Description
(GARDEN CENTER - SHELL & CORE) To construct a new 12,000 square foot, one story, steel frame retail and restaurant shell building and related site improvements. This building will contain a future 3,480 square foot restaurant, a 600 square foot mechanical room and a future 7,920 square foot retail garden store. The garden store tenant improvement is being constructed concurrently with this shell building under building permit BLD06-00454.The future restaurant space will require a separate tenant improvement permit to finish for occupancy. This lot is within the floodplain area. An elevation certificate is required to be submitted to and approved by Jim Wyllie, Public Works Dept., prior to calling for a framing inspection. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Letter of compliance  5/7/2008 DONE
DetailsCathy Weisshaupt
BLD-Conference10/23/200710/23/200710/23/2007ADONE
Temp. Occ. extended for an additional 90 days per Jennifer thru 1-29-08
Conference7/25/20077/25/20077/25/2007  
Temp. Occ. Cert. extended thru 10-29-07 per Jenifer.
BLD-Final4/27/20074/30/20074/30/2007PPART
DetailsTony Young
dan; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
temp occ ok
FIRE-Final Inspection4/27/20074/30/20074/30/2007APASS
DetailsTroy Cobbley
LIfe safety passed per Brian
FIRE-Alarm Testing4/27/20074/30/20074/30/2007APASS
DetailsTroy Cobbley
Fire alarm passed
Temporary occupancy  4/30/2007 DONE
Temp. Occ. Cert. # 5575 issued 4-30-07 to the 36th Street Garden Center.
FIRE-Final Inspection4/26/20074/27/20074/27/2007AFAIL
DetailsTroy Cobbley
Life safety will be ok to final when the alarm permits are finaled.
BLD-Final4/26/20074/27/20074/27/2007PNR
DetailsTony Young
DAN; Phone #: ###-####
conf only,, need trades 1st
BLD-Final4/25/20074/25/20074/26/2007PNR
DetailsTony Young
dan; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
BLD-Final4/25/20074/26/20074/26/2007PCANC
DetailsTony Young
DAN; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
FIRE-Final Inspection4/25/20074/26/20074/26/2007PCANC
DetailsTroy Cobbley
dan - fire life safety - late afternoon ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
Code Occupancy Approval Temp4/24/20074/24/20074/24/2007ADONE
DetailsMichael Garner
site inspection complete - officer found that the builder has completed the required amount of work for a temporary occupancy - e.g., benches are on site- but not yet emplaced; there is a bond for remaining landscaping - officer contractor, Dan, to telephone me for a final when the rest of the work is complete
BLD-Framing/Rough-in4/20/20074/20/20074/20/2007PPASS
DetailsTony Young
dan; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
pump room for 1 hr construction
BLD-Conference4/13/20074/13/20074/16/2007PPART
DetailsTony Young
Dan,, ADA ?s; Phone #: ###-####
ADA side clear on door side pull to be 18",, will turn door around
BLD-Conference4/12/20074/12/20074/13/2007PPART
DetailsTony Young
dan; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
need ADA issues of side door pull access,,
BLD-Other4/9/20074/10/20074/10/2007APART
DetailsTony Young
DAN - CEILING; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
wip,, ok,, conf. on ADA requirements
BLD-Conference4/2/20074/2/20074/2/2007PPART
DetailsTony Young
dan; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
conf on site w/ 408,, need hand rails on stairs to public way that is out from exits,, will see B.O. about one other possible need area
BLD-Conference3/20/20073/21/20073/21/2007APART
DetailsTony Young
Dan; Phone #: ###-#### Internet Inspection Request from: Stacie Backus
extensive conf. on job for final,, need to see plan review for clarification on ext stairs
BLD-Conference3/19/20073/20/20073/20/2007PNH
DetailsTony Young
Dan; Phone #: ###-#### Internet Inspection Request from: Stacie Backus
will re-schedule
BLD-Framing/Rough-in2/16/20072/20/20072/20/2007APART
DetailsTony Young
dan; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
ok to cover east side and atrium area
BLD-Energy code compliance1/26/20071/26/20071/26/2007PPART
DetailsJim Sly
dan; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
OK to cover select walls......All walls S. of rotunda....Mech rm bathrooms Etc.
