Third Notice BLD | 8/18/2006 | 8/18/2006 | 3/9/2007 | | DONE |
|
|
|
Second Notice has not been responded to.
|
Fee Review-notes | 2/28/2006 | 2/28/2006 | 3/9/2007 | | DONE |
|
|
|
|
Second Notice BLD | 7/7/2006 | 7/7/2006 | 8/18/2006 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | 6/5/2006 | 6/5/2006 | 7/7/2006 | | DONE |
Dave Hannah
|
|
|
|
BLD-Final | 6/2/2006 | 6/5/2006 | 6/5/2006 | P | PASS |
Dave Hannah
|
|
|
john; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
DOC - Permit Finaled | 6/5/2006 | 6/5/2006 | 6/5/2006 | P | PASS |
Dave Hannah
|
|
|
|
FIRE-Final Inspection | 6/2/2006 | 6/5/2006 | 6/5/2006 | A | PASS |
Forrest France
|
|
|
Fire life safety passed inspection. Contractor could not provide the signature card at the time of inspection.
|
BLD-Framing/Rough-in | 4/18/2006 | 4/18/2006 | 4/19/2006 | P | PASS |
Dave Hannah
|
|
|
John; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong ok to cover after plumb r/i
|
Issue PAID IN FULL permit | | | 4/5/2006 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 3/29/2006 | | 3/30/2006 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/30/2006 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/30/2006 | | |
|
|
|
|
Permit Ready to Issue | | | 3/30/2006 | | DONE |
|
|
|
|
Telephone call | | | 3/30/2006 | | DONE |
|
|
|
called ###-#### and told Matt that permit is ready, fees, and need GC and RCE
|
Plan assigned to (CJW) | 3/2/2006 | | 3/30/2006 | | PASS |
|
|
|
3/30/2006 13:20:17 CJW - activity updated through activity BLDA022 from case BLD06-00473.
|
Routing - FIRE | 3/28/2006 | | 3/29/2006 | | PASS |
|
|
|
Attached review comments to plans. Faxed review comments to architect.
|
1st review completed | | | 3/29/2006 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 3/3/2006 | | 3/28/2006 | | PASS |
|
|
|
Drawings approved.
|
Plan Reviewer's activity | | | 3/17/2006 | | DONE |
|
|
|
(3-17-06) Requested an interpretation from the Building Division Manager about the location and access to restrooms. Direction is needed before a decision can be made. CJW (3-27-06) Written interpretation issued. CJW
|
Routing - PUBLIC WORKS | 3/2/2006 | | 3/3/2006 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/1/2006 | | |
|
|
|
|
Application received | | | 2/28/2006 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/28/2006 | | |
|
|
|
|