Letter of compliance | | | 8/14/2007 | | DONE |
|
|
|
Letter of Complance issued 8-14-07
|
BLD-Final | 8/9/2007 | 8/13/2007 | 8/13/2007 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 8/9/2007 at 3:13:04 PM. Contact: ###-####.
|
BLD-Final | 8/9/2007 | 8/9/2007 | 8/9/2007 | A | NR |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 8/9/2007 at 6:43:21 AM. Contact: ###-####.
|
FIRE-Final Inspection | 8/8/2007 | 8/8/2007 | 8/8/2007 | A | PASS |
Forrest France
|
|
|
Final fire life safety inspection passed.
|
FIRE-Alarm Testing | 8/7/2007 | 8/8/2007 | 8/8/2007 | A | PASS |
Forrest France
|
|
|
Inspection intended for fire life safety.
|
BLD-Final | 7/18/2007 | 7/19/2007 | 7/20/2007 | A | NR |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 7/18/2007 at 1:28:14 PM. Contact: ###-####. needs fire sprink and life saftey first
|
FIRE-Final Inspection | 7/18/2007 | 7/19/2007 | 7/19/2007 | A | FAIL |
Troy Cobbley
|
|
|
No inspection performed. Needs fire sprinkler final first.
|
BLD-Final | 4/26/2007 | 4/26/2007 | 4/26/2007 | P | CANC |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 4/26/2007 at 6:24:04 AM. Contact: ###-####.
|
BLD-Final | 4/26/2007 | 4/26/2007 | 4/26/2007 | A | NR |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 4/26/2007 at 6:24:04 AM. Contact: ###-####. needs fire life safty finals
|
FIRE-Final Inspection | 4/26/2007 | 4/26/2007 | 4/26/2007 | A | PART |
Forrest France
|
|
|
Need to complete related project permits pending completion of remodel work areas including the autology room for fire sprinkler and fire alarm as indicated on permit scope.
|
BLD-Wall cover | 3/7/2007 | 3/7/2007 | 3/7/2007 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 3/7/2007 at 6:40:18 AM. Contact: ###-####.
|
BLD-Aging Inspection | 7/27/2006 | 7/27/2006 | 7/31/2006 | | PASS |
Dave Hannah
|
|
|
|
Telephone call | | | 7/26/2006 | | DONE |
|
|
|
tlk to curtis that permit and fees are ready to be picked up
|
Override - Parcel Holds | | | 7/26/2006 | | |
|
|
|
|
Permit Ready to Issue | | | 7/26/2006 | | DONE |
|
|
|
|
(F) Reprint permit | | | 7/26/2006 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 7/26/2006 | | DONE |
|
|
|
|
Plan assigned to (DRS) | 7/12/2006 | 7/12/2006 | 7/25/2006 | | PASS |
|
|
|
7/25/2006 07:23:00 DRS - activity updated through activity BLDA022 from case BLD06-00205.
|
Routing - PLAN CHECK | 7/21/2006 | | 7/25/2006 | | PASS |
|
|
|
Plan Modification approved.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/25/2006 | | PASS |
|
|
|
Plan Mod to permit desk for re-issue.
|
Override - Parcel Holds | | | 7/25/2006 | | |
|
|
|
|
Inspection Record Card- Bld | | | 7/25/2006 | | DONE |
|
|
|
|
Routing - FIRE | 7/18/2006 | | 7/21/2006 | | PASS |
|
|
|
Attached revised review comments to plans.
|
Routing - PLAN CHECK | 7/12/2006 | | 7/18/2006 | | PEND |
|
|
|
Routing to fire code analyst.
|
CHANGE STATUS TO (REV) | | | 7/12/2006 | | DONE |
|
|
|
Plan Modification
|
Plans ACCEPTED BY PLAN TECH | | | 7/12/2006 | | |
|
|
|
|
Plan Modification Accepted | | | 7/11/2006 | | |
|
|
|
The phlebotomy Lab has been shifted in order to provide additional seating in the admitting area, previous area was 2,040 new area is 2,559. please note the previous location of the smoke barrier has shifted slightly to accommodate the locker and break area. Although the areas ,design,and function of the tenant inprovement are very similar,all sheets are resubmitted to avoid confusion.
|
Issue & PRINT to be Invoiced | | | 4/5/2006 | | DONE |
|
|
|
|
Plan assigned to (DRS) | 2/6/2006 | | 3/7/2006 | | PASS |
|
|
|
3/7/2006 07:40:44 DRS - activity updated through activity BLDA022 from case BLD06-00205.
|
Routing - PLAN CHECK | 3/3/2006 | | 3/7/2006 | | PASS |
|
|
|
No further reviews required. routing to permit desk to issue.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/7/2006 | | PASS |
|
|
|
|
Permit Ready to Issue | | | 3/7/2006 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/7/2006 | | DONE |
|
|
|
|
Telephone call | | | 3/7/2006 | | DONE |
|
|
|
talked to curtis at ###-#### that permit is ready
|
Routing - PLUMBING | 3/2/2006 | | 3/3/2006 | | PASS |
|
|
|
per plans, resubmittal letter on lab sink backflow protection, and 120 deg. hot water to public lavs, and 2003 upc. no r.ps. required.
|
Routing - PLAN CHECK | 2/27/2006 | | 3/2/2006 | | PEND |
|
|
|
Received response to plumbing plan review from Josh Howa. Attaching response to plans and re-routing plans back to plumbing plan review.
|
Plan resubmittals received | | | 3/2/2006 | | DONE |
|
|
|
Received letter of transmittal, one plumbing review response letter and one copy of sheet LS-3 taken to Dan S. (:rad
|
Routing - FIRE | 2/23/2006 | | 2/27/2006 | | PASS |
|
|
|
Attached review comments to plans. Faxed review comments to architect.
|
1st review completed | | | 2/27/2006 | | FAIL |
|
|
|
Failed plumbing.
|
Routing - PLAN CHECK | 2/13/2006 | | 2/23/2006 | | PEND |
|
|
|
No resubmittals required. Routing to fire code analyst for review.
|
Routing - PLUMBING | 2/7/2006 | | 2/13/2006 | | FAIL |
|
|
|
120 deg. max hot water to public lavs. hot and cold water reduced pressure backflow preventors required at the sink in lab 15202. if any lab work is done in 15107 water lines must also be protected. eyewash at sink in 15202 must be potable water supplied. provide a location with drainage to accept discharge for r.p.s, above.
|
Routing - PUBLIC WORKS | 2/6/2006 | | 2/7/2006 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 1/27/2006 | | |
|
|
|
|
Application received | | | 1/26/2006 | | |
|
|
|
|
Fee Review-notes | 1/26/2006 | 1/26/2006 | | | |
|
|
|
|