/13/2006 | | DONE |
|
|
|
Called the Architect. Asked him for the structural design required under permit BLD06-00012 and asked him to put the key notes back on Sheet A1.0.
|
Plan resubmittals received | | | 2/10/2006 | | DONE |
|
|
|
Received 1 project letter, & 2 copys of sheets A1.0,A2.1 taken to Carl W.
|
Routing - FIRE | 1/26/2006 | | 1/26/2006 | | PASS |
|
|
|
See attached comments.
|
1st review completed | | | 1/26/2006 | | FAIL |
|
|
|
Failed Plan Check.
|
Routing - PLAN CHECK | 1/10/2006 | | 1/24/2006 | | FAIL |
|
|
|
The IBC plan review was started on January 20, 2006 and was finished on January 23, 2006. Revised drawings were required. See the plan review report. This project wasn't immediately routed to Fire becasue the other 2 permits needed to be completed first.
|
Routing - PUBLIC WORKS | 1/10/2006 | | 1/10/2006 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 1/6/2006 | | |
|
|
|
|
Application received | | | 1/4/2006 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/4/2006 | | |
|
|
|
|
BLD-Final | 5/26/2006 | 5/30/2006 | | A | |
Dave Hannah
|
|
|
andy - call prior to insp; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|