BLD-Final | 12/21/2007 | 12/21/2007 | 12/21/2007 | P | PASS |
Dave Hannah
|
|
|
|
DOC - Permit Finaled | 12/21/2007 | 12/21/2007 | 12/21/2007 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Final | 12/20/2007 | 12/20/2007 | 12/20/2007 | P | CANC |
Dave Hannah
|
|
|
|
BLD-Final | 12/19/2007 | 12/20/2007 | 12/20/2007 | A | FAIL |
Dave Hannah
|
|
|
john Phone #: ###-#### everything is ok but for fire sprinkler permit needs to be finaled ok for cc after that
|
BLD-Final | 12/18/2007 | 12/18/2007 | 12/18/2007 | P | NR |
Mike Jordan
|
|
|
john Phone #: ###-####. Still needs fire final and plumbing.
|
BLD-Grading Inspection | 12/14/2007 | 12/14/2007 | 12/14/2007 | A | DONE |
|
|
|
Final grading and drainage approved
|
BLD-Energy code compliance | 12/20/2006 | 12/21/2006 | 12/21/2006 | A | PASS |
Dave Hannah
|
|
|
john - insulation ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith ok to cover
|
BLD-Framing/Rough-in | 12/15/2006 | 12/18/2006 | 12/18/2006 | A | PASS |
Dave Hannah
|
|
|
john; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles ok to insulate
|
BLD-Framing/Rough-in | 10/23/2006 | 10/24/2006 | 10/24/2006 | A | PART |
Dave Hannah
|
|
|
john - note: shear panel ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith ok to covcer ext
|
BLD-Foundation | 4/28/2006 | 5/1/2006 | 5/1/2006 | A | PASS |
Dave Hannah
|
|
|
larry; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
BLD-Footing | 4/19/2006 | 4/21/2006 | 4/21/2006 | A | PASS |
Dave Hannah
|
|
|
BRENT; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
PubWorks Subgrade Approval | 4/20/2006 | 4/20/2006 | 4/20/2006 | | DONE |
|
|
|
footing subgrade approved by the geotechnical engineer
|
Issue PAID IN FULL permit | | | 3/3/2006 | | DONE |
|
|
|
|
Plan assigned to (SAM) | 1/25/2006 | 3/1/2006 | 3/2/2006 | | PASS |
|
|
|
3/2/2006 11:08:57 SAM - activity updated through activity BLDA022 from case BLD06-00174.
|
Routing - PLAN CHECK | | | 3/2/2006 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 3/2/2006 | | PEND |
|
|
|
I called and talked to Eric Wolfe. He is going to get me girder truss locations so I can finish the plan review. I also called and talked to John Ryan. He is going to fax me his contractor registration number.
|
Case Summary (BLD) | | | 3/2/2006 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/2/2006 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/2/2006 | | |
|
|
|
|
Permit Ready to Issue | | | 3/2/2006 | | |
|
|
|
|
Inspection Record Card- Bld | | | 3/2/2006 | | DONE |
|
|
|
|
Telephone call | | | 3/2/2006 | | |
|
|
|
Left message with Ryan Construction Co ###-#### to pick up permit 3-2-06 eus
|
Routing - FIRE | 2/15/2006 | | 2/16/2006 | | PASS |
|
|
|
This house shall be provided with a modified NFPA 13D automatic fire sprinkler system. Modifications include sprinklers in all closets, baths, and foyers, and in addition attached garages shall be sprinklered with a single row of dry sidewall sprinklers along the wall between the garage and the house. (Boulder Heights Estates sub, aka El Paseo)
|
Routing - Erosion and Sediment | 2/14/2006 | | 2/15/2006 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Routing - PLANNING | 2/10/2006 | | 2/14/2006 | | PASS |
|
|
|
Routed to Angela Wood per CFH05-00050.
|
Routing - PUBLIC WORKS GRADING | 2/10/2006 | | 2/10/2006 | | PASS |
|
|
|
Approved as category 1 by CFH05-00050
|
Routing - PUBLIC WORKS | 2/10/2006 | | 2/10/2006 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS GRADING | 1/25/2006 | | 1/26/2006 | | FAIL |
|
|
|
retaining wall detail is for a 2 foot high wall. Needs 4.5 foot high wall detail. Plan must indicate where wall drain will discharge. These conditions were placed in hillside development approval letter fron 12/6/05.
|
Application received | | | 1/25/2006 | | |
|
|
|
|