BLD-Framing/Rough-in1/16/20071/17/20071/17/2007APART
DetailsTony Young
jessica; Phone #: ###-#### Internet Inspection Request from: Darla Downs
brick ties ok
FIRE-Conference1/8/20071/8/20071/8/2007PDONE
DetailsTroy Cobbley
Dan and I went over fire extinguisher locations
BLD-Other1/4/20071/4/20071/4/2007PPART
DetailsTony Young
dan- note: shear ; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
plywood on rear ok to cover
BLD-Wall cover1/2/20071/3/20071/4/2007APART
DetailsTony Young
Dan, trash enclosure rebar inspection; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt
exterior plywood ok per RFI and attachment to steel studs ok per letter from structural engineer
BLD-Other1/2/20071/3/20071/3/2007APART
DetailsTony Young
Dan, trash enclosure rebar inspection; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt
vert. rebar is in place for masonary
BLD - Request for Extension12/28/200612/28/200612/28/2006 PASS
DetailsTony Young
###-#### - jessica Note: not ready shooting for May!!!
(F) Reprint permit  12/28/2006 DONE
Override - Parcel Holds  12/28/2006  
(F) Reprint permit  12/26/2006 DONE
Plan assigned to (JCM)9/7/20069/7/200612/21/2006 PASS
12/21/2006 08:29:28 JCM - activity updated through activity BLDA022 from case BLD06-00453.
Routing - PLAN CHECK12/14/2006 12/21/2006 PASS
PLANS/APPL TAKEN TO FRONT DESK  12/21/2006 DONE
Inspection Record Card- Bld  12/21/2006 DONE
Telephone call  12/21/2006 DONE
lft ms for bruce poe that permit and fees are ready to be picked up for modification
Telephone call  12/21/2006 DONE
lft ms with secretary that permit and fees are ready to be picked upo for mod
Override - Parcel Holds  12/21/2006  
Permit Ready to Issue  12/21/2006 DONE
BLD-Framing/Rough-in12/12/200612/13/200612/14/2006APART
DetailsTony Young
Dan,, roof steel; Phone #: ###-####
wip.. ok to keep going,, special inspection on the welding,, pending reports
Routing - PLANNING12/12/2006 12/13/2006 PASS
Approved per DRH05-00311 MOD #3
BLD-Framing/Rough-in12/12/200612/12/200612/12/2006PCANC
DetailsTony Young
structural steel or roof deck inspection please/// ###-#### dan
Override - Parcel Holds  12/12/2006  
Override - Parcel Holds  12/12/2006  
Plan Reviewer's activity  12/7/2006 DONE
Removed parcel tag to allow framing inspection after receiving floodplain elevation and okay to remove from Jim Wyllie. JCM
Routing - PLANNING9/11/2006 9/12/2006 FAIL
Applicant must apply for Design Review Modification for any exterior changes.
Routing - PLUMBING9/8/2006 9/11/2006 PASS
detail a page p1.1 water sizing to 3 toilets and a urinal is too small. r.p. required on water to the garden center.
Routing - PLAN CHECK9/7/2006 9/8/2006  
Plan Modification Accepted  9/7/2006  
plan modification accepted for bld06-00453 & 454 for the redesign on sheets a2.0, A7.0, Mp0.0, P0.1, P1.1, M0.1, M1.1, M1.2, M1.3A, M1.3B, M1.4, E2.P1, E2.P2-routed to john Menard
BLD-Other8/3/20068/7/20068/7/2006APART
DetailsTony Young
dan - rebar insp for stem wall; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley
pending s. i. report
BLD-Other8/2/20068/3/20068/3/2006APART
DetailsTony Young
dan - call prior to re-bar insp; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley
met w/ s. i.,, ok pending report,, also asked Dan to call all insections in
Override - Parcel Holds1/1/19001/1/19008/3/2006  
Override - Parcel Holds1/1/19001/1/19008/2/2006  
BLD-Other7/20/20067/21/20067/21/2006PPART
DetailsTony Young
re-bar inspection//Dan Jafek ###-####
exterior and interior pad ftgs,, pend, s. i. report
Override - Parcel Holds  7/20/2006  
BLD-Footing7/14/20067/17/20067/17/2006PNR
DetailsMike Jordan
dan - ###-#### Note: rebar. contractor to rewshedule for tommorrow afternoon.
