Case Summary (BLD) | | | 5/29/2008 | | DONE |
|
|
|
|
BLD-Final | 6/12/2007 | 6/12/2007 | 6/12/2007 | P | PASS |
Jim Sly
|
|
|
daryl - please call for access ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith C/C issued
|
DOC - Permit Finaled | 6/12/2007 | 6/12/2007 | 6/12/2007 | P | PASS |
Jim Sly
|
|
|
|
BLD-Energy code compliance | 8/31/2006 | 8/31/2006 | 8/31/2006 | P | PASS |
Jim Sly
|
|
|
michelle ; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley
|
BLD-Framing/Rough-in | 8/28/2006 | 8/28/2006 | 8/28/2006 | P | PASS |
Jim Sly
|
|
|
darby; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley
|
BLD-Footing | 7/7/2006 | 7/10/2006 | 7/10/2006 | A | PART |
Mike Jordan
|
|
|
pat; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley. Needs to add additional rebar at interior column pad footing. contractor was notified.
|
BLD-Footing | 7/7/2006 | 7/7/2006 | 7/7/2006 | P | CANC |
Jim Sly
|
|
|
per pat - nr///blb darby-- ###-#### cell --late pm if possible
|
Issue PAID IN FULL permit | | | 7/7/2006 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/6/2006 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 7/6/2006 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/6/2006 | | DONE |
|
|
|
|
Telephone call | | | 7/6/2006 | | DONE |
|
|
|
spoke to darby@###-####/told permit was ready and fees associated with it
|
Routing - PLAN CHECK | 2/16/2006 | | 7/6/2006 | | PASS |
|
|
|
Only one set approved do to red-lining.
|
Case Summary (BLD) | | | 7/5/2006 | | |
|
|
|
|
Plan Reviewer's activity | | | 6/30/2006 | | DONE |
|
|
|
6/30/06 Engineering was brought in for tall walls. Still need wall bracing shown on each floor. I called and left a message on Matt's phone.
7/5/06 Darby came in and marked wall bracing on plans.
|
Plan assigned to (DJO) | 2/27/2006 | | 3/21/2006 | | FAIL |
|
|
|
Routed back to office. (Steve Munroe)
|
Plan assigned to (SAM) | 3/21/2006 | | 3/21/2006 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 3/21/2006 | | DONE |
|
|
|
3/21/06 08:20 I called and left a message for Matt. I let him know that I need tall wall engineering and wall bracing shown on the plans for each floor. Plans are on hold.
5/18/06 10:15 I called and left a message for Matt. I let him know that I am still waiting for the above items. Plans are still on hold.
|
Plan assigned to (SAM) | 1/30/2006 | 1/30/2006 | 2/27/2006 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 2/15/2006 | | 2/16/2006 | | PASS |
|
|
|
|
Routing - PLANNING | 2/15/2006 | | 2/15/2006 | | PASS |
|
|
|
driveway width 33' wide maximum
|
Application received | | | 1/30/2006 | | |
|
|
|
|
Routing - PLANNING | 1/30/2006 | | | | FAIL |
|
|
|
Need adequate site plan. called and left message 1/30/06 ctc
|