Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD06-00104
StatusFinaled
Name MCCARTER-MOORHOUSE CO INC
Site Address 13905 W WAINWRIGHT DR
Project NameCALM OFFICE BLDG
Customer Number 
ePlanReviewNo
Description
Calm Office Building - (Orthodontist Office) - To finish and occupy a new 2, 544 sq. ft. office space for Doctor Stephan Morris within a 10,951 sq. ft. office shell building per approved plans and attachments. Permit for the shell building is BLD06-00102. This building is fully fire sprinkled for area. Energy requirements for this space for envelope and mechanical, wall and ceiling finishes, and doors are shown on the shell permit plans BLD06-00102. Fire sprinklers for area and as regulated by Boise Fire.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice BLD3/21/20073/21/20074/5/2007 DONE
Second Notice has not been responded to.
Fee Review-notes1/18/20061/18/20064/5/2007 DONE
Routing - Addressing6/29/2006 4/5/2007 PASS
Routing - PLAN CHECK7/11/2006 4/5/2007 PASS
Second Notice BLD3/8/20073/8/20073/21/2007 DONE
First Notice has not been responded to.
First Notice 2/16/20073/8/2007 DONE
FIRE-Final Inspection2/15/20072/16/20072/16/2007APART
DetailsTroy Cobbley
life safety finaled
FIRE-Final Inspection2/14/20072/15/20072/16/2007PPASS
DetailsTroy Cobbley
life safety finaled
Permanent occupancy  2/16/2007 DONE
Perm. Occ. Cert. # 11438 issued 2-16-07 to Dr. Stephan Morris.
BLD-Final2/14/20072/15/20072/15/2007PPASS
DetailsJim Sly
dana ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
OK for Perm Occ.
Permanent Occupancy 2/15/20072/15/2007 DONE
Details
BLD-Energy code compliance12/7/200612/8/200612/8/2006PPASS
DetailsJim Sly
dana ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
FIRE-Sprinkler Rough-in12/6/200612/7/200612/7/2006APASS
DetailsTroy Cobbley
Sprinkler piping is ok to cover
BLD-Energy code compliance11/30/200612/1/200612/1/2006APASS
DetailsJim Sly
dana ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
BLD-Framing/Rough-in11/28/200611/29/200611/29/2006APASS
DetailsJim Sly
dana ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
BLD-Aging Inspection10/11/200610/11/200610/11/2006 DONE
DetailsJim Sly
WIP
Telephone call  7/12/2006 DONE
lft vm with shan reeder ###-#### that permit and fees are ready to be picked up
Issue PAID IN FULL permit  7/12/2006 DONE
Case Summary (BLD)  7/11/2006  
PLANS/APPL TAKEN TO FRONT DESK  7/11/2006  
Permit Ready to Issue  7/11/2006 DONE
Print Occupancy Form  7/11/2006 DONE
Routing - FIRE7/7/2006 7/11/2006 PASS
Attached revised review comments to plans.
Plan assigned to (MLO)1/19/2006 7/11/2006 PASS
7/11/2006 11:01:16 MLO - activity updated through activity BLDA022 from case BLD06-00104.
Routing - PLUMBING6/30/2006 7/6/2006 PASS
additional cross connection protection may be required.
Routing - PUBLIC WORKS6/29/2006 6/30/2006 PASS
Routing - PLAN CHECK6/29/2006 6/29/2006 PASS
Plan resubmittals received  6/26/2006  
received "2" sets of plans 2 sheets of a-1, eo.o, e2.0l, e2.op, e2.os, e3.o, m-1, p-1, p-2, & p-3//plans taken to mike otto
Plan resubmittals requested  3/23/2006 HOLD
The engineer Shawn Reeder has provided a letter requesting that this permit be separated from the shell portion of the building. Separate plans are to be provided for this T.I. permit. Plans submitted on 1/18/2006 will be used for the shell only.. Routing for the resubmitted plans will start over. 3/23/2006 MLO
Routing - PLAN CHECK3/23/2006 3/23/2006 HOLD
New plans to be provided per engineer Shawn Reeder
Plan resubmittals received  3/21/2006 DONE
received 1 response, & 2 copys of sheets A-1,A-2,A-6,A-7 taken to Mike O.
Routing - PLAN CHECK3/6/2006 3/8/2006 FAIL
corrections for the T.I. have not been addressed. Sent fax to architect MLO
Plan resubmittals received  3/6/2006  
Received 1 copy of plan reveiw response letter from Architect, 2 copies of A-0, A-1, 1 copy of A-4, three copies of A-5 and taken to Mike O.
Routing - FIRE2/6/2006 2/7/2006 PASS
Approved pending satisfactory fullfillment of plan reviewers resubmittal request clarifying accuracy of mechanical plans.
1st review completed  2/7/2006 FAIL
Failed Plan Check and Planning.
Routing - PLAN CHECK1/31/2006 2/6/2006 FAIL
corrections sent to engineer
Plan resubmittals requested  2/6/2006 DONE
IBC , incomplete plans submitted for review. MLO
Routing - PLANNING1/31/2006 1/31/2006 FAIL
Need additional landscape information. Buffer of evergreen material needed along south yard. Note on landscape plan states "Area bermed and landscaped"; however, nothing is indicated in the yard. NOTE: This correction applied to the shell and not the tenant improvement which is totally interior and does not require planning approval. This correction was written on this permit for when submitted there was only one set of plans and the cross over occurred. A second set of plans has been provided after the shell permit was issued. MLO
Plans ACCEPTED BY PLAN TECH  1/18/2006  
Application received  1/18/2006  
Recd Pcfee & Taken To Pln CK  1/18/2006