Information based on query as of Saturday, June 29, 2024.
Permit Information
Permit NumberBLD06-00152
StatusFinaled
Name FIRST SERVICE GROUP
Site Address 1320 S MAPLE GROVE RD
Project NameFirst Service Group Bldg
Customer Number 
ePlanReviewNo
Description
(First Service Group Office Shell Building) To build a new 5800 square foot, one story, retail and office shell building and related site improvements. This building will be constructed of masonry exterior walls with wood framed interior walls and roof system. This is a shell permit only. There is no occupancy allowed under this permit. Separate tenant improvement permits will be required to finish this building for occupancy. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice BLD3/5/20083/5/20089/29/2008 DONE
DetailsCathy Brown
Second Notice has not been responded to.
Second Notice BLD1/9/20081/9/20083/5/2008 DONE
DetailsCathy Brown
First Notice has not been responded to.
First Notice12/21/200712/21/20071/9/2008 DONE
DetailsMike Jordan
BLD-Final12/21/200712/21/200712/21/2007PPASS
DetailsMike Jordan
DOC - Permit Finaled12/21/200712/21/200712/21/2007PPASS
DetailsMike Jordan
Attic access in canopy area provided. Letter of compliance issued.
BLD-Final11/8/200711/9/200711/9/2007APART
DetailsMike Jordan
Scheduled by a contractor via Hello! on 11/8/2007 at 3:06:32 PM. Contact: ###-####. Needs to provide attic access at front canopy area, everything else ok. Will issue letter of compliance once attic access has been provided.
Code Occupancy Approval11/9/200711/9/200711/9/2007PPASS
DetailsScott M.Brown
OK FOR FINAL
BLD-Final11/8/200711/8/200711/8/2007PNR
DetailsMike Jordan
Scheduled by a contractor via Hello! on 11/8/2007 at 10:58:59 AM. Contact: ###-####.
FIRE-Final Inspection11/7/200711/7/200711/7/2007PPASS
DetailsTroy Cobbley
life safety passed
PubWorks Occupancy Approval11/1/200711/1/200711/1/2007 DONE
FIRE-Final Inspection10/30/200710/30/200710/30/2007AFAIL
DetailsTroy Cobbley
Provide the city approved comments for both the shell adn tenant improvement, provide approved hardware on the exterior doors other than the main exit as discussed, provide approved hardware on the office doors, finish the installation of the remote annunciator and test the duct smoke detectors, provide address as discussed. I told the builder there may be other items that are addressed on the city comments.
Code Occupancy Approval Temp10/29/200710/29/200710/29/2007PFAIL
DetailsScott M.Brown
FAILED LANDSCAPE NOT CLOSE TO PLANS, NEED TO RESUBMIT/REPLACE AS SHOWN ON PLANS. BOND FOR LANDSCAPE IF OCCUPANCY NEEDED
BLD-Conference10/11/200710/12/200710/12/2007ADONE
DetailsJim Sly
blake Phone #: ###-####
Told Blake that he needs Public Works and Zoning to final.....B 4 calling for Structural final (for shell).
BLD-Framing/Rough-in3/16/20073/19/20073/19/2007APASS
DetailsMike Jordan
John; Phone #: ###-#### Internet Inspection Request from: Stacie Backus. Straps on roof have been insatalled. ok to cover.
BLD-Framing/Rough-in3/8/20073/9/20073/9/2007PPART
DetailsMike Jordan
john; Phone #: ###-#### Internet Inspection Request from: Victoria Beall. Needs to add straps on roof.
BLD-Foundation11/3/200611/3/200611/3/2006PCANC
DetailsMike Jordan
Scheduled by a contractor via Hello! on 11/3/2006 at 8:53:56 AM. Contact: ###-####.
BLD-Foundation11/2/200611/2/200611/2/2006PPASS
DetailsMike Jordan
Scheduled by a contractor via Hello! on 11/2/2006 at 10:31:05 AM. Contact: ###-####. Perimeter stemwalls.
BLD-Footing10/31/200610/31/200610/31/2006PPART
DetailsMike Jordan
Scheduled by a contractor via Hello! on 10/31/2006 at 8:50:21 AM. Contact: ###-####. wip. perimeter, all verts not yet tied. No special insp. required as per project start up sheet. Noted to contractor that conc. must be mech. vibrated.
(F) Reprint permit  10/25/2006  
Issue PAID IN FULL permit  10/24/2006  
Ready Permit EXTENDED  10/11/2006 DONE
see scanned document from jenifer g.
Ready Permit EXTENDED  10/11/2006  
Telephone call  9/19/2006 DONE
talked to zion zimmerman at ###-#### reason permit has not been picked up is had issues with p & z on the design review and waiting on achd-
Inspection Record Card- Bld  8/10/2006 DONE
Telephone call  8/10/2006 DONE
tlk to dion Zimmerman ###-#### that permit and fees are ready to be picked up but needs GC/RCE # and ACHD
Permit Ready to Issue  8/10/2006 DONE
Plan assigned to (JCM)1/26/2006 8/9/2006 PASS
8/9/2006 16:29:40 JCM - activity updated through activity BLDA022 from case BLD06-00152.
Routing - PLAN CHECK8/3/2006 8/9/2006  
Plan resubmittals received  8/9/2006  
Received 1pg. letter to John Menard from David Everson w/GJZ Architects and 2 copies of pages SD-1.0 & L-1.0; taken to John Menard
Routing - PLANNING8/9/2006 8/9/2006 PASS
Routing - PLAN CHECK8/9/2006 8/9/2006 PASS
PLANS/APPL TAKEN TO FRONT DESK  8/9/2006 DONE
Routing - PLANNING8/1/2006 8/3/2006 FAIL
Applicant has not submitted revised plans to DR for approval.

