Permit Information
Permit NumberBLD06-00325
StatusFinaled
Name MILLIMAN
Site Address 950 W BANNOCK ST Unit: 510
Project Name10TH & BANNOCK-5TH FLR
Customer Number 
ePlanReviewNo
Description
(RCE #8247 - CHRISTENSEN CORP .(MILLIMAN - BANNER BANK BLDG - STE 510) This building is fire sprinklered because it is a high-rise. To construct a 2,324 square foot office tenant space on the 5th story of a high-rise building. Work is to include interior Nordwall demountable nonbearing partitions, doors, and sidelights. The access floor system and the suspended ceilings were installed under permit BLD05-02939. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes. The fire sprinkler system shall comply with NFPA 13 as regulated by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Case Summary (BLD)  11/6/2015 DONE
Third Notice BLD7/18/20077/18/20071/18/2008 DONE
DetailsHattie E James
Second Notice has not been responded to.
Second Notice BLD6/21/20076/21/20077/18/2007 DONE
First Notice has not been responded to.
First Notice 5/22/20076/21/2007 DONE
Print Occupancy Form  5/22/2007 DONE
Permanent occupancy  5/22/2007 DONE
Perm. Occ. Cert. # 11625 issued 5-22-07 to Milliman.
BLD-Final4/25/20074/25/20074/25/2007PPASS
DetailsDave Hannah
Steve; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt ok for perm occ
CHANGE STATUS TO (ISS)  4/25/2007 DONE
Permanent Occupancy 5/26/20065/26/2006 DONE
Details
BLD-Final5/5/20065/8/20065/8/2006PPART
DetailsDave Hannah
greg; Phone #: ###-#### Internet Inspection Request from: Rita DeYoung ok for temp occ
FIRE-Final Inspection5/5/20065/8/20065/8/2006APASS
DetailsForrest France
Corrections are completed, fire life safety passed inspection.
FIRE-Final Inspection5/4/20065/5/20065/5/2006AFAIL
DetailsForrest France
Need to provide suite address as indicated on review notes, need to verify path of egress lighting is installed and functional within the TI space.
BLD-Final5/3/20065/4/20065/5/2006PFAIL
DetailsDave Hannah
GREG; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles needs other trades to final no inspection done
BLD-Framing/Rough-in4/28/20065/1/20065/1/2006APASS
DetailsDave Hannah
greg; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie wall system ok
BLD-Energy code compliance4/28/20065/1/20065/1/2006APASS
DetailsDave Hannah
greg; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie wall insulation ok
Routing - FIRE4/5/2006 4/7/2006 PASS
Attached reveiw comments to plans. Faxed review comments to architect.
Routing - PLAN CHECK4/7/2006 4/7/2006 DONE
PLANS/APPL TAKEN TO FRONT DESK  4/7/2006 DONE
Print Occupancy Form  4/7/2006  
Permit Ready to Issue  4/7/2006  
Telephone call  4/7/2006 DONE
tlk to amy to let you know that permit and fees are ready to be picked up
Issue PAID IN FULL permit  4/7/2006  
Plan assigned to (CJW)2/13/2006 4/7/2006 PASS
4/7/2006 09:49:14 CJW - activity updated through activity BLDA022 from case BLD06-00325.
Routing - PLAN CHECK3/16/2006 4/5/2006 PASS
(3-16-06) Drawings on hold until alternate is approved. (4-5-06) The alternate was approved.
Plan resubmittals received  3/16/2006  
Received 1 transmittal, 5 letters for Carl W. & 2 copys of sheets G-01,AF-106,A-105,A-106,A-201,A-301,A-302,A-304 taken to Carl W
Routing - FIRE3/8/2006 3/16/2006 FAIL
Failed pending approval of combustible tenant wall construction by building official. (3-17-06) The completed date was altered to show when it actually came back to Plan Check. CJW
1st review completed  3/13/2006 FAIL
Failed fire.
Plan resubmittals received  3/7/2006 DONE
An alternative construction request was submitted to Jenifer Gilliland.
Routing - PLAN CHECK2/14/2006 3/7/2006 FAIL
The IBC plan review was started on March 7, 2006 and was finished the same day. Additional information and revised drawings were required. See the plan review report.
Plan Reviewer's activity  3/6/2006  
Received a request for an alternate to the code. Waiting for a resolution.
Routing - PUBLIC WORKS2/13/2006 2/14/2006 PASS
Plans ACCEPTED BY PLAN TECH  2/10/2006  
Application received  2/9/2006  
Recd Pcfee & Taken To Pln CK  2/9/2006  
Fee Review-notes2/9/20062/9/2006