BLD-Final | 12/29/2006 | 12/29/2006 | 12/29/2006 | P | PASS |
Dave Hannah
|
|
|
Cindy Note: call 30 min before insp ; Phone #: ###-#### Internet Inspection Request from: Sherri Bennett
|
DOC - Permit Finaled | 12/29/2006 | 12/29/2006 | 12/29/2006 | P | PASS |
Dave Hannah
|
|
|
|
Routing - FIRE | 12/28/2006 | | 12/28/2006 | | PASS |
|
|
|
approved modified site plan per Sam Rogers, see attached scanned document //12/28/06 LEG
|
Plan Modification Accepted | | | 12/28/2006 | | PASS |
|
|
|
Modified site plan resubmitted showing driveway to be extended to 20' in width and letter from Strata Engr'g attesting (per inspection) that the driveway appears to be built to adequately support 70,000 lb GVW load. Plans approved as an acceptable alternative to a sprinkler system, subject to red-lined annotations on site plan indicating both sides of driveway to be widened at street to meet the 28' I/S and 48' O/S radius requirement; to be field verified.
|
BLD-Final | 12/22/2006 | 12/22/2006 | 12/22/2006 | P | NR |
Tony Young
|
|
|
j.p. - note - cert. of occupancy ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
|
BLD-Grading Inspection | 12/22/2006 | 12/22/2006 | 12/22/2006 | | BOND |
|
|
|
The rough grading and drainage has been completed at the above mentioned address. However, fine grading, revegetation, the roof drain connection to the ACHD storm drain, and as built grading plans have not been completed. For this the engineer has recommended a bond of $1,500.00. Upon receipt of this bond the grading and drainage is conditionally approved.
|
BLD-Final | 12/21/2006 | 12/21/2006 | 12/21/2006 | P | FAIL |
Dave Hannah
|
|
|
j.p. ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith needs terrys hillside final and a handrail on stairs of deck also nees to close up openning along side of stairs at riser
|
BLD-Energy code compliance | 9/19/2006 | 9/20/2006 | 9/20/2006 | A | PASS |
Dave Hannah
|
|
|
cindy; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley
|
BLD-Framing/Rough-in | 9/13/2006 | 9/14/2006 | 9/14/2006 | A | PART |
Dave Hannah
|
|
|
cindy; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley c/n on site ok to cover ext walls ok to insulate int all but for areas were hold downs are not finashed
|
BLD-Footing | 4/24/2006 | 4/25/2006 | 4/25/2006 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 4/24/2006 at 1:57:04 PM. Contact: ###-####. this was a foundation inspection
|
BLD-Foundation | 4/25/2006 | 4/25/2006 | 4/25/2006 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 4/24/2006 at 1:57:04 PM. Contact: ###-####.
|
BLD-Footing | 4/20/2006 | 4/21/2006 | 4/21/2006 | A | PASS |
Dave Hannah
|
|
|
jim; Phone #: ###-#### Internet Inspection Request from: Rita DeYoung
|
PubWorks Subgrade Approval | 4/19/2006 | 4/19/2006 | 4/19/2006 | | DONE |
|
|
|
Footing subgrade approved by geotechnical engineer
|
Inspection Record Card- Bld | | | 3/10/2006 | | DONE |
|
|
|
|
Telephone call | | | 3/10/2006 | | DONE |
|
|
|
lft vm ###-#### that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 3/10/2006 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 3/10/2006 | | DONE |
|
|
|
|
Plan assigned to (SAM) | 1/13/2006 | 3/8/2006 | 3/9/2006 | | PASS |
|
|
|
3/9/2006 15:21:31 SAM - activity updated through activity BLDA022 from case BLD06-00078.
|
Routing - PLAN CHECK | 3/6/2006 | | 3/9/2006 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 3/9/2006 | | DONE |
|
|
|
09:30 I called and left Cindy a message letting her know that I need some information. I need deck joist size and ridge beam size. Plans are on hold.
|
Case Summary (BLD) | | | 3/9/2006 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/9/2006 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 3/6/2006 | | 3/6/2006 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Routing - FIRE | 2/28/2006 | | 3/2/2006 | | PASS |
|
|
|
FD vehicle access shall be provided to within 150' of all points of any structure. Due to the set back of this house, FD vehicle access is not acceptable from the street. Therefore, this house will require an NFPA 13D automatic fire sprinkler system. An acceptable alternative is to resubmit revised plans showing the driveway to be a paved surface capable of supporting 70,000 lbs. GVW and 24,000 lbs. per axle, a minimum of 20'-0" wide, extending 90' in length from the intersection with the street, with a 48'-0" outside turning radius and 28'-0" inside radius at the intersection with the street.
|
Routing - Erosion and Sediment | 2/27/2006 | | 2/28/2006 | | FAIL |
|
|
|
ESC plan failed, no ESC application included in submittal. Notified PD, left vm.
|
Routing - PLANNING | 2/15/2006 | | 2/24/2006 | | PASS |
Tom Curren
|
|
|
No site was submitted. Contacted Cindy Wolstenholme 2/17. TAC Reviewed site plan 2/24/2004. Site Plan OK. TAC
|
Routing - PUBLIC WORKS GRADING | 2/15/2006 | | 2/15/2006 | | PASS |
|
|
|
Approved as Category 3
|
Routing - PUBLIC WORKS | 2/15/2006 | | 2/15/2006 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS GRADING | 1/13/2006 | | 1/18/2006 | | FAIL |
|
|
|
Drainage revisions required. Plan indicates collecting roof runoof and discharging across property line.
|
Application received | | | 1/13/2006 | | |
|
|
|
|