Permit Information
Permit NumberBLD06-00351
StatusFinaled
Name MICRON TECHNOLOGY INC
Site Address 8000 S FEDERAL WAY
Project Name 
Customer NumberC9193
ePlanReviewNo
Description
Micron Building #80 - (C9193) - Build-out Area For Additional Metrology - To construct cleanroom walls and install new 8'-0" egress door at the corridor wall to create a new approximate 1685 square foot Metrology Area #109A in a previously unoccupied area. This work also includes related access floor and ceiling hepa filters. This work also inlcudes structural modifications to the second floor for new mechanical equipment and open the floor for a new return air chase. This work is being done at the first and second floors of building #80 between grid lines F&H and 3&5. All construction per the approved plans.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice BLD2/2/20072/2/20072/12/2007 DONE
First Notice has not been responded to.
First Notice1/16/20071/16/20072/2/2007 DONE
DetailsJim Storey
BLD-Final1/16/20071/16/20071/16/2007PPASS
DetailsJim Storey
greg; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
DOC - Permit Finaled1/16/20071/16/20071/16/2007PPASS
DetailsJim Storey
BLD-Aging Inspection1/5/20071/5/20071/5/2007 PASS
DetailsJim Storey
BLD-Aging Inspection11/2/200611/2/200611/2/2006 NR
DetailsJim Storey
pending fir final insp.
BLD-Aging Inspection9/1/20069/1/20069/1/2006 PASS
DetailsJim Storey
wip
FIRE-Final Inspection6/26/20066/27/20066/27/2006APART
DetailsForrest France
Fire life safety for the east cleanroom area passed inspection, project related FS work remains to be finaled.
BLD-Framing/Rough-in6/8/20066/12/20066/12/2006APASS
DetailsJim Storey
Greg Adams, Bldg. #80; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
FIRE-Final Inspection4/25/20065/1/20065/1/2006ACANC
DetailsForrest France
craig pager #99710; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles per craig 4/25/2006
Plan assigned to (JCM)2/23/2006 3/10/2006 PASS
3/10/2006 13:51:55 JCM - activity updated through activity BLDA022 from case BLD06-00351.
Plan Reviewer's activity  3/10/2006 PASS
Reviewed and approved on last Micron visit. JCM
PLANS/APPL TAKEN TO FRONT DESK  3/10/2006 DONE
Issue & PRINT to be Invoiced  3/10/2006 DONE
Plan Reviewer's activity  3/2/2006 FAIL
Plan had been stamped by the structural engineer, but calculations were not supplied. I felt structural calculations should be provided for this scope of work. JCM
Plan Reviewer's activity  2/24/2006 FAIL
Requires structural calculations and stamps and signatures by the design professionals. Will do a second review at the Micron site next week. JCM
1st review completed  2/24/2006 FAIL
DetailsJohn Menard
Routing - FIRE2/24/2006 2/23/2006 PASS
Fire review acceptable but plans not signed as they are to be revised for Building modifications. Will sign off at next visit when Bldg approves them. FA permit (FIR 06-00110) plans not ready, has no application or equipment cut sheets. SPK permit (FIR 06-00109) aleady approved.
Application received  2/14/2006 DONE
This permit was created on the web by Paul Marcolina
Third Notice BLD2/12/20072/12/2007   
Second Notice has not been responded to.
Plan assigned from Web2/14/20062/24/2006