BLD-Final | 2/12/2007 | 2/13/2007 | 2/13/2007 | A | PASS |
Tony Young
|
|
|
Jonathan; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt
|
DOC - Permit Finaled | 2/13/2007 | 2/13/2007 | 2/13/2007 | P | PASS |
Tony Young
|
|
|
c of o issued
|
BLD-Grading Inspection | 2/13/2007 | 2/13/2007 | 2/13/2007 | | BOND |
|
|
|
The rough grading and drainage have been completed at the above mentioned address. However, final grading and the construction of a three foot high retaining wall beside the garage have not been completed. For this the engineer has recommended a bond of $2,000.00. Upon receipt of this bond the grading and drainage is conditionally approved
|
BLD-Final | 2/2/2007 | 2/5/2007 | 2/5/2007 | A | NR |
Tony Young
|
|
|
jonathan ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith need hillside 1st
|
BLD-Energy code compliance | 10/11/2006 | 10/12/2006 | 10/12/2006 | A | PASS |
Jim Sly
|
|
|
jim; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
|
BLD-Framing/Rough-in | 10/11/2006 | 10/12/2006 | 10/12/2006 | A | PASS |
Jim Sly
|
|
|
jim - note: shear nailing ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
|
BLD-Framing/Rough-in | 10/4/2006 | 10/5/2006 | 10/5/2006 | A | FAIL |
Mike Jordan
|
|
|
jim; Phone #: ###-#### Internet Inspection Request from: Patricia Smith. No shear insp. done. Circular stairway tred depths do no conform to code. Complete lateral bracing. c/n posted. ok to insul.
|
BLD-Foundation | 7/19/2006 | 7/19/2006 | 7/19/2006 | P | PASS |
Jim Sly
|
|
|
clay; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley
|
BLD-Footing | 7/13/2006 | 7/14/2006 | 7/14/2006 | A | PART |
Tony Young
|
|
|
clay - pour around 11:30; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley
|
PubWorks Subgrade Approval | 7/14/2006 | 7/14/2006 | 7/14/2006 | | DONE |
|
|
|
Footing subgrade approved by the geotechnical engineer
|
Issue PAID IN FULL permit | | | 6/23/2006 | | DONE |
|
|
|
|
Telephone call | | | 6/1/2006 | | DONE |
|
|
|
tlk to welch custom homes ###-#### that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 6/1/2006 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/31/2006 | | DONE |
|
|
|
|
Plan assigned to (SRZ) | 5/30/2006 | 5/30/2006 | 5/30/2006 | | PASS |
|
|
|
5/30/2006 14:29:09 SRZ - activity updated through activity BLDA022 from case BLD06-00404.
|
Plan assigned to (SAM) | 2/17/2006 | 2/17/2006 | 5/30/2006 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 5/5/2006 | | 5/30/2006 | | PASS |
|
|
|
|
Case Summary (BLD) | | | 5/30/2006 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/30/2006 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 5/2/2006 | | 5/4/2006 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Routing - FIRE | 5/4/2006 | | 5/4/2006 | | PASS |
|
|
|
This house requires an NFPA 13D automatic fire sprinkler system, modified by the installation of a single row of dry sidewall sprinklers along the walls common to attached garages and the living spaces.
|
Routing - PUBLIC WORKS GRADING | 5/2/2006 | | 5/2/2006 | | PASS |
|
|
|
Received revised foundation plan and approved as Category 3.
|
Routing - PLANNING | 5/2/2006 | | 5/2/2006 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 5/2/2006 | | 5/2/2006 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS GRADING | 2/17/2006 | | 2/22/2006 | | FAIL |
|
|
|
Foundation plan does not indicate a step in the foundation that will be necessary due to the exterior proposed grades. Talked to Jim Welch and he said that they are considering abandoning the project.
|
Application received | | | 2/17/2006 | | |
|
|
|
|