Second Notice BLD | 5/9/2007 | 5/9/2007 | 5/25/2007 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 4/24/2007 | 5/9/2007 | | DONE |
|
|
|
|
Permanent occupancy UNPAID FEE | | | 4/5/2007 | | DONE |
|
|
|
Perm. Occ. Cert. #11516 issued 4-5-07 to the Ameritel Warehouse.
|
BLD-Final | 2/23/2007 | 2/26/2007 | 2/26/2007 | A | PASS |
Mike Jordan
|
|
|
clay ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith. Received final aff. letter from special insp. agency. ok for perm occ. No card to sign for perm.
|
Permanent Occupancy | | 2/26/2007 | 2/26/2007 | | DONE |
|
|
|
|
BLD-Final | 2/14/2007 | 2/15/2007 | 2/15/2007 | P | PART |
Mike Jordan
|
|
|
robert; Phone #: ###-#### Internet Inspection Request from: Victoria Beall. Ok for temp occ. Need final Aff. lettrer from Special insp. agency.
|
FIRE-Final Inspection | 2/14/2007 | 2/15/2007 | 2/15/2007 | A | PASS |
Troy Cobbley
|
|
|
Life safety finaled
|
PubWorks Occupancy Approval | 2/6/2007 | 2/6/2007 | 2/6/2007 | | DONE |
|
|
|
Signed final occupancy 01/31/07 R. Rokovitz.
|
Plan Reviewer's activity | | | 2/2/2007 | | DONE |
|
|
|
Architect has removed the installation of fire sprinklers from this building. The building will not require fire sprinklers. This has been reviewed and approved by the building code and fire code reviewers.
|
Plan Reviewer's activity | | | 2/2/2007 | | DONE |
|
|
|
Permit revised to clarify that there is a fire sprinkler stubbed to the building, but the building is not fire sprinkled. JCM
|
Code Occupancy Approval | | | 2/1/2007 | | PASS |
|
|
|
FINAL SIGNED OFF.
|
FIRE-Final Inspection | 1/30/2007 | 1/31/2007 | 1/31/2007 | P | FAIL |
Troy Cobbley
|
|
|
Need to update the permit application since it says that the building will be sprinklered and it isn't. Also need to remove the thumbturn deadbolts and tag the fire extinguishers.
|
BLD-Framing/Rough-in | 10/16/2006 | 10/16/2006 | 10/16/2006 | P | PASS |
Mike Jordan
|
|
|
robert ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
|
BLD-Framing/Rough-in | 10/4/2006 | 10/4/2006 | 10/4/2006 | P | PASS |
Mike Jordan
|
|
|
bob; Phone #: ###-#### Internet Inspection Request from: Patricia Smith. Exterior steel stud framing, and interior wood framed walls.
|
BLD-Foundation | 8/1/2006 | 8/2/2006 | 8/2/2006 | A | PART |
Jim Sly
|
|
|
robert - late am if possible; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley 3x3 Sq columns.....MTI on site.....
|
BLD-Footing | 7/14/2006 | 7/17/2006 | 7/17/2006 | A | PART |
Tony Young
|
|
|
ROBERT; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles pending s. i. report
|
BLD-Other | 6/28/2006 | 6/29/2006 | 6/29/2006 | A | PASS |
Mike Jordan
|
|
|
robert Note: panel ins; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles. tilt panels. also recieved special insp.
|
BLD-Footing | 6/13/2006 | 6/14/2006 | 6/14/2006 | P | PASS |
Mike Jordan
|
|
|
robert Note: also panel inspection; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles. perimeter footings and six conc. tilt panels.
|
(F) Reprint permit | | | 5/8/2006 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 5/5/2006 | | DONE |
|
|
|
|
Print Occupancy Form | | | 3/28/2006 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/28/2006 | | |
|
|
|
|
Telephone call | | | 3/28/2006 | | DONE |
|
|
|
talked to clay odell at ###-#### to verlfy plans are ready & need achd before picking up
|
Routing - PLAN CHECK | 3/27/2006 | | 3/27/2006 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/27/2006 | | DONE |
|
|
|
|
Plan assigned to (JCM) | 2/6/2006 | | 3/27/2006 | | PASS |
|
|
|
3/27/2006 16:14:21 JCM - activity updated through activity BLDA022 from case BLD06-00271.
|
Routing - PLUMBING | 3/17/2006 | | 3/20/2006 | | PASS |
|
|
|
per plans and 2003 upc
|
Routing - PUBLIC WORKS | 3/14/2006 | | 3/17/2006 | | FAIL |
|
|
|
CONTACT JIM PARDY AT ###-####
|
Routing - PUBLIC WORKS | 3/17/2006 | | 3/17/2006 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 3/3/2006 | | 3/14/2006 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 3/14/2006 | | PASS |
|
|
|
Reviewed and approved structural and nonsturctural revisions, JCM
|
Routing Off Site - STRUCTURAL | 3/14/2006 | | 3/14/2006 | | PASS |
|
|
|
I reviewed resubmitted structural plans and calculations. JCM
|
Plan resubmittals received | | | 3/8/2006 | | DONE |
|
|
|
Received 1 response,2 review comments,1 letter to MR. Blomberg & 2 copys of sheets C1,C2,C3,C4,C5,C6,C7,C8 A0.1,A1.1,A3.1,S-1,S-7.1,P0.1,P1.0 taken to John M.
|
Routing - FIRE | 2/28/2006 | | 3/3/2006 | | PASS |
|
|
|
Faxed review to architect. Attached comments to plans.
|
1st review completed | | | 3/3/2006 | | FAIL |
|
|
|
Failed in building, structural, plumbing and public works. JCM
|
Plan resubmittals requested | | | 2/28/2006 | | DONE |
|
|
|
E-mailed the architect a copy of the plan review requesting revisions. JCM
|
Routing - PLAN CHECK | 2/23/2006 | | 2/28/2006 | | FAIL |
|
|
|
John Menard
|
Plan resubmittals requested | | | 2/24/2006 | | DONE |
|
|
|
Faxed the architect a copy of the comment list from the consulting structural engineer requesting revisions. JCM
|
Routing - PLANNING | 2/14/2006 | | 2/23/2006 | | PASS |
|
|
|
Approved.
|
Routing Off Site - STRUCTURAL | 2/7/2006 | | 2/21/2006 | | FAIL |
|
|
|
Received a faxed comment list from the consulting structural engineer requesting revisions. JCM
|
Routing - PLUMBING | 2/10/2006 | | 2/14/2006 | | FAIL |
|
|
|
secondary roof drainage required.
|
Routing - Erosion and Sediment | 2/10/2006 | | 2/10/2006 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Routing - PUBLIC WORKS | 2/8/2006 | | 2/10/2006 | | FAIL |
|
|
|
Plans for construction of public sewer must be submitted separately to Public Works and approved prior to Public Works sign off on building plans. Contact Jim Pardy ###-####
|
Routing - PLANNING Land Div | 2/6/2006 | | 2/8/2006 | | PASS |
|
|
|
property was a annexed into the city in 2004 and was a buildable lot in the county prior to Jan. 1, 1985.
|
Plans ACCEPTED BY PLAN TECH | | | 2/6/2006 | | |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 2/6/2006 | | |
|
|
|
|
Application received | | | 2/3/2006 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/3/2006 | | |
|
|
|
|
Third Notice BLD | 5/25/2007 | 5/25/2007 | | | |
|
|
|
Second Notice has not been responded to.
|
Fee Review-notes | 2/3/2006 | 2/3/2006 | | | |
|
|
|
|