BLD-Final | 11/3/2006 | 11/3/2006 | 11/3/2006 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 11/3/2006 at 7:25:25 AM. Contact: ###-####.
|
DOC - Permit Finaled | 11/3/2006 | 11/3/2006 | 11/3/2006 | P | PASS |
Dave Hannah
|
|
|
|
Code Occupancy Approval | | | 11/2/2006 | | PASS |
|
|
|
compliance met.
|
BLD-Final | 10/31/2006 | 10/31/2006 | 10/31/2006 | P | NR |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 10/31/2006 at 11:04:39 AM. Contact: ###-####. needs DRH signed off other items ok for final
|
Case Summary (BLD) | | | 8/16/2006 | | |
|
|
|
|
BLD-Conference | 8/3/2006 | 8/3/2006 | 8/3/2006 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 8/3/2006 at 7:04:41 AM. Contact: ###-####.
|
BLD-Energy code compliance | 7/31/2006 | 7/31/2006 | 7/31/2006 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 7/31/2006 at 8:30:12 AM. Contact: ###-####.
|
BLD-Framing/Rough-in | 7/25/2006 | 7/25/2006 | 7/25/2006 | P | FAIL |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 7/25/2006 at 9:08:40 AM. Contact: ###-####. c/n on site ok to insulate
|
BLD-Conference | 6/5/2006 | 6/6/2006 | 6/6/2006 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 6/5/2006 at 3:28:13 PM. Contact: ###-####. truss firewall ok to set
|
BLD-Conference | 5/31/2006 | 5/31/2006 | 5/31/2006 | P | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 5/31/2006 at 7:40:04 AM. Contact: ###-####. second storey fire wall ok to stand
|
FIRE-Conference | 5/30/2006 | 5/31/2006 | 5/31/2006 | A | NR |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 5/30/2006 at 10:55:37 AM. Contact: ###-####.
|
FIRE-Conference | 5/30/2006 | 5/30/2006 | 5/30/2006 | P | CANC |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 5/30/2006 at 7:01:05 AM. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on May 30 2006 10:57AM.
|
FIRE-Conference | 5/24/2006 | 5/25/2006 | 5/25/2006 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 5/24/2006 at 3:53:55 PM. Contact: ###-####. 1rts level fire wall ok to stand
|
BLD-Conference | 5/23/2006 | 5/24/2006 | 5/24/2006 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 5/23/2006 at 2:19:04 PM. Contact: ###-####. fire walls
|
BLD-Conference | 5/19/2006 | 5/19/2006 | 5/19/2006 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 5/19/2006 at 9:02:19 AM. Contact: ###-####.
|
BLD-Conference | 5/3/2006 | 5/4/2006 | 5/4/2006 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 5/3/2006 at 1:24:21 PM. Contact: ###-####. discussed fire wall
|
BLD-Foundation | 4/26/2006 | 4/27/2006 | 4/27/2006 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 4/26/2006 at 10:26:00 PM. Contact: ###-####.
|
BLD-Footing | 4/25/2006 | 4/26/2006 | 4/26/2006 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 4/25/2006 at 10:39:32 PM. Contact: ###-####.
|
BLD-Footing | 4/24/2006 | 4/25/2006 | 4/25/2006 | P | NR |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 4/24/2006 at 5:44:34 PM. Contact: ###-####.
|
(F) Reprint permit | | | 4/19/2006 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 4/18/2006 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/7/2006 | | |
|
|
|
|
Inspection Record Card- Bld | | | 3/7/2006 | | DONE |
|
|
|
|
Telephone call | | | 3/7/2006 | | |
|
|
|
Informed Lois (Boise City Building Company) ###-#### to pick up permit 3-7-06 eus
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/6/2006 | | DONE |
|
|
|
|
Plan assigned to (SAM) | 2/14/2006 | 2/14/2006 | 2/27/2006 | | DONE |
|
|
|
|
Routing - PLANNING | 2/14/2006 | | 2/15/2006 | | PASS |
|
|
|
Meets the requirements of CAA05-00302. Routed to Sarah Schafer to confirm compliance with DRH05-00406. (CER) 2/15/06
|
Routing - PUBLIC WORKS | 2/15/2006 | | 2/15/2006 | | PASS |
|
|
|
|
Routing - PLANNING | 2/15/2006 | | 2/15/2006 | | PASS |
|
|
|
Approved per DRH05-00406.
|
Application received | | | 2/14/2006 | | |
|
|
|
|
Routing - PLANNING Land Div | 2/14/2006 | | 2/14/2006 | | PASS |
|
|
|
construction is entirely on lots 9&10 the south 2 feet of lot 8 is all setback. Lots 9&10 are existing platted lots.
|
Routing - PLAN CHECK | 2/15/2006 | | | | |
|
|
|
|
Plan assigned to (DJO) | 2/27/2006 | | | | |
|
|
|
|