(F) Reprint permit  7/14/2006  
Override - Parcel Holds  7/14/2006  
Override - Parcel Holds  7/13/2006  
Issue PAID IN FULL permit  7/13/2006 DONE
CHANGE ISSUED DATE  7/13/2006 DONE
Routing - PLAN CHECK6/30/2006 7/5/2006 PASS
PLANS/APPL TAKEN TO FRONT DESK  7/5/2006 DONE
Override - Parcel Holds  7/5/2006  
Inspection Record Card- Bld  7/5/2006 DONE
Override - Parcel Holds  7/5/2006  
Permit Ready to Issue  7/5/2006 DONE
Telephone call  7/5/2006 DONE
Spoke with Jessica and told her that permit is ready & fees, also that we need GC information and the ACHD impact fees information///7/5/06 @ 2:15pm BAS
Plan assigned to (JCM)2/24/2006 7/5/2006 PASS
7/5/2006 09:02:39 JCM - activity updated through activity BLDA022 from case BLD06-00453.
Routing - PLANNING6/28/2006 6/30/2006 PASS
Approved per DRH05-00311 Modification #1
Routing - PLANNING Land Div6/27/2006 6/28/2006 PASS
Approved.
Plan Reviewer's activity  6/27/2006 PASS
Reviewed and approved final resubmittals. JCM
Routing - PLAN CHECK6/6/2006 6/27/2006 PASS
Plan resubmittals received  6/26/2006  
Recieved trasmittal letter, 2 copies of 8 1/2" x 11" site plan, two copies of the following pages: A0.0, A0.1, erosian and sediment control plan, C1.0, L1.0, L2.0, L3.0, L4.0, L5.0, L6.0, A1.0, A1.1, A2.0, A2.1, A3.0, A4.0, A4.1, A4.2, A5.0, A5.1, A5.2, A6.0, A7.0, A7.1, A8.0, A9.0, A9.1, A9.2, A10.0, A10.1, S0.1, S1.01, S1.02, S1.03, S2.01, S2.02, S2.03, S2.04, S3.01, S4.01, S5.01, S5.02, S5.03, S5.04, S5.05, S5.06, S5.07, MP0.0, P0.1, P1.1, M0.1, M1.1, M1.2, M1.3, M1.4, FP1.0, E1.0, E2.F1, E2.L1, E2.L2, E2.P1, E2.P2, E2.S1, E2.T1, E3.0; taken to John Menard
Routing - PLUMBING6/1/2006 6/6/2006 PASS
additional cross connection protection may be required.
Routing - PLANNING5/25/2006 6/1/2006 FAIL
The revisions will require review and approval of a staff-level modification to DRH05-00311. Emailed applicant at 5:00p.m. on 5/30/06. Plans routed to A. Wood for CUP compliance (AW PASSED IN APRIL). CER.
Telephone call  5/31/2006 DONE
Spoke with architect regarding installation delay of new fire hydrants. Advised architect that a formal written request must be made to the fire marshal regarding the proceeding of construction without the installed and functioning new fire hydrants. .
Plan resubmittals requested  5/25/2006 DONE
E-mailed the architect with the comment list requesting revisions related to the owner requested plan changes. JCM
Routing - PLAN CHECK3/22/2006 5/25/2006 FAIL
Plan resubmittals received  5/23/2006  
Received 1 plan review comments,2 supplemental structural calcs, & 3 copys of sheets A2-1,A2-2,A2-3,A5-1 taken to John M.
Routing Off Site - STRUCTURAL5/15/2006 5/23/2006 PASS
Called Action Couriers for pick up
Routing - PLANNING Land Div5/18/2006 5/18/2006 PEND
Still need survey drawing and verification of access road for fire protection.
Plan resubmittals received  5/12/2006  
Received 1 copy of cover transmittal letter; 1 copy of Structural calcs; 2 copies of Division 16 specifications index; 3 copies of the following sheets- A0.0, A0.1, SHEET 1 OF 1, C1.0, L1.0M, L2.0, L3.0, L4.0, L5.0, L6.0, A1.0, A1.1, A2.0, A2.1, A3.0, A4.0, A4.1, A4.2, A5.0, A5.1, A5.2, A6.0, A7.0, A7.1, A8.0, A9.0, A9.1, A9.2,M A10.0, A10.1, S0.1, S1.01, S1.02, S1.03, S2.01, S2.02, S2.03, S2.04, S3.01, S4.01, S5.01, S5.02, S5.03, S5.04, S5.05, S5.06,S5.07, MP0.0, P0.1, P1.1, M0.1, M1.1, M1.2, M1.3, M1.4, FP1.0, E1.0, E2.F1, E2.L1, E2.L2, E2.P1, E2.P2, E2.S1, E2.T1, E3.0 and taken to John M
Plan resubmittals requested  5/2/2006 DONE
E-mailed the architect a copy of the second review from the consulting structural engineer requesting additional revisions. JCM
Routing Off Site - STRUCTURAL4/21/2006 5/1/2006 FAIL
Valled Action Couriers for pick up - Received comment letter from consulting structural engineer for second review requesting addtional revisions. JCM
Plan resubmittals received  4/27/2006 DONE
Received 1letter, & 3 copys of sheets A0-1,A1-1,A4-1,A5-1,A6-1 taken to John M.
