Third Notice BLD | 6/14/2006 | 6/14/2006 | 8/7/2006 | | DONE |
|
|
|
Second Notice has not been responded to.
|
Second Notice BLD | 5/25/2006 | 5/25/2006 | 6/14/2006 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 5/9/2006 | 5/25/2006 | | DONE |
|
|
|
|
Permanent occupancy UNPAID FEE | | | 5/9/2006 | | DONE |
|
|
|
Perm. Occ. Cert. 11004 issued 5-2-06 to T 3 Wireless.
|
BLD-Final | 5/1/2006 | 5/2/2006 | 5/2/2006 | A | PASS |
Mike Jordan
|
|
|
Thad; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa. ok for perm occ.
|
Permanent Occupancy | | 5/2/2006 | 5/2/2006 | | DONE |
|
|
|
|
BLD-Final | 4/28/2006 | 5/1/2006 | 5/1/2006 | P | FAIL |
Mike Jordan
|
|
|
thab - Note: Late as possible Mon Morn; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles. Needs spreader bars on grid ceiling.
|
FIRE-Final Inspection | 4/28/2006 | 5/1/2006 | 5/1/2006 | A | PASS |
Troy Cobbley
|
|
|
fire life safety finaled
|
FIRE-Final Inspection | 4/27/2006 | 4/28/2006 | 4/28/2006 | P | FAIL |
Troy Cobbley
|
|
|
A fire extinguisher needs to be provided with an annual inspection tag. Also doors and hardware needs to be installed.
|
Print Occupancy Form | | | 4/26/2006 | | DONE |
|
|
|
printed new card per does not need plumbing sign off - see comments
|
Issue PAID IN FULL permit | | | 3/15/2006 | | DONE |
|
|
|
|
Plan assigned to (DRS) | 1/30/2006 | | 3/2/2006 | | PASS |
|
|
|
3/2/2006 09:30:36 DRS - activity updated through activity BLDA022 from case BLD06-00183.
|
Routing - PLAN CHECK | 2/13/2006 | | 3/2/2006 | | PASS |
|
|
|
Resubmittals of 2/28/06 inserted into plans. Taking plans to permit desk for issue.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/2/2006 | | PASS |
|
|
|
|
Permit Ready to Issue | | | 3/2/2006 | | |
|
|
|
|
Print Occupancy Form | | | 3/2/2006 | | DONE |
|
|
|
|
Telephone call | | | 3/2/2006 | | |
|
|
|
Informed Kyle (BRS Architects) ###-#### to pick up permit 3-2-06 eus
|
Plan resubmittals received | | | 2/28/2006 | | |
|
|
|
Received 1 copy transmittal letter and 3 copies of each A1.1 & A2.1 and taken to Dan S.
|
Routing - PLAN CHECK | 1/31/2006 | | 2/13/2006 | | FAIL |
|
|
|
Faxed and e-mailed copy of plan review items needing correction or addressed to the architect. Routing to fire code analyst for review.
|
Routing - FIRE | 2/13/2006 | | 2/13/2006 | | PASS |
|
|
|
Attached review comments to plans. Faxed to architect.
|
Plan resubmittals requested | | | 2/13/2006 | | DONE |
|
|
|
Faxed and e-mailed copy of plan review items needing correction or clarification to Kyle at BRS.
|
1st review completed | | | 2/13/2006 | | FAIL |
|
|
|
Failed plan check.
|
Routing - PUBLIC WORKS | 1/30/2006 | | 1/31/2006 | | PASS |
|
|
|
|
Pending Assignment by MYS | 1/25/2006 | | 1/30/2006 | | DONE |
|
|
|
1/30/2006 15:21:53 MYS - activity updated through activity BLDA168 from case BLD06-00183.
|
Plans ACCEPTED BY PLAN TECH | | | 1/27/2006 | | |
|
|
|
|
Application received | | | 1/25/2006 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/25/2006 | | |
|
|
|
|
Fee Review-notes | 1/25/2006 | 1/25/2006 | | | |
|
|
|
|