BLD-Final | 8/25/2006 | 8/25/2006 | 8/25/2006 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 8/25/2006 at 10:10:56 AM. Contact: ###-####.
|
DOC - Permit Finaled | 8/25/2006 | 8/25/2006 | 8/25/2006 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Foundation | 7/28/2006 | 7/28/2006 | 7/28/2006 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 7/28/2006 at 7:41:18 AM. Contact: ###-####.
|
BLD-Footing | 7/27/2006 | 7/27/2006 | 7/27/2006 | P | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 7/27/2006 at 7:59:59 AM. Contact: ###-####. garage,, poured
|
BLD-Energy code compliance | 6/7/2006 | 6/7/2006 | 6/7/2006 | P | PASS |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 6/7/2006 at 7:13:27 AM. Contact: ###-####.
|
BLD-Framing/Rough-in | 6/2/2006 | 6/5/2006 | 6/5/2006 | A | PASS |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 6/2/2006 at 3:32:10 PM. Contact: ###-####.
|
BLD-Framing/Rough-in | 6/2/2006 | 6/2/2006 | 6/2/2006 | P | PART |
Tony Young
|
|
|
ok to insulate,, c/n on blue tag
|
BLD-Framing/Rough-in | 6/2/2006 | 6/2/2006 | 6/2/2006 | P | NR |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 6/2/2006 at 7:18:16 AM. Contact: ###-####.
|
BLD-Foundation | 3/30/2006 | 3/31/2006 | 3/31/2006 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 3/30/2006 at 8:44:50 PM. Contact: ###-####.
|
BLD-Footing | 3/29/2006 | 3/30/2006 | 3/30/2006 | A | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 3/29/2006 at 8:11:34 PM. Contact: ###-####.
|
BLD-Footing | 3/29/2006 | 3/29/2006 | 3/29/2006 | P | NR |
Tony Young
|
|
|
mana; Phone #: ###-#### too much rain
|
BLD-Footing | 3/28/2006 | 3/29/2006 | 3/29/2006 | A | CANC |
Tony Young
|
|
|
Mana; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong meeting,, resched for pm
|
Inspection Record Card- Bld | | | 3/15/2006 | | |
|
|
|
|
Permit Ready to Issue | | | 3/15/2006 | | DONE |
|
|
|
|
Telephone call | | | 3/15/2006 | | DONE |
|
|
|
left mess that permit is ready
|
Issue PAID IN FULL permit | | | 3/15/2006 | | |
|
|
|
|
Plan assigned to (SRZ) | 3/3/2006 | 3/3/2006 | 3/14/2006 | | PASS |
|
|
|
3/14/2006 16:21:13 SRZ - activity updated through activity BLDA022 from case BLD06-00342.
|
Routing - PLAN CHECK | 2/17/2006 | | 3/14/2006 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 3/14/2006 | | DONE |
|
|
|
Recieved roof Engineering. (SRZ)
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/14/2006 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 3/6/2006 | | PASS |
|
|
|
Roof does not fall within Prescriptive Light Frame Construction. Need Engineering for Roof Design. (SRZ)
|
Plan assigned to (SAM) | 2/13/2006 | 2/13/2006 | 3/3/2006 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 3/3/2006 | | |
|
|
|
|
Routing - PUBLIC WORKS | 2/17/2006 | | 2/17/2006 | | PASS |
|
|
|
|
Routing - PLANNING | 2/17/2006 | | 2/17/2006 | | PASS |
|
|
|
Approved per DRH05-00464 and as noted for back-up accross alley and garage dimension.
|
Application received | | | 2/13/2006 | | |
|
|
|
|
Routing - PLANNING | 2/13/2006 | | 2/14/2005 | | FAIL |
|
|
|
Routed to Sarah Schafer per DR approval. DRH appeal period is not over until February 16, 2006 at 4. Plans will be in my office until that time.
|