Plan resubmittals received  4/27/2006 DONE
Received 1 comments,3 comment responses, 3 copys of letter to MR. Jayo & 3 copys of sheets A0-1,A1-1,A2-0,A2-1,A2-2,A2-3,A4-1,A4-2,A5-1,A6-1A7-3 taken to John M.
Routing - PUBLIC WORKS4/20/2006 4/20/2006 PASS
Plan resubmittals received  4/20/2006 DONE
Received 1 trasnmittal,3 comment response, & 3 copys of sheets S0.1,S1.01,S1.02,S1.03,S2.03,S2.04,S4.01,S5.01,S5.02,S5.03,S5.04,S5.05,S5.06,S5.07 taken to John M.
Plan resubmittals received  4/3/2006  
Received 1 cover transmittal letter, 2 pages of CPI International, Inc-summary of danpalon test data & results, 5 pages of construction testing corporation-tests on translucent skylights panels, pages 1 of 6, 2 of 6, 3 of 6 & 6 of 6 of CPI translucent fire rated systems ans taken to John M.
Plan resubmittals requested  3/29/2006 DONE
E-mailed the achitect a copy of the comment list from the consulting structural engineer requesting revisions. JCM
Routing Off Site - STRUCTURAL3/14/2006 3/28/2006 FAIL
Called Action Couriers for pick up
Plan resubmittals requested  3/22/2006 DONE
E-mailed the architect with a copy of the plan review comment list requesting revisions. JCM
Plan Reviewer's activity  3/22/2006 DONE
Waited to receive revised plans before putting review cycle. JCM
1st review completed  3/22/2006 FAIL
Failed Plan Check and Public Works.
Routing - FIRE3/22/2006 3/22/2006 PASS
Attached review comments to plans. Faxed comments to architect.
Routing - PLAN CHECK3/8/2006 3/22/2006 FAIL
John M.
Plan resubmittals received  3/13/2006 DONE
Received 1 transmittal, 3 structural calcs, & 4 copys of sheets S0.1,S1.01,S1.02,S1.03,S2.01,S2.02,S2.03,S2.04,S3.01,S4.01,S5.01,S5.02,S5.03,S5.04,S5.05,S5.06 taken to John M.
Routing Off Site - STRUCTURAL2/24/2006 3/8/2006  
Called Action Couriers for pick up - I received a phone call from the architect indicating that there will be structural revisiosn to the original submittal. I e-mailed the consulting structural engineer to request that they do not do the structural review until they receive the revised plans and calculations. JCM
Routing - PLANNING  3/8/2006 PASS
Approved per DRH05-0311-Marty S. (3/2/06)

Routed to Angela W for compliance with CUP05-000133.
Routing - PLUMBING2/28/2006 3/2/2006 PASS
approved per plan and 2003 UPC
Routing - Erosion and Sediment2/28/2006 2/28/2006 PASS
ESC plan approved with attached conditions.
Routing - PUBLIC WORKS2/27/2006 2/28/2006 FAIL
Drainage plan does not meet standards. Finish floor elevation not in conformance with flood plain requirements, Drainage from project routed to off-pad areas. Off-pad drainage has not yet been approved. Contact Jim Wyllie ###-####
Routing - PLANNING Land Div2/24/2006 2/27/2006 PEND
Parcel is a legal parcel. Entitled to a building permit. Applicant must provide a separate survey showing new structure on the whole parcel. Building location must match setbacks proposed for Lot 23, Block 1 of 36th Street Garden Plaza Subdivision. Prior to issuance of building permit must construct access road to building site.
Recd Pcfee & Taken To Pln CK  2/24/2006 DONE
Plans ACCEPTED BY PLAN TECH  2/24/2006  
Plan routing begun/NEW & ADDTN  2/24/2006  
Application received  2/24/2006  
Code Occupancy Approval4/23/20074/23/2007 P 
Details
dan - final; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
Fee Review-notes2/24/20062/24/2006   
Routing - PLAN CHECK