See attached letter to Dion Zimmerman
Routing Off Site - STRUCTURAL7/28/2006 8/1/2006 PASS
//C @ alled Action Courier for pick up :pm BAS - Received a faxed letter from the consulting structural engieer approving the final structural revisions. JCM
Routing - PLAN CHECK7/5/2006 8/1/2006  
Plan resubmittals received  7/28/2006  
Received 1 copy of cover letter, 1 copy of a letter from Holladay Engineering, 3 copies of A-3.0, A-3.1, A-3.2 and taken to John Menard
Plan resubmittals requested  7/24/2006 DONE
FAxed the architect a copy of the review letter from the consulting structural engineer. JCM
Routing Off Site - STRUCTURAL7/17/2006 7/24/2006 FAIL
Faxed the consulting structural engineer the final response to structural comments. JCM
Plan resubmittals received  7/14/2006  
Received comment items from the design structural engineer.
Plan resubmittals requested  7/6/2006 DONE
Faxed the architect a copy of the comment list from the consulting structural engineer requesting additioanl revisions. JCM
Routing Off Site - STRUCTURAL6/26/2006 7/6/2006 FAIL
Called Action Couriers for pick up - Received a faxed letter from the consulting structural engineer requesting additional revisions. JCM
Routing - FIRE6/30/2006 7/5/2006 PASS
Attached review comments to plans.
Routing - PLANNING6/29/2006 6/30/2006 FAIL
Applicant has not submitted revised plans to DR for approval.

See attached letter to Dion Zimmerman
Routing - Erosion and Sediment6/28/2006 6/29/2006 PASS
ESC plan approved with attached conditions.
Plan resubmittals received  6/28/2006  
received "3" sets of plans including 3 sheets of C-1.0, & C-2.0, also including an erosion app with 2 copies of storm water pollution prevention plans & 2 sets of erosion plans from stanley construction inc-& transmittal sheet from stanley consultants -plans taken to john menard.
Plan Reviewer's activity  6/28/2006 PASS
Reviewed and approved nonstructural resubmitted plans. JCM
Plan resubmittals received  6/21/2006  
Recieved 3 pg. response to comments, 3 copies of 3pg. "Project Start Up for Special Inspections", 3 copies of 4pg. structural calcs, 3 copies of the following pages: G-1.0, SD-1.0, L-1.0, S-1.0, S-2.0, S-2.1, A-3.0, A-3.1, A-3.2; taken to John Menard.
Routing - PLAN CHECK2/21/2006 2/28/2006 PASS
1st review completed  2/21/2006 FAIL
Failed Planning, Plan Check.
Routing - FIRE2/16/2006 2/21/2006 PASS
Attached review comments to plans. Faxed comments to architect.
Plan resubmittals requested  2/16/2006 DONE
E-mailed the architect a copy of the plan review comment list requesting revisions. JCM
Routing - PLAN CHECK2/7/2006 2/16/2006 FAIL
Plan resubmittals requested  2/10/2006 DONE
Faxed the architect a copy of the comment list from the consulting structural engineer requesting revisions. JCM
Routing Off Site - STRUCTURAL1/26/2006 2/8/2006 FAIL
Called Action Couriers for pick up - Received faxed comment list from the consulting structural engineer requesting revisions. JCM
Routing - PLANNING2/6/2006 2/7/2006 FAIL
DRH05-00208 approved the building to be located on the south side of Candleston Court. The applicant has not received Design Review approval for the proposed building. 2/7/06 SMS

Called Dion Zimmerman to let him know.
Routing - PLUMBING2/3/2006 2/6/2006 PASS
per plans and 2003 upc
Routing - Erosion and Sediment2/1/2006 2/3/2006 FAIL
ESC plan does not cover scope of work for structures: The esc submitted plan covers the development, utilities not structures. Informed applicant. Construction schedule is outdated.
Routing - PUBLIC WORKS1/31/2006 2/1/2006 PASS
Routing - PLANNING Land Div1/25/2006 1/31/2006 PASS
Property located in the Newcastle Heights Sub.
Plans ACCEPTED BY PLAN TECH  1/25/2006  
Recd Pcfee & Taken To Pln CK  1/23/2006  
Fee Review-notes1/23/20061/23/2006