Second Notice BLD | 2/2/2007 | 2/2/2007 | 2/12/2007 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | 1/16/2007 | 1/16/2007 | 2/2/2007 | | DONE |
Jim Storey
|
|
|
|
BLD-Final | 1/16/2007 | 1/16/2007 | 1/16/2007 | P | PASS |
Jim Storey
|
|
|
greg; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
|
DOC - Permit Finaled | 1/16/2007 | 1/16/2007 | 1/16/2007 | P | PASS |
Jim Storey
|
|
|
|
BLD-Aging Inspection | 1/5/2007 | 1/5/2007 | 1/5/2007 | | PASS |
Jim Storey
|
|
|
|
BLD-Aging Inspection | 11/2/2006 | 11/2/2006 | 11/2/2006 | | NR |
Jim Storey
|
|
|
pending fir final insp.
|
BLD-Aging Inspection | 9/1/2006 | 9/1/2006 | 9/1/2006 | | PASS |
Jim Storey
|
|
|
wip
|
FIRE-Final Inspection | 6/26/2006 | 6/27/2006 | 6/27/2006 | A | PART |
Forrest France
|
|
|
Fire life safety for the east cleanroom area passed inspection, project related FS work remains to be finaled.
|
BLD-Framing/Rough-in | 6/8/2006 | 6/12/2006 | 6/12/2006 | A | PASS |
Jim Storey
|
|
|
Greg Adams, Bldg. #80; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
FIRE-Final Inspection | 4/25/2006 | 5/1/2006 | 5/1/2006 | A | CANC |
Forrest France
|
|
|
craig pager #99710; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles per craig 4/25/2006
|
Plan assigned to (JCM) | 2/23/2006 | | 3/10/2006 | | PASS |
|
|
|
3/10/2006 13:51:55 JCM - activity updated through activity BLDA022 from case BLD06-00351.
|
Plan Reviewer's activity | | | 3/10/2006 | | PASS |
|
|
|
Reviewed and approved on last Micron visit. JCM
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/10/2006 | | DONE |
|
|
|
|
Issue & PRINT to be Invoiced | | | 3/10/2006 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 3/2/2006 | | FAIL |
|
|
|
Plan had been stamped by the structural engineer, but calculations were not supplied. I felt structural calculations should be provided for this scope of work. JCM
|
Plan Reviewer's activity | | | 2/24/2006 | | FAIL |
|
|
|
Requires structural calculations and stamps and signatures by the design professionals. Will do a second review at the Micron site next week. JCM
|
1st review completed | | | 2/24/2006 | | FAIL |
John Menard
|
|
|
|
Routing - FIRE | 2/24/2006 | | 2/23/2006 | | PASS |
|
|
|
Fire review acceptable but plans not signed as they are to be revised for Building modifications. Will sign off at next visit when Bldg approves them. FA permit (FIR 06-00110) plans not ready, has no application or equipment cut sheets. SPK permit (FIR 06-00109) aleady approved.
|
Application received | | | 2/14/2006 | | DONE |
|
|
|
This permit was created on the web by Paul Marcolina
|
Third Notice BLD | 2/12/2007 | 2/12/2007 | | | |
|
|
|
Second Notice has not been responded to.
|
Plan assigned from Web | 2/14/2006 | 2/24/2006 | | | |
|
|
|
|