Second Notice BLD | 3/29/2006 | 3/29/2006 | 4/14/2006 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | 3/13/2006 | 3/13/2006 | 3/29/2006 | | DONE |
Jim Storey
|
|
|
|
BLD-Final | 3/10/2006 | 3/13/2006 | 3/13/2006 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 3/10/2006 at 7:57:47 AM. Contact: ###-####.
|
DOC - Permit Finaled | 3/13/2006 | 3/13/2006 | 3/13/2006 | P | PASS |
Jim Storey
|
|
|
|
FIRE-Final Inspection | 3/9/2006 | 3/10/2006 | 3/10/2006 | A | PASS |
Forrest France
|
|
|
Fire life safety for the permitted work is satisfactory, note-need to seal hole in the rated wall where the sprinkler line was removed prior to structural final inspection.
|
Issue & PRINT to be Invoiced | | | 2/15/2006 | | DONE |
|
|
|
|
Plan assigned to (JCM) | 2/9/2006 | | 2/14/2006 | | PASS |
|
|
|
2/14/2006 15:39:10 JCM - activity updated through activity BLDA022 from case BLD06-00315.
|
Plan Reviewer's activity | | | 2/10/2006 | | PASS |
|
|
|
Plan reviewed and approved at the Micron site. JCM
|
Routing - FIRE | 2/9/2006 | | 2/10/2006 | | PASS |
|
|
|
Passed at on-site review. AS plans need revision prior to review; discussed with S. Murdock. FA plans not acceptable: revise location of strobe, clarify smoke detection system and add connection to facility FA 1-line, provide a FA permit application and supporting documentation. "Attach" the AS and FA permits to this buidling permit project.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/10/2006 | | DONE |
|
|
|
|
1st review completed | | | 2/10/2006 | | PASS |
|
|
|
|
Application received | | | 2/9/2006 | | DONE |
|
|
|
This permit was created on the web by Paul Marcolina
|
Third Notice BLD | 4/14/2006 | 4/14/2006 | | | |
|
|
|
Second Notice has not been responded to.
|
Plan assigned from Web | 2/9/2006 | 2/19/2006 | | | |
|
|
|
|