BLD-Final | 9/12/2008 | 9/15/2008 | 9/15/2008 | A | PASS |
Jim Storey
|
|
|
Christine Phone #: ###-####
|
DOC - Permit Finaled | 9/15/2008 | 9/15/2008 | 9/15/2008 | P | PASS |
Jim Storey
|
|
|
|
BLD-Final | 9/11/2008 | 9/12/2008 | 9/12/2008 | A | FAIL |
Jim Storey
|
|
|
christine- call for access Phone #: ###-#### need safty glazing.
|
BLD-Wall cover | 6/14/2006 | 6/15/2006 | 6/15/2006 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 6/14/2006 at 1:54:48 PM.
|
BLD-Energy code compliance | 6/8/2006 | 6/13/2006 | 6/13/2006 | A | NR |
Jim Storey
|
|
|
john; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
BLD-Framing/Rough-in | 6/8/2006 | 6/13/2006 | 6/13/2006 | A | PART |
Jim Storey
|
|
|
john; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles framing ok pending stop work posted by mech insp.
|
BLD-Foundation | 2/20/2006 | 2/22/2006 | 2/22/2006 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 2/20/2006 at 3:31:53 PM. Contact: ###-####.
|
BLD-Footing | 2/20/2006 | 2/21/2006 | 2/21/2006 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 2/20/2006 at 3:31:02 PM. Contact: ###-####.
|
BLD-Footing | 2/15/2006 | 2/16/2006 | 2/16/2006 | A | PART |
Jim Storey
|
|
|
Jed; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong rework back setbacks
|
Issue PAID IN FULL permit | | | 2/15/2006 | | |
|
|
|
|
Plan assigned to (SAM) | 1/10/2006 | 1/19/2006 | 1/31/2006 | | PASS |
|
|
|
1/31/2006 09:32:49 SAM - activity updated through activity BLDA022 from case BLD06-00041.
|
Routing - PLAN CHECK | 1/13/2006 | | 1/31/2006 | | PASS |
|
|
|
|
Case Summary (BLD) | | | 1/31/2006 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/31/2006 | | DONE |
|
|
|
Only one set of plans approved due to red-lining.
|
Inspection Record Card- Bld | | | 1/31/2006 | | DONE |
|
|
|
|
Telephone call | | | 1/31/2006 | | DONE |
|
|
|
lft vm ###-#### jim johnston that permit and fees are ready to be picked up cmc
|
Permit Ready to Issue | | | 1/31/2006 | | DONE |
|
|
|
|
Plan resubmittals received | | | 1/27/2006 | | |
|
|
|
Received 2 copies of each A1.01, A1.02, A2.01, A2.02,A3.01,S1.01,S1.02,S1.03,E1.01 and taken to Steve Munroe
|
Telephone call | | | 1/26/2006 | | DONE |
|
|
|
please call John Johnston when ready ###-####
|
Plan Reviewer's activity | | | 1/20/2006 | | DONE |
|
|
|
14:05 I called and left a message for John Johnston to call me. I need entry door, deck joists engineered, correct foundation section and other foundation questions answered. Plans are on hold.
|
Routing - Erosion and Sediment | 1/13/2006 | | 1/13/2006 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Routing - PUBLIC WORKS | 1/12/2006 | | 1/12/2006 | | PASS |
|
|
|
|
Routing - PLANNING | 1/10/2006 | | 1/12/2006 | | PASS |
Tom Curren
|
|
|
design shows roof overhangs extend more than 2 ft into setbacks. Talked to architect Kevin McKeen. He agreed to remove items that extended more than 2 feet.
|
Application received | | | 1/10/2006 | | |
|
|
|
|