Third Notice BLD | 6/14/2006 | 6/14/2006 | 11/7/2007 | | DONE |
|
|
|
Second Notice has not been responded to.
|
Second Notice BLD | 5/25/2006 | 5/25/2006 | 6/14/2006 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 5/9/2006 | 5/25/2006 | | DONE |
|
|
|
|
Permanent occupancy UNPAID FEE | | | 5/9/2006 | | DONE |
|
|
|
Perm. Occ. Cert. # 11014 issued 5-9-06 to Dr. Sharon Oster.
|
FIRE-Final Inspection | 5/8/2006 | 5/8/2006 | 5/8/2006 | P | PASS |
Forrest France
|
|
|
Fire life safety passed final inspection, project related alarm and sprinkler permits are finaled.
|
BLD-Final | 5/8/2006 | 5/8/2006 | 5/8/2006 | P | PASS |
Dave Hannah
|
|
|
mike - ###-#### Note: late as possible; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles ok for perm occ
|
Permanent Occupancy | | 5/8/2006 | 5/8/2006 | | DONE |
|
|
|
|
FIRE-Final Inspection | 5/5/2006 | 5/5/2006 | 5/7/2006 | P | FAIL |
Forrest France
|
|
|
The project related fire sprinkler permit must be finaled before life safety building final approval. NOTE: the tenant has moved in prior to approval, notified the general contractor there will be no occupancy allowed prior to issuance of a certificate of occupancy.
|
BLD-Framing/Rough-in | 4/25/2006 | 4/25/2006 | 4/25/2006 | P | PART |
Dave Hannah
|
|
|
mike; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie ok to drop in ceiling grid
|
BLD-Energy code compliance | 3/20/2006 | 3/20/2006 | 3/20/2006 | P | PASS |
Dave Hannah
|
|
|
mike; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
|
BLD-Framing/Rough-in | 3/13/2006 | 3/13/2006 | 3/14/2006 | P | PASS |
Dave Hannah
|
|
|
Mike; Phone #: ###-####; 3rd floor Internet Inspection Request from: Elizabeth Esong
|
Issue PAID IN FULL permit | | | 3/1/2006 | | DONE |
|
|
|
|
Telephone call | | | 2/7/2006 | | DONE |
|
|
|
talked to cornel larson at ###-#### permit is ready
|
Permit Ready to Issue | | | 2/6/2006 | | DONE |
|
|
|
|
Print Occupancy Form | | | 2/6/2006 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/3/2006 | | DONE |
|
|
|
|
Plan assigned to (R_H) | 1/26/2006 | | 2/3/2006 | | PASS |
|
|
|
2/3/2006 09:37:29 RMH - activity updated through activity BLDA022 from case BLD06-00094.
|
Routing - PLAN CHECK | 1/31/2006 | | 2/3/2006 | | PEND |
|
|
|
No corrections required by building department review, routed plans to the fire department 2/3/06. Permit pending fire departments review.
|
Routing - FIRE | 2/3/2006 | | 2/3/2006 | | PASS |
|
|
|
Faxed To Architect. Attached comments to plans.
|
Case Summary (BLD) | | | 2/3/2006 | | DONE |
|
|
|
|
1st review completed | | | 2/3/2006 | | PASS |
|
|
|
|
Routing - PLUMBING | 1/30/2006 | | 1/31/2006 | | PASS |
|
|
|
120 deg. max. hot water to public lavs.
|
Routing - PUBLIC WORKS | 1/26/2006 | | 1/30/2006 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 1/18/2006 | | |
|
|
|
|
Application received | | | 1/17/2006 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/17/2006 | | |
|
|
|
|
Fee Review-notes | 1/17/2006 | 1/17/2006 | | | |
|
|
|
|
Routing - PLAN CHECK | 2/3/2006 | | | | |
|
|
|
|