BLD-Final | 8/28/2006 | 8/29/2006 | 8/29/2006 | A | PASS |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 8/28/2006 at 4:45:18 PM. Contact: ###-####.
|
DOC - Permit Finaled | 8/29/2006 | 8/29/2006 | 8/29/2006 | P | PASS |
Tony Young
|
|
|
C OF O ISSUED
|
BLD-Final | 8/25/2006 | 8/25/2006 | 8/25/2006 | P | FAIL |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 8/25/2006 at 10:12:08 AM. Contact: ###-####. tempered glass c/n on site
|
BLD-Foundation | 7/28/2006 | 7/28/2006 | 7/28/2006 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 7/28/2006 at 7:42:21 AM. Contact: ###-####.
|
BLD-Footing | 7/27/2006 | 7/27/2006 | 7/27/2006 | P | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 7/27/2006 at 8:01:01 AM. Contact: ###-####. garage,, ftgs poured
|
BLD-Energy code compliance | 6/2/2006 | 6/2/2006 | 6/2/2006 | P | PASS |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 6/2/2006 at 7:16:40 AM. Contact: ###-####.
|
BLD-Framing/Rough-in | 5/30/2006 | 5/30/2006 | 5/30/2006 | P | PASS |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 5/30/2006 at 6:59:34 AM. Contact: ###-####.
|
BLD-Foundation | 3/30/2006 | 3/31/2006 | 3/31/2006 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 3/30/2006 at 8:45:44 PM. Contact: ###-####.
|
BLD-Footing | 3/29/2006 | 3/30/2006 | 3/30/2006 | A | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 3/29/2006 at 8:12:51 PM. Contact: ###-####.
|
BLD-Footing | 3/29/2006 | 3/29/2006 | 3/29/2006 | P | NR |
Tony Young
|
|
|
mana; Phone #: ###-#### to much rain
|
BLD-Footing | 3/28/2006 | 3/29/2006 | 3/29/2006 | A | CANC |
Tony Young
|
|
|
Mana; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong meeting, resched for pm
|
Plan assigned to (SRZ) | 3/6/2006 | 3/6/2006 | 3/15/2006 | | PASS |
|
|
|
3/15/2006 08:40:08 SRZ - activity updated through activity BLDA022 from case BLD06-00350.
|
Routing - PLAN CHECK | 2/17/2006 | | 3/15/2006 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 3/15/2006 | | DONE |
|
|
|
Recieved Roof Engineering. (SRZ)
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/15/2006 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/15/2006 | | |
|
|
|
|
Telephone call | | | 3/15/2006 | | |
|
|
|
Informed Lois (Boise City Building Company) ###-#### to pick up permit 3-15-06 eus
|
Permit Ready to Issue | | | 3/15/2006 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 3/15/2006 | | DONE |
|
|
|
|
Plan assigned to (SAM) | 2/17/2006 | 2/17/2006 | 3/6/2006 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 3/6/2006 | | |
|
|
|
|
Plan Reviewer's activity | | | 3/6/2006 | | PASS |
|
|
|
Roof does not fall within Prescriptive Light Frame Construction. Need Engineering for Roof Design. (SRZ)
|
Routing - PLANNING | 2/17/2006 | | 2/17/2006 | | PASS |
|
|
|
Approved per DRH05-00468 and as noted for back-up accross alley and garage dimension.
|
Routing - PUBLIC WORKS | 2/17/2006 | | 2/17/2006 | | PASS |
|
|
|
|
Routing - PLANNING | 2/13/2006 | | 2/14/2006 | | FAIL |
|
|
|
DRH appeal period does not end until 4 on February 16, 2006. Plans will be in my office until then.
|
Application received | | | 2/13/2006 | | |
|
|
|
|