Case Summary (BLD) | | | 9/18/2008 | | |
|
|
|
|
PubWorks Occupancy Approval | 3/28/2007 | 3/28/2007 | 3/28/2007 | | DONE |
|
|
|
Signed final occupancy 03/13/07 by S. Landaluce.
|
First Notice | 3/14/2007 | 3/14/2007 | 3/26/2007 | | DONE |
Mike Jordan
|
|
|
This permit finaled on the web by Matt Smith
|
BLD-Final | 3/13/2007 | 3/14/2007 | 3/14/2007 | A | PASS |
Mike Jordan
|
|
|
darrin; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
|
DOC - Permit Finaled | 3/14/2007 | 3/14/2007 | 3/14/2007 | P | PASS |
Mike Jordan
|
|
|
Shell and core ok. Letter of compliance was issued.
|
FIRE-Final Inspection | 3/9/2007 | 3/12/2007 | 3/12/2007 | A | FAIL |
Troy Cobbley
|
|
|
Need to have fire sprinkler permit finaled first and then this permit is ready to be finaled.
|
Code Occupancy Approval | 1/24/2007 | 1/24/2007 | 1/24/2007 | P | PASS |
Carol Montgomery
|
|
|
|
Code Occupancy Approval Temp | | | 11/14/2006 | | |
|
|
|
Cashiers check for bond $2351 received 11/9/2006
|
COD-Stop Work/Reinspection MOD | 10/5/2006 | 10/5/2006 | 10/5/2006 | P | DONE |
Carol Montgomery
|
|
|
Issued CN for cond. #10 - replace the perma bark with required mulch/soil aid - stripping and H/C signs needed. $158.00 reinspection fee required.
|
BLD-Framing/Rough-in | 8/18/2006 | 8/18/2006 | 8/18/2006 | P | PASS |
Tom Arcoraci
|
|
|
darin; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley
|
BLD-Concrete | 5/31/2006 | 6/2/2006 | 6/2/2006 | A | PART |
Jim Sly
|
|
|
Daren; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt
|
BLD-Concrete | 5/31/2006 | 6/1/2006 | 6/1/2006 | A | PART |
Jim Sly
|
|
|
Daren; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt Pouring footings......MTI on site.
|
BLD-Footing | 5/30/2006 | 5/31/2006 | 5/31/2006 | A | PART |
Jim Sly
|
|
|
Phone #: ###-#### Internet Inspection Request from: Rita DeYoung Working on backfill and compaction of footings MTI scheduled for tests today.
|
BLD-Footing | 5/30/2006 | 5/30/2006 | 5/30/2006 | P | PART |
Jim Sly
|
|
|
Phone #: ###-#### Internet Inspection Request from: Rita DeYoung OK Pending Special insp tests and approvals MTI on site.
|
BLD-Other | 5/9/2006 | 5/9/2006 | 5/9/2006 | P | PART |
Jim Sly
|
|
|
darin Note: rebar; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles Slab pour OK Pending MTI special inspections, tests and approvals.
|
(F) Reprint permit | | | 5/5/2006 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 5/4/2006 | | DONE |
|
|
|
|
Routing Off Site - STRUCTURAL | 3/31/2006 | | 4/14/2006 | | PASS |
|
|
|
Called Action Couriers for pick up.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/14/2006 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 4/14/2006 | | DONE |
|
|
|
|
Telephone call | | | 4/14/2006 | | DONE |
|
|
|
lft vm with wes ###-#### that permit and fees are ready to be picked up and fees
|
Permit Ready to Issue | | | 4/14/2006 | | DONE |
|
|
|
|
Plan assigned to (JCM) | 2/10/2006 | | 4/14/2006 | | PASS |
|
|
|
4/14/2006 10:57:23 JCM - activity updated through activity BLDA022 from case BLD06-00288.
|
Routing - PLAN CHECK | 2/28/2006 | | 4/14/2006 | | PASS |
|
|
|
|
Plan resubmittals received | | | 3/30/2006 | | DONE |
|
|
|
Received 1 transmittal,2 letters to Wes Steele, 2 review calcs & 4 copys of sheets S1.1,S2.1,S3.1,S4.2 taken to John M.
|
Plan resubmittals requested | | | 2/28/2006 | | DONE |
|
|
|
E-mailed the architect a copy of the comment list from the consulting structural engineer requesting revisions. JCM
|
1st review completed | | | 2/28/2006 | | FAIL |
|
|
|
Failed plan check.
|
Routing - FIRE | 2/24/2006 | | 2/28/2006 | | PASS |
|
|
|
Faxed review comments to architect. Attached review comments to plans.
|
Routing Off Site - STRUCTURAL | 2/10/2006 | | 2/27/2006 | | FAIL |
|
|
|
Called Action Couriers for pick up - Received e-mailed comment list from the consulting structural engineer requesting revisions. JCM
|
Routing - PLAN CHECK | 2/21/2006 | | 2/24/2006 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 2/24/2006 | | PASS |
|
|
|
Plans reviewed and approved as submitted with red lined note attached comments. JCM
|
Routing - PLANNING | 2/15/2006 | | 2/21/2006 | | PASS |
|
|
|
Sara S. Approved per DRH05-00098.
|
Routing - PLUMBING | 2/15/2006 | | 2/15/2006 | | PASS |
|
|
|
min. 1/4" per foot grade on roof drain piping from the termination at the catch basin to the 1st. tee. per plans and 2003 upc
|
Routing - Erosion and Sediment | 2/15/2006 | | 2/15/2006 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Routing - PUBLIC WORKS | 2/13/2006 | | 2/15/2006 | | PASS |
|
|
|
|
Routing - PLANNING Land Div | 2/10/2006 | | 2/13/2006 | | PASS |
|
|
|
parcel created by a record of survey (ROS05-00086).
|
Plans ACCEPTED BY PLAN TECH | | | 2/10/2006 | | |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 2/10/2006 | | |
|
|
|
|
Application received | | | 2/6/2006 | | |
|
|
|
|